2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
*Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
Dr. Priscilla Choy |
2151 2089 |
Remark: * A notification
letter was issued to EPD by SOR on 11 February 2015 regarding the change of
Environmental Team Leader (ETL) under Contract No. HY/2011/09 from Dr. H.F Chan to Dr. Priscilla
Choy is effective starting from 16 February 2015.
2.8
ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department
as the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P83 and 2 piles were concreted in this reporting
period.
(b) Total 161 pours
for column were completed with 3 pours in this reporting period; 59 columns were completed to top level (28 gridlines - P87 to P114).
(c) Backfilling work and sheetpile removal work of P84L&R are completed.
(d) Pre-bored for sheet pile at P81R
& L are completed, excavation work in progress.
(e) Sewage diversion at P82 is in
progress.
(f) P83L piling work is in progress.
(g) P83R pile cap excavation work is
in progress.
(h) Portal P95 erection of formwork
completed, steel fixing is in progress.
(i) Portal P96 was concreted on 11
February 2015, removal of formwork is in progress.
(j) Portal P97 dismantling of steel
brackets system was completed.
(k) Portal P114 Removal of remaining falsework resumed on 27 January 2015 and it was completed
in early February 2015.
(l) Portal P101 removal of steel
bracket system is in progress.
(m) Portal P98 was concreted on 23
January 2015, removal of soffit formwork & falsework
is in progress.
(n) Portal P100 removal of falsework is in progress.
(o) Portal P99 was concreted on 4
February 2015, removal of formwork is in progress.
(p) Portal P94 erection of vertical
formwork and wing slab scaffold are in progress.
(q) Portal P93 erection of soffit is
in progress.
(r) Portal P92 foundation work for falsework was completed.
(s) Portal P88 erection of planking
above steel bracket was completed, erection of falsework
is in progress.
(t) Portal P87 backfilling temporary
platform for steel bracket erection is in progress;
(u) Construction of drainage work
near P115 Abutment is almost completed, except installation of manhole covers;
and
(v) Excavation work and construction
of temporary foundations for P114 segment temporary supports is in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Piling
jackets were installed at D18-R2A side.
(b) Piling jackets were dismantled at P6 & P10.
(c) Pile excavations and casing installation are in progress at P26-L3A and
D18-R2A with 9nos. piles concreted in the reporting period.
(d) Inter-face
coring tests were carried out at P10, P11 & P13.
(e) No Full
depth coring test was carried.
(f) Sonic tests
were carried out at P5, P10 & P57.
(g) Grouting
works were carried out at P13 & P15.
Kelly Method:
(h) Piling platform removal and temporary pile extraction were carried
out at P2, P7 & P12.
(i) All pile testing and toe grout works were completed.
Disposal from
Marine Works
(a)
The disposals in this reporting
period are shown in below table.
Disposal Location |
No of Trip |
Type of Materials |
TM38 |
2 |
Inert Materials |
TMCLK |
0 |
Inert Materials |
HK Open Sea Mud Pits |
0 |
Types II Marine Mud |
Cross Boundary Disposal |
6 |
Type I Marine Mud |
Pilecap
Construction:
(a) 10 precast cap shells were installed P3, P4, P17, P22
& P23.
(b) Stage 1 concreting was completed
at P2, P4, P24, P25 & P53R.
(c) Stage 1
works is in progress at P3, P4, P17, P24, P25 &
P53R.
(d) Stage 2 concreting was completed
at P21, P24, P31 & P53.
(e) Stage 2
works is in progress at P3, P25, P21, P24, P31 &
P53.
(f) Kingpost installation and associated steel welding works for precast
shell installation are in progress at P1, P12, P22
& P23.
(g) Concrete trimming and advanced
trimming (inside casing) works were carried out at P1, P7, P12, P15, P17, P22,
P54, P79 & P80.
Pier Location |
Side |
Progress |
P70 |
L |
Concreting works of pile cap
completed on 13-Jan-15 |
R |
Concreting works of pile cap
completed on 5-Jan-15 |
|
P71 |
L |
Concreting works of pile cap
completed on 6-Oct-14 |
R |
Concreting works of pile cap
completed on 18-Dec-14 |
|
P72 |
L |
Trimming of pile head concrete
completed; Installation of formworks for
pile cap is in progress |
R |
Concreting works of pile cap
completed on 31-Jan-15 |
|
P73 |
L |
Concreting works of pile cap
completed on 4-Dec-14 |
R |
Concreting works of pile cap
completed on 3-Jan-15 |
|
P74 |
L |
Excavation works is in
progress |
R |
Excavation works is in
progress |
|
P76 |
L |
Excavation works is in
progress |
R |
Excavation works is in
progress |
|
P77 |
L |
Trimming of pile head concrete
is in progress |
R |
Concreting works of plug
completed on 13-Feb-15; Dewatering to be started |
|
P78 |
L |
Concreting works of pile cap
completed on 24-Jan-15 |
R |
Concreting works of pile cap
completed on 30-Jan-15 |
In-situ Column
Construction
(a) 1st lift works is in progress at P28, P31, P59
& P70.
(b) 1st lift concrete was poured at P29, P30 & P62.
(c) Pier head works is in progress at P50, P61 & P62.
(d) Pier head concreting was poured at P63 & P64.
Precast Column
Erection
(e) P33-34 – base units installed.
(f) P35 – Base and First unit installed.
(g) P36 - P38 – Pier Heads installed.
(h) P44 & P41 vertical nailing tendons stressed.
In-situ Double Blade
Column Construction
Pier Location |
Side |
Progress |
P19 |
L |
Completed 2nd and 3rd
lift |
R |
Completed 2nd lift
and 3rd lift in progress |
|
P20 |
L |
Completed 5th and 6th
lift and 7th lift in progress |
R |
Completed 5th lift
and 6th lift in progress |
|
P71 |
L |
All cast with pier head |
R |
Completed 1st lift
and 2nd lift in progress |
|
P73 |
L |
Completed kicker and 1st
lift in progress |
R |
Completed kicker and 1st
lift in progress |
Marine Portal
(a) Falsework of the portal at
P52 is in progress and construction of portal at P60 was resumed on 23 Feb 2015.
Deck Erection
(a)
Setting up of Equipment:
Type of Equipment |
Status |
Lifting Frames 1 (LF1) |
Assembly
of the first set of LF1 is on-going at WA4; Steelwork
for the 4th set of Lifting Frames is under fabrication with some
deliveries commenced. |
Lifting Frames 3 (LF3) |
Fabrication
of LF3 in China has commenced. |
Launching Gantry 1 (LG1) |
LG1
assembly has been completed, load test carried out and segment erection at
P110 commenced. |
Launching Gantry 2 (LG2) |
Truss
beams for LG2 have been erected at P46 and P47 ready for the main truss
elements erection. One main truss is assembled on the P46 and P47 pile caps
with the other main truss partially assembled on a barge. |
- A cumulative total of 37 segments have been
erected.
Precast Segment
(a)
Segment Casting and Delivery
Item |
Number in this reporting period |
Cumulative No. of Precast Segment Completed (up to 28th of each month) |
Segment Cast |
176 |
1777 |
Segment Delivered |
28 |
108 |
(b)
Off-site Storage:
Area |
No. in Off-site Storage |
A1 |
134 |
A2 |
240 |
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of Shell |
Number of
Precast Shell Cast in this reporting period |
Cumulative No.
of Precast Shell Completed (up to 28th of each month) |
CP1 |
6 |
74 |
CP2 |
Completed |
12 |
CP3 |
1 |
7 |
CP4 |
Completed |
8 |
CP5 |
Completed |
6 |
CP6 |
0 |
3 |
Precast Column &
Precast Pier Head Casting
(a)
Progress of the precast column & precast pier
head casting:
- All the 5 moulds
are in service for precast production;
- Totally
10 precast elements (8 piers with 6m high and 2 monolithic pier heads) were
cast in this reporting period.
- Cumulatively 137
precast elements have been produced.
(b)
Delivery Progress:
Item |
No. of units delivered in this reporting
period |
Cumulative No |
Segment Delivered |
8 (2 trips) |
56 (14 trips) |
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
Portion A: GW-RW0838-14 |
23/08/2014 (19:00) |
22/02/2015 (23:00) |
Expired |
P81 – P82: GW-RS1064-14 |
11/10/2014 (00:00) |
10/04/2015 (24:00) |
Valid |
P81 – P114: GW-RS1250-14 |
06/11/2014(19:00) |
05/02/2015(23:00) |
Expired |
P101 – P113: GW-RS1297-14 |
21/11/2014(19:00) |
31/03/2015 (06:30) |
Valid |
P69 – P74: GW-RS1340-14 |
30/11/2014 (00:00) |
31/03/2015(24:00) |
Valid |
WA4: GW-RW0984-14 |
15/12/2014(19:00) |
14/06/2015(23:00) |
Valid |
P75 –
P80 :GW-RS1421-14 |
22/12/2014(19:00) |
31/03/2015(24:00) |
Valid |
WA7: GW-RW1024-14 |
13/01/2015(19:00) |
12/07/2015(07:00) |
Valid |
P0 – P68: GW-RS0081-15 |
23/01/2015(19:00) |
22/03/2015(24:00) |
Cancelled
on 10 February 2015 |
P101 – P113 & Southeast Quay: GW-RS0111-15 |
02/02/2015(19:00) |
30/06/2015(05:30) |
Valid |
P76 – P80: GW-RS0094-15 |
03/02/2015(01:30) |
02/08/2015(08:00) |
Valid |
P81 – P114: GW-RS0122-15 |
06/02/2015(19:00) |
05/08/2015(23:00) |
Valid |
P0 – P68: GW-RS0130-15 |
10/02/2015(19:00) |
08/08/2015(24:00) |
Valid |
Waters next to Southeast Quay: GW-RS0181-15 |
23/02/2015(19:00) |
22/08/2015(23:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
A/C# 7016948 (Vessel Disposal) |
18/11/2014 |
28/02/2015 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C:
WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7:
WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Cross-border
dumping of dredged sediment of Category L and Category Mp
at Erchau Island in China EP/MD/15-195 |
10/01/2015 |
09/02/2015 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1 – Open Sea Disposal) marine sediment EP/MD/15-226 |
11/02/2015 |
09/08/2015 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1D and Type 2) marine
sediment EP/MD/15-210 |
01/02/2015 |
28/02/2015 |
Valid |