9.1
Major site activities for the coming reporting month will include:
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading
and Unloading of rebar materials
Marine Viaduct (P0 to P80)
Reverse Circulation Drill (RCD) Method:
Piling
works
Mooring
bits and silt curtain installation
Installation
of piling jackets
Dismantling
of piling jackets
Pile
excavation and casing installation
Inter-face
tests, full depth coring test and sonic test
Grouting
works
Kelly Method:
Removal
of piling platform and temporary pile extraction
Inter-face
tests, full depth coring
test
and sonic test
Toe
grouting works
Pile Cap Construction:
Installation
of precast cap shells
Concreting
Kingpost
installation and associated steel welding works
Concreting
trimming
Works with Cofferdam:
Installation
of waling strut
Installation
of sheet pile
Installation
of temporary working platform
Installation
of shear pin
Installation
of bored pile casing
Excavation
works and casting of concrete plug
Dewatering
works and sealing works
Additional
welding
Column Construction:
Lifting
works
Lift
concreting
Pier
head works
Pier
head concreting
Column
insert installation, mobilization and temporary works
Deck Erection:
Segment
Unloading Frame (SUF)
Winches
test
Assembly
and erection of Lifting Frame 2
Erection
of segment on pier
Land Viaduct (P85 to Abutment at SHT)
& Marine Viaduct (P81 - P84)
Pile
construction
Pouring
of column
Pre-bored
for sheet pile for cofferdam construction
Seawall
block coring and breaking
Formwork
erection
Blinding
concrete for scaffolding works
Dismantling
of steel bracket system
Erection
of steel bracket system cross road steel portal beams erection and
corresponding falsework erection
Steel
girders and cross beams erection
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.