2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      Pile construction is in progress at P82 to P83 and 3 piles were concreted in this reporting period.

(b)     Total 147 pours for column were completed with 8 pours in this reporting period; 54 columns were completed to top level (26 gridlines – P88, P90 to P114.

(c)      Pilecap P84L and P84R was completed.

(d)     Pre-bored for sheet pile for cofferdam construction at P81R & L in progress.

(e)      Sewage diversion at P83 is in progress.

(f)      P83L piling work is in progress.

(g)     P82L piling work was completed.

(h)     Portal P107 dismantling of falsework and steel girder system was completed on 15 December 2014.

(i)       Portal P106  falsework dismantling is in progress.

(j)       Portal P95 erection of steel cross beams and planking at P95R is in progress.

(k)     Portal P108 dismantling of falsework and steel bracket system was completed.

(l)       Portal P114 installation of temporary supports and temporary jacks are in progress.

(m)   Portal P102 was concreted on 29 November 2014 and removal of falsework is in progress.

(n)     Portal P101 was cast on 9 December 2014 and removal of formwork is in progress.

(o)     Portal P97 was concreted on 17 December 2014 and removal of side formwork was in progress.

(p)     Portal P98 erection of side formwork is in progress.

(q)     Portal P100 steel fixing is in progress.

(r)       Portal P99 erection formwork is in progress.

(s)      Portal P96 erection of falsework and planking are in progress.


Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction works at P68 and P69 may be resumed on 23 December 2014.

(b) Remobilization for P75’s works started on 25 September 2014. Excavation by backhoe on flat top barge is on-going and steel boxes are under construction at WA7.

(c) Piling jackets were installed at D18 & P8.

(d)  Piling jackets were dismantled at D17 & D20.

(e)  Pile excavations and casing installation are in progress at P5, P10 & D18 with 6 nos. piles concreted in the reporting period.

(f)  Inter-face coring tests were carried out at P15, P23, P24 & P80.

(g)  Full depth coring test was carried at P24.

(h)        Sonic tests were carried out at P15, P23, P55 & P80.

(i)    Grouting works were carried out at P23, P24, P25 & P31.

 

Kelly Method:

(k) Piling platform removal and temporary pile extraction were carried out at P3, P4, P21 & P31.

(l)         Pile excavation by Kelly method are in progress at P2, & P7 and 4 piles concreted in the reporting period.

(m)        All friction piles by Kelly Method were completed.

(n)  All inter-face core tests were completed.

(o) Full depth coring was carried out at P12-R3.

(p)  Sonic tests were carried out at P1, P2, P7 & P12.

(q) Toe grouting works were carried out at P1, P2, P3 & P7.

Disposal from Marine Works

(a)    The disposals in this reporting period are shown in below table.

Disposal Location

No of Trip

Type of Materials

TM38

2

Inert Materials

TMCLK

0

Inert Materials

HK Open Sea Mud Pits

3

Type II Materials

Cross Boundary Disposal

4

Marine Mud

 

Pilecap Construction:

(a)  10 precast cap shells were installed P14, P16, P30, P32 & P59.

(b)   Stage 1 concreting was completed at P27, P28, P30, P32 & P59.

(c)  Stage 1 works is in progress at P14, P16, P27, P28, P30, P32 & P52.

(d) Stage 2 concreting was completed at P27, P28, P29, P67.

(e)  Stage 2 works is in progress at P27, P28, P29, P32, P67.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P14, P16, P21, P30, P31 & P53.

(g) Concrete trimming and advanced trimming (inside casing) works were carried out at P16, P21, P24, P25, P27, P28, P31, P53, P58 & P59.

(h)  Submerged pilecap works with cofferdam:

 

Pier Location

Side

Progress

P70

L

Formwork installation for pile cap is in progress;

R

Formwork installation for pile cap completed;

Re-bar steel fixing is in progress.

P71

L

Concreting works of pile cap completed on 6-Oct-14

R

Concreting works of pile cap completed on 18-Dec-14

P72

L

Concrete plug was casted on 24-Dec-14;

Curing is in progress.

R

Installation of 3rd layer of waling & strut completed;

Dewatering to the bottom of cofferdam is in progress.

P73

L

Concreting works of pile cap completed on 4-Dec-14

R

Formwork installation for pile cap completed;

Re-bar steel fixing is in progress.

P74

L

Excavation works in progress

R

Excavation works in progress

P76

L

Installation of 1st & 2nd waling & strut completed;

Installation of 3rd waling & strut is in progress.

R

Installation of 1st & 2nd waling & strut completed;

Excavation works to be started.

P77

L

Installation of 1st & 2nd waling & strut completed;

Excavation works is in progress.

R

Installation of 1st & 2nd waling & strut completed;

Installation of 3rd waling & strut to be started.

P78

L

Installation of 3rd waling & strut completed;

Cleaning & drainage works is in progress.

R

Concrete plug was casted on 17-Dec-14;

Installation of 3rd waling & strut to be started.

 

In-situ Column Construction

(a)    1st lift works is in progress at P33, P34, P50, P61, P63 & P64.

(b)   1st lift concrete was poured at P33, P34, P50 & P64.

(c)    2nd lift works is in progress :  P50.

(d)   2nd lift concreting was poured: N/A.

(e)    Pier head works is in progress at: P49, P51, P60, P65 & P66.

(f)    Pier head concreting in progress at P49, P60 & P66.

 

Precast Column Erection

(g)   P37 and P38 – base units installed.

(h)   P39 to P41 – all units installed.

(i)     P43 to P44 – all units installed.

 

In-situ Double Blade Column Construction

 

Pier Location

Side

Progress

P19

 

L

1st lift works in progress

R

1st lift works in progress

P20

 

L

completed 3rd lift and 4th lift works in progress

R

completed 2nd lift and 3rd lift works in progress

P71

 

L

completed 1st lift and 2nd lift works in progress

R

Column works to be started by end of December

 

Marine Portal

(a)    Portal construction at P52 commence on 11 Dec 2014. Temporary barrier piles were driven at the location for safety measures.

 

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

Segment Unloading Frame (SUF)

Fully operational

Lifting Frames 1 (LF1)

Assembly of the first set of LF1 is on-going at WA4 but is still hampered by lack of available area;

 

Steelwork for the 4th set of Lifting Frames is under fabrication with some deliveries commenced;

Lifting Frames 2 (LF2)

LF2 at P109-P110 L & R have now been removed and preliminary works are underway in preparation to erect P109 span by crane.

 

Launching Gantry 1 (LG1)

LG1 assembly continues at Portion C with all components on site;

LCB’s and all main truss elements erected (with the exception of the link trusses).

 

Launching Gantry 2 (LG2)

Assembly of truss has commenced with main elements lifted on to pile-caps at P47/P46. Further erection will be continued after completion of in-situ SOP works.

-        A total of 22 segments have been erected to date with P45 SOP and one of P46 segments delivered to site and off-loaded into temporary storage on a “flat-top” barge during this reporting period.

Precast Segment

(a)      Progress for mould assembly:

Type of Segment

Number of Mould

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH1

2

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

2

Completed

CP (long span SOP)

4

Completed (2 x CPA and 2 x CPB)

DT

1

Completed

E/EV

2

Completed

 

(b)     Segment Casting and Delivery

Item

Number in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

Segment Cast

215

1601

Segment Delivered

4

80

 

(c)      Off-site Storage:

Area

No. in Off-site Storage

A1

134

A2

240

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

5

61

CP2

Completed

12

CP3

2

4

CP4

Completed

8

CP5

2

6

CP6

2

2

 

Precast Column & Precast Pier Head Casting

(a)      Progress of the precast column & precast pier head casting:

-     All the 5 moulds are in service for precast production;

-      Totally 21 precast elements (14 piers with 6m high, 4 monolithic pier heads and 3 pier heads supporting bearings) were cast in this reporting period. 

-      Cumulatively 93 precast elements have been produced.

(b)     Delivery Progress:

Item

No. of units delivered in this reporting period

Cumulative No

 

Segment Delivered

12 (3 trips)

32 (8 trips)


Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/D

22/12/2014

N/A

Valid

Consruction Noise Permit (CNP)

WA4: GW-RW0496-14 

10/07/2014 (19:00)

01/01/2015 (23:00)

Cancelled on 15 December 2014

WA7: GW-RW0509-14

14/07/2014 (19:00)

13/01/2015 (07:00)

Valid

Portion A: GW-RW0838-14

23/08/2014 (19:00)

22/02/2015 (23:00)

Valid

P101 – P113: GW-RS0903-14

05/09/2014 (19:00)

04/12/2014 (05:30)

Expired

P81 – P82: GW-RS1064-14

11/10/2014 (00:00)

10/04/2015 (24:00)

Valid

P0 – P68: GW-RS1163-14

23/10/2014 (19:00)

22/01/2015 (24:00)

Valid

P75 – P80: GW-RS1179-14       

01/11/2014(19:00)

31/01/2015(24:00)

Cancelled on 22 December 2014

P81 – P114: GW-RS1250-14

06/11/2014(19:00)

05/02/2015(23:00)

Valid

P101 – P113: GW-RS1297-14

21/11/2014(19:00)

31/03/2015 (06:30)

Valid

P69 – P74: GW-RS1340-14

30/11/2014 (00:00)

31/03/2015(24:00)

Valid

P101 – P113: GW-RS1372-14

08/12/2014(19:00)

31/01/2015(05:30)

Valid

WA4: GW-RW0984-14

15/12/2014(19:00)

14/06/2015(23:00)

Valid

P75 – P80 :GW-RS1421-14

22/12/2014(19:00)

31/03/2015(24:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

18/11/2014

28/02/2015

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/15-078

06/08/2014

31/01/2015

Valid

Cross-border dumping of dredged sediment of Category L and Category Mp at Erchau Island in China

EP/MD/15-143

10/11/2014

09/12/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2)  marine sediment

EP/MD/15-163

01/12/2014

31/12/2014

Valid

Cross-border dumping of dredged sediment of Category L and Category Mp at Erchau Island in China

EP/MD/15-170

10/12/2014

09/01/2015

Valid