2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department
as the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P82 to P83 and 3 piles were
concreted in this reporting period.
(b) Total 147 pours
for column were completed with 8 pours
in this reporting period; 54 columns
were completed to top level (26
gridlines – P88, P90 to P114.
(c) Pilecap P84L and P84R was completed.
(d) Pre-bored for sheet pile for
cofferdam construction at P81R & L in progress.
(e) Sewage diversion at P83 is in
progress.
(f) P83L piling work is in progress.
(g) P82L piling work was completed.
(h) Portal P107 dismantling of falsework and steel girder system was completed on 15
December 2014.
(i) Portal P106 falsework
dismantling is in progress.
(j) Portal P95 erection of steel
cross beams and planking at P95R is in progress.
(k) Portal P108 dismantling of falsework and steel bracket system was completed.
(l) Portal P114 installation of
temporary supports and temporary jacks are in progress.
(m) Portal P102 was concreted on 29
November 2014 and removal of falsework is in progress.
(n) Portal P101 was cast on 9
December 2014 and removal of formwork is in progress.
(o) Portal P97 was concreted on 17
December 2014 and removal of side formwork was in progress.
(p) Portal P98 erection of side
formwork is in progress.
(q) Portal P100 steel fixing is in
progress.
(r) Portal P99 erection formwork is
in progress.
(s) Portal P96 erection of falsework and planking are in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Construction
works at P68 and P69 may be resumed on 23 December 2014.
(b) Remobilization for P75’s works started on 25 September 2014. Excavation
by backhoe on flat top barge is on-going and steel boxes are under construction
at WA7.
(c) Piling jackets were installed at D18 & P8.
(d) Piling
jackets were dismantled at D17 & D20.
(e) Pile
excavations and casing installation are in progress at P5, P10 & D18 with 6
nos. piles concreted in the reporting period.
(f) Inter-face
coring tests were carried out at P15, P23, P24 &
P80.
(g) Full depth
coring test was carried at P24.
(h) Sonic tests were carried out at P15, P23, P55
& P80.
(i) Grouting works were carried out at P23, P24, P25
& P31.
Kelly Method:
(k) Piling platform removal and temporary pile extraction were carried
out at P3, P4, P21 & P31.
(l) Pile excavation by Kelly method are in progress at P2, & P7 and
4 piles concreted in the reporting period.
(m) All
friction piles by Kelly Method were completed.
(n) All inter-face
core tests were completed.
(o) Full depth coring was carried out at P12-R3.
(p) Sonic tests were
carried out at P1, P2, P7 & P12.
(q) Toe grouting works were carried out at P1,
P2, P3 & P7.
Disposal from
Marine Works
(a)
The disposals in this reporting
period are shown in below table.
Disposal Location |
No of Trip |
Type of Materials |
TM38 |
2 |
Inert Materials |
TMCLK |
0 |
Inert Materials |
HK Open Sea Mud Pits |
3 |
Type II Materials |
Cross Boundary Disposal |
4 |
Marine Mud |
Pilecap
Construction:
(a) 10 precast cap shells were installed P14, P16, P30, P32
& P59.
(b) Stage 1 concreting was completed
at P27, P28, P30, P32 & P59.
(c) Stage 1
works is in progress at P14, P16, P27, P28, P30, P32
& P52.
(d) Stage 2 concreting was completed
at P27, P28, P29, P67.
(e) Stage 2
works is in progress at P27, P28, P29, P32, P67.
(f) Kingpost installation and associated steel welding works for precast
shell installation are in progress at P14, P16, P21, P30, P31
& P53.
(g) Concrete trimming and advanced
trimming (inside casing) works were carried out at P16, P21, P24, P25, P27,
P28, P31, P53, P58 & P59.
Pier Location |
Side |
Progress |
P70 |
L |
Formwork installation for pile
cap is in progress; |
R |
Formwork installation for pile
cap completed; Re-bar steel fixing is in
progress. |
|
P71 |
L |
Concreting works of pile cap
completed on 6-Oct-14 |
R |
Concreting works of pile cap
completed on 18-Dec-14 |
|
P72 |
L |
Concrete plug was casted on
24-Dec-14; Curing is in progress. |
R |
Installation of 3rd layer of
waling & strut completed; Dewatering to the bottom of
cofferdam is in progress. |
|
P73 |
L |
Concreting works of pile cap
completed on 4-Dec-14 |
R |
Formwork installation for pile
cap completed; Re-bar steel fixing is in
progress. |
|
P74 |
L |
Excavation works in progress |
R |
Excavation works in progress |
|
P76 |
L |
Installation of 1st
& 2nd waling & strut completed; Installation of 3rd
waling & strut is in progress. |
R |
Installation of 1st
& 2nd waling & strut completed; Excavation works to be
started. |
|
P77 |
L |
Installation of 1st
& 2nd waling & strut completed; Excavation works is in
progress. |
R |
Installation of 1st
& 2nd waling & strut completed; Installation of 3rd
waling & strut to be started. |
|
P78 |
L |
Installation of 3rd
waling & strut completed; Cleaning & drainage works
is in progress. |
R |
Concrete plug was casted on
17-Dec-14; Installation of 3rd
waling & strut to be started. |
In-situ Column
Construction
(a) 1st lift works is in progress at P33, P34, P50, P61, P63 & P64.
(b) 1st lift concrete was poured at P33, P34, P50
& P64.
(c) 2nd lift works is in progress : P50.
(d) 2nd lift concreting was poured: N/A.
(e) Pier head works is in progress at: P49, P51, P60, P65
& P66.
(f) Pier head concreting in progress at P49, P60 & P66.
Precast Column
Erection
(g) P37 and P38 – base units installed.
(h) P39 to P41 – all units installed.
(i) P43 to P44 – all units installed.
In-situ Double Blade
Column Construction
Pier Location |
Side |
Progress |
P19 |
L |
1st
lift works in progress |
R |
1st lift
works in progress |
|
P20 |
L |
completed
3rd lift and 4th lift works in progress |
R |
completed
2nd lift and 3rd lift works in progress |
|
P71 |
L |
completed
1st lift and 2nd lift works in progress |
R |
Column
works to be started by end of December |
Marine Portal
(a) Portal construction at P52 commence on 11 Dec 2014. Temporary barrier
piles were driven at the location for safety measures.
Deck Erection
(a)
Setting up of Equipment:
Type of Equipment |
Status |
Segment Unloading Frame
(SUF) |
Fully
operational |
Lifting Frames 1 (LF1) |
Assembly
of the first set of LF1 is on-going at WA4 but is still hampered by lack of
available area; Steelwork
for the 4th set of Lifting Frames is under fabrication with some
deliveries commenced; |
Lifting Frames 2 (LF2) |
LF2 at
P109-P110 L & R have now been removed and preliminary works are underway
in preparation to erect P109 span by crane. |
Launching Gantry 1 (LG1) |
LG1
assembly continues at Portion C with all components on site; LCB’s
and all main truss elements erected (with the exception of the link trusses). |
Launching Gantry 2 (LG2) |
Assembly
of truss has commenced with main elements lifted on to pile-caps at P47/P46.
Further erection will be continued after completion of in-situ SOP works. |
- A total of 22 segments have been erected to
date with P45 SOP and one of P46 segments delivered to site and off-loaded into
temporary storage on a “flat-top” barge during this reporting period.
Precast Segment
(a) Progress
for mould assembly:
Type of Segment |
Number of Mould |
Status |
A |
10 |
Completed (including 2
nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH1 |
2 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
2 |
Completed |
CP (long span SOP) |
4 |
Completed (2 x CPA and 2
x CPB) |
DT |
1 |
Completed |
E/EV |
2 |
Completed |
(b)
Segment Casting and Delivery
Item |
Number in this reporting period |
Cumulative No. of Precast Shell Completed (up to 28th of each month) |
Segment Cast |
215 |
1601 |
Segment Delivered |
4 |
80 |
(c)
Off-site Storage:
Area |
No. in Off-site Storage |
A1 |
134 |
A2 |
240 |
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of Shell |
Number of
Precast Shell Cast in this reporting period |
Cumulative No.
of Precast Shell Completed (up to 28th of each month) |
CP1 |
5 |
61 |
CP2 |
Completed |
12 |
CP3 |
2 |
4 |
CP4 |
Completed |
8 |
CP5 |
2 |
6 |
CP6 |
2 |
2 |
Precast Column &
Precast Pier Head Casting
(a)
Progress of the precast column & precast pier
head casting:
- All the 5 moulds
are in service for precast production;
- Totally
21 precast elements (14 piers with 6m high, 4 monolithic pier heads and 3 pier
heads supporting bearings) were cast in this reporting period.
- Cumulatively 93
precast elements have been produced.
(b)
Delivery Progress:
Item |
No. of units delivered in this reporting
period |
Cumulative No |
Segment Delivered |
12 (3 trips) |
32 (8 trips) |
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
WA4:
GW-RW0496-14 |
10/07/2014 (19:00) |
01/01/2015 (23:00) |
Cancelled
on 15 December 2014 |
WA7: GW-RW0509-14 |
14/07/2014 (19:00) |
13/01/2015 (07:00) |
Valid |
Portion A: GW-RW0838-14 |
23/08/2014 (19:00) |
22/02/2015 (23:00) |
Valid |
P101 – P113: GW-RS0903-14 |
05/09/2014 (19:00) |
04/12/2014 (05:30) |
Expired |
P81 – P82: GW-RS1064-14 |
11/10/2014 (00:00) |
10/04/2015 (24:00) |
Valid |
P0 – P68: GW-RS1163-14 |
23/10/2014 (19:00) |
22/01/2015 (24:00) |
Valid |
P75 – P80: GW-RS1179-14 |
01/11/2014(19:00) |
31/01/2015(24:00) |
Cancelled
on 22 December 2014 |
P81 – P114: GW-RS1250-14 |
06/11/2014(19:00) |
05/02/2015(23:00) |
Valid |
P101 – P113: GW-RS1297-14 |
21/11/2014(19:00) |
31/03/2015 (06:30) |
Valid |
P69 – P74: GW-RS1340-14 |
30/11/2014 (00:00) |
31/03/2015(24:00) |
Valid |
P101 – P113: GW-RS1372-14 |
08/12/2014(19:00) |
31/01/2015(05:30) |
Valid |
WA4: GW-RW0984-14 |
15/12/2014(19:00) |
14/06/2015(23:00) |
Valid |
P75 –
P80 :GW-RS1421-14 |
22/12/2014(19:00) |
31/03/2015(24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
A/C# 7016948 (Vessel Disposal) |
18/11/2014 |
28/02/2015 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C:
WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7:
WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1-Open Sea Disposal) marine sediment EP/MD/15-078 |
06/08/2014 |
31/01/2015 |
Valid |
Cross-border
dumping of dredged sediment of Category L and Category Mp
at Erchau Island in China EP/MD/15-143 |
10/11/2014 |
09/12/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1D and Type 2) marine
sediment EP/MD/15-163 |
01/12/2014 |
31/12/2014 |
Valid |
Cross-border
dumping of dredged sediment of Category L and Category Mp
at Erchau Island in China EP/MD/15-170 |
10/12/2014 |
09/01/2015 |
Valid |