Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

08/01/2015

Provide mitigation measures to prevent runoff from site discharging to public road (near P106).

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

08/01/2015

Properly deploy the silt curtain at P91.

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

08/01/2015

Clear the floating rubbish at P82.

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

30/01/2015

Clear the excess rockfill materials at the deck of barge at P68.

Rectification/improvement was observed during the follow-up audit session on 3 February 2015.

30/01/2015

Properly deploy the silt curtain to avoid the gap at P71.

Rectification/improvement was observed during the follow-up audit session on 3 February 2015.

Ecology

08/01/2015

Clear the construction materials / wastes at near the trees at P113, P107, P96 and P95.

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

Air Quality

08/01/2015

Provide water spray for the dry exposed area at near P109.

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

Noise

19/01/2015

Provide acoustic decoupling measures for the power pack at the barge at P52.

Rectification/improvement was observed during the follow-up audit session on 30 January 2015.

19/01/2015

Properly check and repair the noise enclosure at P71 to ensure it comply with Construction Noise Permit.

Rectification/improvement was observed during the follow-up audit session on 3 February 2015.

Waste / Chemical Management

08/01/2015

Provide drip tray for the oil containers and generator at near P108.

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

08/01/2015

Clear the accumulated wastes regularly at P96.

Rectification/improvement was observed during the follow-up audit session on 13 January 2015.

13/01/2015

Oil spillage was observed at the platform at P73. The Contractor was reminded to clear the leaked oil as soon as possible.

Rectification/improvement was observed during the follow-up audit session on 19 January 2015.

13/01/2015

Provide spill kit at the platform at P73.

Rectification/improvement was observed during the follow-up audit session on 19 January 2015.

19/01/2015

Clear the oil spillage at near the power pack at Portion A. (P82)

Rectification/improvement was observed during the follow-up audit session on 30 January 2015.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark:       N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.