7.1
Site audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures in the Contract site. The
summaries of site audits are attached in Appendix
M.
7.2
Site audits were conducted on 3rd, 10th, 17th,
23rd and 31st March 2015 by ET after the commencement of
construction works for the Contract. A joint site audit with the representative
with IEC, SOR, the Contractor and the ET was carried out on 23rd March
2015. The details of observations during site audit can refer to Table 7.1.
7.3
According to EP condition 4.7 and EM&A Manual, periodic monitoring
(every three months) of construction works shall be conducted to ensure the
avoidance of any impacts on Sha Lo Wan (West)
Archaeological Site. Access to Sha Lo Wan (West)
Archaeological site for works areas and storage of construction equipment is
not allowed. The 9th inspection to the Sha Lo Wan (West) Archaeological Site was
conducted on 17th March 2015 and next inspection will be conducted
in June 2015.
7.4
According to the EIA Study Report, Environmental Permit and the EM&A
Manual, the mitigation measures detailed in the documents are recommended to be
implemented during the construction phase.
An updated summary of the EMIS is provided in Appendix N.
7.5
Regular marine travel route for marine vessels were implemented properly
in accordance with the submitted plan and relevant records were kept properly.
7.6
Acoustic decoupling measures for the stationary equipment (generators,
winch generators and air compressors) mounted on boards were adopted according
to EP Condition 3.7 and EM&A Manual, Section 10.2.18.
7.7
Dolphin exclusion zone and dolphin watching plan according to EM&A
Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained
dolphin watcher.
7.8
Spill kits and booms are ready on site for the event of accidental
spillage of oil or other hazardous chemicals from construction activities
including vessels operating for the Contract.
7.9
During site inspections in the reporting month, no non-conformance was
identified. The observations and recommendations made during the audit sessions
are summarized in Table 7.1.
Table
7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Water Quality |
10/03/2015 |
The
silt curtain at P98 and P95 should be used to surround the works area to avoid
the gap. |
Rectification/improvement was observed during
the follow-up audit session on 17 March 2015. |
10/03/2015 |
Regular
check and provide well maintenance for the silt curtain at P68 to ensure it
can function properly. |
Rectification/improvement was not observed
during the follow-up audit session on 17 March 2015.
Further follow-up on this item is required. |
|
17/03/2015 |
To
seal the hole at the bunded area at barge (B22595Y)
near P29. |
Rectification/improvement was observed during
the follow-up audit session on 23 March 2015. |
|
17/03/2015 |
Properly
deploy the silt curtain at P72, P99, P86 and P68. |
Rectification/improvement was not observed
during the follow-up audit session on 23 March 2015.
Further follow-up on this item is required. |
|
23/03/2015 |
The
silt curtain at P71 and P70 should be used to surround the works area to
avoid the gap. |
Rectification/improvement was observed during
the follow-up audit session on 31 March 2015. |
|
31/03/2015 |
Properly
deploy the silt curtain at P68, P72, P86, P99 and P103. |
Rectification/improvement was not observed
during the follow-up audit session on 9 April 2015.
Further follow-up on this item is required. |
|
31/03/2015 |
Clear
the waste materials at near the rockfill platform
at P68. |
Rectification/improvement was observed during
the follow-up audit session on 9 April 2015. |
|
31/03/2015 |
Clear
the sedimentation tank to ensure it can function properly at Portion C. |
Rectification/improvement was not observed
during the follow-up audit session on 9 April 2015.
Further follow-up on this item is required. |
|
Ecology |
03/03/2015 |
Storage
of construction materials at near the trees should be avoid (P100). |
Rectification/improvement was observed during
the follow-up audit session on 10 March 2015. |
10/03/2015 |
Clear
the construction wastes / materials at near the trees at P99 – P102. |
Rectification/improvement was not observed
during the follow-up audit session on 17 March 2015.
Further follow-up on this item is required. |
|
17/03/2015 |
Clear
the construction materials at near the trees at P113, P102 and P100. |
Rectification/improvement was not observed
during the follow-up audit session on 23 March 2015.
Further follow-up on this item is required. |
|
31/03/2015 |
Clear
the construction wastes / materials at near the trees at P87, between P88
& P89, between P94 & P95, P102 and P113. |
Rectification/improvement was not observed
during the follow-up audit session on 9 April 2015.
Further follow-up on this item is required. |
|
Air Quality |
10/03/2015 |
The unpaved area at near P113 should be
watered regularly to avoid dust generation. |
Rectification/improvement was observed during
the follow-up audit session on 17 March 2015. |
23/03/2015 |
The unpaved site area at near P113 should
be watered regularly to avoid dust generation. |
Rectification/improvement was observed during
the follow-up audit session on 31 March 2015. |
|
Noise |
23/03/2015 |
To
repair the noise enclosure at P70. |
Rectification/improvement was not observed
during the follow-up audit session on 31 March 2015.
Further follow-up on this item is required. |
31/03/2015 |
To repair the noise enclosure at P70. |
Rectification/improvement was not observed
during the follow-up audit session on 9 April 2015.
Further follow-up on this item is required. |
|
Waste / Chemical Management |
03/03/2015 |
Clear
the accumulated construction wastes at near P107. |
Rectification/improvement was observed during
the follow-up audit session on 10 March 2015. |
03/03/2015 |
Clear
the mixture of water and oil at the drip tray at P87. |
Rectification/improvement was observed during
the follow-up audit session on 17 March 2015. |
|
17/03/2015 |
Clear
the construction wastes at the side of pile cap of P27. |
Rectification/improvement was observed during
the follow-up audit session on 23 March 2015. |
|
23/03/2015 |
Clear
the concrete debris and used cement bags at P50. |
Rectification/improvement was observed during
the follow-up audit session on 31 March 2015. |
|
31/03/2015 |
Clear
the accumulated general refuse at platform at P70. |
Rectification/improvement was observed during
the follow-up audit session on 9 April 2015. |
|
31/03/2015 |
To
clear the oil spillage at near P109. |
Rectification/improvement was not observed
during the follow-up audit session on 9 April 2015.
Further follow-up on this item is required. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural
Heritage (Sha Lo Wan (West) Archaeological Site) |
17/03/2015 |
N/A(1) |
N/A(1) |
Remark: N/A(1) - No
major environmental deficiency was identified during the site inspection in the
reporting month.
7.10
According to the Contractor, 681m3 inert C&D materials were
generated during the reporting month.
7.11
The Contractor was advised to minimize the wastes generated through the
recycling or reusing. All mitigation measures stipulated in approved waste management
plan shall be fully implemented.
7.12
The amount of wastes generated by the activities of the Contract during
the reporting month is shown in Appendix
O.