7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 3rd, 10th, 17th, 23rd and 31st March 2015 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 23rd March 2015. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 9th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 17th March 2015 and next inspection will be conducted in June 2015.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

10/03/2015

The silt curtain at P98 and P95 should be used to surround the works area to avoid the gap.

Rectification/improvement was observed during the follow-up audit session on 17 March 2015.

10/03/2015

Regular check and provide well maintenance for the silt curtain at P68 to ensure it can function properly.

Rectification/improvement was not observed during the follow-up audit session on 17 March 2015. Further follow-up on this item is required.

17/03/2015

To seal the hole at the bunded area at barge (B22595Y) near P29.

Rectification/improvement was observed during the follow-up audit session on 23 March 2015.

17/03/2015

Properly deploy the silt curtain at P72, P99, P86 and P68.

Rectification/improvement was not observed during the follow-up audit session on 23 March 2015. Further follow-up on this item is required.

23/03/2015

The silt curtain at P71 and P70 should be used to surround the works area to avoid the gap.

Rectification/improvement was observed during the follow-up audit session on 31 March 2015.

31/03/2015

Properly deploy the silt curtain at P68, P72, P86, P99 and P103.

Rectification/improvement was not observed during the follow-up audit session on 9 April 2015. Further follow-up on this item is required.

31/03/2015

Clear the waste materials at near the rockfill platform at P68.

Rectification/improvement was observed during the follow-up audit session on 9 April 2015.

31/03/2015

Clear the sedimentation tank to ensure it can function properly at Portion C.

Rectification/improvement was not observed during the follow-up audit session on 9 April 2015. Further follow-up on this item is required.

Ecology

03/03/2015

Storage of construction materials at near the trees should be avoid (P100).

Rectification/improvement was observed during the follow-up audit session on 10 March 2015.

10/03/2015

Clear the construction wastes / materials at near the trees at P99 – P102.

Rectification/improvement was not observed during the follow-up audit session on 17 March 2015. Further follow-up on this item is required.

17/03/2015

Clear the construction materials at near the trees at P113, P102 and P100.

Rectification/improvement was not observed during the follow-up audit session on 23 March 2015. Further follow-up on this item is required.

31/03/2015

Clear the construction wastes / materials at near the trees at P87, between P88 & P89, between P94 & P95, P102 and P113.

Rectification/improvement was not observed during the follow-up audit session on 9 April 2015. Further follow-up on this item is required.

Air Quality

10/03/2015

The unpaved area at near P113 should be watered regularly to avoid dust generation.

Rectification/improvement was observed during the follow-up audit session on 17 March 2015.

23/03/2015

The unpaved site area at near P113 should be watered regularly to avoid dust generation.

Rectification/improvement was observed during the follow-up audit session on 31 March 2015.

Noise

23/03/2015

To repair the noise enclosure at P70.

Rectification/improvement was not observed during the follow-up audit session on 31 March 2015. Further follow-up on this item is required.

31/03/2015

To repair the noise enclosure at P70.

Rectification/improvement was not observed during the follow-up audit session on 9 April 2015. Further follow-up on this item is required.

Waste / Chemical Management

03/03/2015

Clear the accumulated construction wastes at near P107.

Rectification/improvement was observed during the follow-up audit session on 10 March 2015.

03/03/2015

Clear the mixture of water and oil at the drip tray at P87.

Rectification/improvement was observed during the follow-up audit session on 17 March 2015.

17/03/2015

Clear the construction wastes at the side of pile cap of P27.

Rectification/improvement was observed during the follow-up audit session on 23 March 2015.

23/03/2015

Clear the concrete debris and used cement bags at P50.

Rectification/improvement was observed during the follow-up audit session on 31 March 2015.

31/03/2015

Clear the accumulated general refuse at platform at P70.

Rectification/improvement was observed during the follow-up audit session on 9 April 2015.

31/03/2015

To clear the oil spillage at near P109.

Rectification/improvement was not observed during the follow-up audit session on 9 April 2015. Further follow-up on this item is required.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

17/03/2015

N/A(1)

N/A(1)

Remark:       N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 681m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.