This is the 23rd monthly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project
“Contract No. HY/2011/09 – Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary
and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in December
2014.
Environmental Monitoring
and Audit Progress
2.
A summary of the monitoring activities in this reporting month is listed
in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
1st, 5th, 11th, 17th,
23rd and 29th December 2014. |
24-hr TSP Monitoring |
1st, 5th, 11th,
17th, 23rd and 29th December 2014. |
Noise Monitoring |
2nd , 8th , 18th,
24th and 30th December 2014 |
Water Quality Monitoring |
1st, 3rd, 5th, 8th,
10th, 12th, 15th, 17th , 20th,
22nd, 24th, 27th, 29th and 31st
December 2014 |
3rd and 10th December 2014 |
|
Additional Land-based
Dolphin Behaviour and Movement Monitoring |
5th and 18th December 2014 |
Environmental Site
Inspection |
2nd, 9th, 16th,
23rd and 30th December 2014 |
Archaeological Site
Inspection |
30th December 2014 |
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of the reporting month is
tabulated in Table II.
Table II Summary
Table for Events Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Exceedance |
No. of Exceedance related to the Construction Activities of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
1 |
1 |
0 |
0 |
1-hour
TSP Monitoring
4.
All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour
TSP Monitoring
5.
All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
Construction
Noise
6.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was recorded.
Water Quality
7.
All water quality monitoring was conducted as scheduled in the reporting
month. There are one Action Level and one Limit Level exceedances for suspended
solids were recorded. No Action/Limit Level exceedance for dissolved oxygen and
turbidity were recorded.
8.
According to the investigation, the exceedances are considered not due
to the Contract as sediment plume
discharging to the monitoring stations from the area outside the site boundary
was observed and the exceeded result was within the ranges baseline monitoring
results.
Complaint Log
9.
Three environmental complaints were received in the reporting month.
Notification of
Summons and Successful Prosecutions
10.
No notification of summons and successful prosecution was received in
the reporting month.
11.
This report has been developed in compliance with the reporting
requirements for the subsequent monthly EM&A Report as required by the
EM&A Manual for Hong Kong Link Road (EM&A Manual).
12.
Major site activities for
the coming reporting month will include:
WA4
Fabrication of rebar cages
Fabrication of temporary piling platforms
WA7
Fabrication of rebar cages
Loading and Unloading of rebar materials
Marine
Viaduct (P0 to P80)
Reverse
Circulation Drill (RCD) Method:
Excavation works and concreting of piles
Interface core, sonic testing and grouting
works for piling works
Kelly
Method:
Piling platform removal and temporary pile
extraction
Interface coring, sonic testing and
grouting works
Pile
Cap, Column and Portal Construction:
Pile cap construction
Pier stem and pier head construction
Precast column erection
Preparation works for Segments on Pier (SOP) installation
Construction of double blade column
Commence falsework
of the Portal
Commence construction of Portal
Deck
Erection:
Complete stitch concrete works
Land
Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
Piling works
Pre-bored for sheet pile for cofferdam
construction
Pile head excavation / trimming
Column construction
Backfilling and remove ELS
Portals construction works
Dismantling of falsework
system for Portals
Erection of steel bracket and falsework system for Portals
Installation of temporary jacks and
nailing and removal of falsework system