EXECUTIVE SUMMARY

Introduction

1.              This is the 23rd monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in December 2014.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

1st, 5th, 11th, 17th, 23rd and 29th December 2014.

24-hr TSP Monitoring

1st, 5th, 11th, 17th, 23rd and 29th December 2014.

Noise Monitoring

2nd , 8th , 18th, 24th and 30th December 2014

Water Quality Monitoring

1st, 3rd, 5th, 8th, 10th, 12th, 15th, 17th , 20th, 22nd, 24th, 27th, 29th and 31st December 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

3rd  and 10th December 2014

Additional Land-based Dolphin Behaviour and Movement Monitoring

5th  and 18th December 2014

Environmental Site Inspection

2nd, 9th, 16th, 23rd and 30th December 2014

Archaeological Site Inspection

30th December 2014


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

1

1

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are one Action Level and one Limit Level exceedances for suspended solids were recorded. No Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.

 

8.              According to the investigation, the exceedances are considered not due to the Contract as sediment plume discharging to the monitoring stations from the area outside the site boundary was observed and the exceeded result was within the ranges baseline monitoring results.

Complaint Log

 

9.              Three environmental complaints were received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

 

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

 

Marine Viaduct (P0 to P80)

Reverse Circulation Drill (RCD) Method:

Ÿ   Excavation works and concreting of piles

Ÿ   Interface core, sonic testing and grouting works for piling works

 

Kelly Method:

Ÿ   Piling platform removal and temporary pile extraction

Ÿ   Interface coring, sonic testing and grouting works

 

 

Pile Cap, Column and Portal Construction:

Ÿ   Pile cap construction

Ÿ   Pier stem and pier head construction

Ÿ   Precast column erection

Ÿ   Preparation works for Segments on Pier (SOP) installation

Ÿ   Construction of double blade column

Ÿ   Commence falsework of the Portal

Ÿ   Commence construction of Portal

 

 

Deck Erection:

Ÿ   Complete stitch concrete works

 

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

Ÿ   Piling works

Ÿ   Pre-bored for sheet pile for cofferdam construction

Ÿ   Pile head excavation / trimming

Ÿ   Column construction

Ÿ   Backfilling and remove ELS

Ÿ   Portals construction works

Ÿ   Dismantling of falsework system for Portals

Ÿ   Erection of steel bracket and falsework system for Portals

Ÿ   Installation of temporary jacks and nailing and removal of falsework system