2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department
as the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) The last pile for land viaduct was concreted in this reporting
period.
(b) Total 169 pours
for column were completed with 7 pours in this reporting period; 61 columns were completed to top level (30 gridlines - P85 to P114). Land viaduct column completed.
(c) P81R&L excavation works and
waling & struts installation work are in progress.
(d) Sewage diversion at P82 is in
progress.
(e) P82R pre-bored sheet pile were
completed, P82L pre-bored sheet pile in progress.
(f) P83R pile cap excavation work and
waling & struts installation is in progress.
(g) Portal Works:
Pier
Location |
Progress |
P84 |
Formation
work is in progress, steel bracket system to be erected; |
P87 |
Erection
of steel girders and cross beams is in progress; |
P88 |
Erection
of vertical formwork and kickers is in progress; |
P93 |
Steel
fixing for portal is in progress; |
P94 |
Portal
was concreted on 24 March 2015; |
P95 |
Portal
was concreted on 13 March 2015, removal of vertical formwork is in progress; |
P96 |
Removal
of falsework is in progress; |
P98 |
Removal
of steel bracket system is in progress; |
P99 |
Removal
of falsework is in progress; |
P100 |
Removal
of falsework was completed; |
P101 |
Removal
of falsework was completed; |
(h) Construction of drainage work
near P115 Abutment was completed, adjusting manhole covers is in progress.
(i) Construction of temporary
foundations for P114 segment temporary supports at R & C Lines were
completed, pile caps construction at L-Line is in progress.
Marine Viaduct (P0 to P80)
RCD Method (except P68):
(a) Piling
jackets were dismantled at D18 and P26.
(b) Pile excavations and casing installation are in progress at P69. 4 marine piles using RCD method were concreted
in the reporting period.
(c) Inter-face coring tests were carried out at P5, P6, P10, P11 & P26.
(d) No Full
depth coring test was carried.
(e) Sonic tests
were carried out at P5, P6, P10, P11 & P69.
(f) Grouting
works were carried out at P26.
Progress at P68
(a) Temporary platform formation is on-going
(about 16,000T of grade 150 fill placed and 2,000T of rock armour).
(b) Jacket was installed on
RHS and casing driven.
(c) Logistic platform was
completed.
Disposal from
Marine Works
(a)
The disposals in this reporting
period are shown in below table.
Disposal
Location |
No of
Trip |
Type of
Materials |
TM38 |
0 |
Inert Materials |
TMCLK |
0 |
Inert Materials |
HK Open Sea Mud Pits |
1 |
Types II Marine Mud |
Cross Boundary Disposal |
5 |
Type I Marine Mud |
Pilecap
Construction:
(a) 8 precast cap shells were installed P1, P12, P54
& P58.
(b) Stage 1 concreting was completed
at P12, P17, P22 & P23.
(c) Stage 1
works is in progress at P1, P12, P17, P22 & P23.
(d) Stage 2 concreting was completed at P3, P4, P17R, P22
& P25.
(e) Stage 2
works is in progress at P3, P4, P17, P22, P23 &
P25.
(f) Kingpost installation and associated steel welding works for precast
shell installation are in progress at P7, P12, P13, P15
& P54.
(g) Concrete trimming and advanced
trimming (inside casing) works were carried out at P2, P7, P15, P19-F1 &F2,
P22, P55, P79 & P80.
(h) Submerged pilecap
works with cofferdam:
Pier Location |
Side |
Progress |
P70 |
L |
Concreting
works of pile cap completed on 13-Jan-15 |
R |
Concreting works of pile cap
completed on 5-Jan-15 |
|
P71 |
L |
Concreting works of pile cap
completed on 6-Oct-14 |
R |
Concreting works of pile cap
completed on 18-Dec-14 |
|
P72 |
L |
Concreting works of pile cap
completed on 10-Mar-15 |
R |
Concreting works of pile cap
completed on 31-Jan-15 |
|
P73 |
L |
Concreting works of pile cap
completed on 4-Dec-14 |
R |
Concreting works of pile cap
completed on 3-Jan-15 |
|
P74 |
L |
Concreting works of plug
completed on 2-Mar-15; Trimming of pile head concrete
is in progress |
R |
Excavation works is in
progress |
|
P75 |
L |
Rock excavation is in progress |
R |
Rock excavation is in progress |
|
P76 |
L |
Trimming of pile head concrete
is in progress |
R |
Concreting works of plug
completed on 16-Mar-15; Cleaning works before blinding
layer is in progress. |
|
P77 |
L |
Concreting works of pile cap
completed on 24-Mar-15 |
R |
Steel Fixing works of pile cap
is in progress |
|
P78 |
L |
Concreting works of pile cap
completed on 24-Jan-15 |
R |
Concreting works of pile cap
completed on 30-Jan-15 |
In-situ Column
Construction
(a) 1st lift works is in progress at P16, P21, P27, P28, P29,
P30, P31, P53, P59 & P70.
(b) 1st lift concrete was poured at P27, P28, P29, P30, P31, P53,
P59 and P70.
(c) 2nd lift works and poured at P53.
(d) Pier head works is in progress at P50, P61 & P62.
(e) Pier head concreting was poured at P50, P61 & P62
Precast Column
Erection
(f) P29, P30 & P32 - Base units installed.
(g) P32 - P44 All precast units now installed.
(h) P43 - Vertical nailing tendons stressed.
In-situ Double Blade
Column Construction
Pier Location |
Side |
Progress |
P18 |
L |
To be started in April 2015 |
R |
To be started in April 2015 |
|
P19 |
L |
Completed 4th and 5th lift in
progress |
R |
Completed 3rd & 4th lift
and started for 5th lift |
|
P20 |
L |
All cast in March 2015, total
7th lift |
R |
All cast in March 2015, total
7th lift |
|
P71 |
L |
All cast in February 2015,
total 3 lifts (including pierhead) |
R |
All cast in March 2015, total
3 lifts (including pierhead) |
|
P72 |
L |
To be started in April 2015 |
R |
To be started in April 2015 |
|
P73 |
L |
Completed 1st lift
and 2nd lift in progress |
R |
Completed 1st lift
and 2nd lift in progress |
Marine Portal
(a) Steel fixing of portal at P52 is in progress. Bearing installation and faleswork of portal at P60 were completed and soffit
formwork is in progress.
Deck Erection
(a)
Setting up of Equipment:
Type of Equipment |
Status |
Lifting Frames 1 (LF1) |
Assembly
of the first set of LF1 is on-going at WA4; Steelwork
for the 2nd set of Lifting Frames is under fabrication with some
deliveries commenced. |
Lifting Frames 3 (LF3) |
Fabrication
of LF3 in China has commenced. Some major components have been completed, and
some deliveries have been commenced.
Assembly of the first 4 sets of LF3 is targeted to be commenced by
mid-April at WA4. |
Launching Gantry 1 (LG1) |
Segment
erection at P110, P111 & P112R&C completed. Gantry
has been commissioned for launching and launched to P113 & P114 is
completed |
Launching Gantry 2 (LG2) |
Load
test and commissioning of the first part have been completed. |
(b)
Segment erection:
-
A cumulative total of 140 segments have been erected
Type |
Location
of Segments erected in this reporting period |
Number
of Segments erected in this reporting period |
Cumulative
No. of Segments erected (up to
28th of each month) |
LG1* |
P110 & P111 |
16 |
112 |
LG2 |
P47 |
4 |
4 |
SOP |
P65 |
4 |
24 |
Precast Segment
(a)
Segment Casting:
Item |
Number
in this reporting period |
Cumulative
No. of Precast Segment Completed (up to
28th of each month) |
Segment Cast |
41 |
1850 |
(b)
Off-site Storage:
Area |
No. in
Off-site Storage |
A1 |
134 |
A2 |
228 |
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of
Shell |
Number
of Precast Shell Cast in this reporting period |
Cumulative
No. of Precast Shell Completed (up to
28th of each month) |
CP1 |
6 |
80 |
CP2 |
Completed |
12 |
CP3 |
1 |
8 |
CP4 |
Completed |
8 |
CP5 |
Completed |
6 |
CP6 |
1 |
4 |
Precast Column &
Precast Pier Head Casting
(a)
Progress of the precast column & precast pier
head casting:
- All the 5 moulds are in
service for precast production.
- Totally
25 precast elements (6 piers with 3m high, 12 piers with 6m high, 4
monolithic pier heads and 3 pier heads with bearing support) were cast in this
reporting period.
- Cumulatively 162
precast elements have been produced.
Delivery for Precast Concrete Elements (by barge)
(a)
Precast Deck Segments:
-
Number of additional barges engaged in this period:
6
-
Cumulative number of barges: 11 (2 barges allocated
for long span storage)
-
Number of Deck Segment deliveries in this period: 7
trips
-
Cumulative number of Deck Segment deliveries: 43
trips
Segment
Types |
Segment
Delivered in this reporting period |
Cumulative
No. of Precast Segment Delivered (up to
28th of each month) |
A |
12 |
40 |
B |
0 |
0 |
C |
0 |
0 |
D |
0 |
0 |
E |
22 |
164 |
(b)
Precast column units:
-
Number of additional barges engaged in this period:
0
-
Cumulative number of barges: 1
-
Number of column unit deliveries in this period: 5
trips
-
Cumulative number of column unit deliveries: 19
trips
Unit
Types |
Number
of units delivered in this reporting period |
Cumulative
No. of Precast Column Delivered (up to
28th of month) |
3m |
4 |
16 |
6m |
8 |
34 |
PH1 |
8 |
18 |
PH2 |
0 |
8 |
(c)
Temporary storage of long span segments:
-
First barge loaded with four long span segments on
26 March 15.
-
Preparation of 2nd Long-Span storage
barge on going.
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
P81 – P82: GW-RS1064-14 |
11/10/2014 (00:00) |
10/04/2015 (24:00) |
Valid |
P101 – P113: GW-RS1297-14 |
21/11/2014(19:00) |
31/03/2015 (06:30) |
Valid |
P69 – P74: GW-RS1340-14 |
30/11/2014 (00:00) |
31/03/2015(24:00) |
Cancelled on 31 March 2015 |
WA4: GW-RW0984-14 |
15/12/2014(19:00) |
14/06/2015(23:00) |
Valid |
P75 –
P80 :GW-RS1421-14 |
22/12/2014(19:00) |
31/03/2015(24:00) |
Cancelled on 5 March 2015 |
WA7: GW-RW1024-14 |
13/01/2015(19:00) |
12/07/2015(07:00) |
Valid |
P101 – P113 & Southeast Quay: GW-RS0111-15 |
02/02/2015(19:00) |
30/06/2015(05:30) |
Cancelled on 23 March 2015 |
P76 – P80: GW-RS0094-15 |
03/02/2015(01:30) |
02/08/2015(08:00) |
Valid |
P81 – P114: GW-RS0122-15 |
06/02/2015(19:00) |
05/08/2015(23:00) |
Valid |
P0 – P68: GW-RS0130-15 |
10/02/2015(19:00) |
08/08/2015(24:00) |
Valid |
Waters next to Southeast Quay: GW-RS0181-15 |
23/02/2015(19:00) |
22/08/2015(23:00) |
Valid |
P75 – P80: GW-RS0226-15 |
05/03/2015(19:00) |
04/09/2015(24:00) |
Valid |
P101 – P114: GW-RS0272-15 |
23/03/2015(19:00) |
22/06/2015(24:00) |
Valid |
P53 – P59: GW-RS0314-15 |
31/03/2015(00:00) |
30/09/2015(07:00) |
Valid |
P69 – P74: GW-RS0333-15 |
31/03/2015(00:00) |
30/09/2015(24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
A/C# 7016948 (Vessel Disposal) |
18/11/2014 |
31/05/2015 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C:
WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1 – Open Sea Disposal) marine sediment EP/MD/15-226 |
11/02/2015 |
09/08/2015 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1D and Type 2) marine
sediment EP/MD/15-235 |
06/03/2015 |
05/04/2015 |
Valid |
Cross-border dumping of dredged sediment
of Category L and Category Mp at Erzhou Island in China EP/MD/15-216 |
03/03/2015 |
02/04/2015 |
Valid |