2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Ramboll Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Environ Hong Kong Limited (Ramboll Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      P81L&R - pile cap were completed; 2 pours of column were completed in this reporting period.

(b)     P82L - ELS excavation was suspended due to settlement.

(c)      P82R - excavation works are in progress.

(d)     P83L - ELS excavation is in progress.

(e)      P83R - 4 pours of column were completed in this reporting period.

(f)      P84L&R - column head were completed

(g)     Portal Works:

Pier Location

Progress

P84

Steel bracket and girders erection completed;

Pier head construction is in progress

P86

Installation of steel bracket and girder system is in progress

P87

Removal of formwork & falsework is in progress

P88

Removal of falsework & steel bracket system was completed.

P89

Erection of soffit formwork was completed, formwork & falsework erection is in progress

P90

Steel fixing is in progress, target for concreting on 30 June 2015

P91

Portal was cast on 9 June 2015. Nailing work and removal of formwork is in progress

P92

Erection of formwork and kickers were completed;

Steel fixing to start

P93

Removal of steel cross beams were completed

 

Marine Viaduct (P0 to P80)

Piling Testing, Coring and Grouting (locations other than P68 & P75):

(a) Inter-face coring tests were carried out at D18.

(b) Full depth coring test was carried at D20-L3.

(c) Sonic test was carried out at D18.

(d) Grouting work was carried out at D17.


 

Progress at P68

(a) Casing installation at R3 to R5 and L2 & L5.

         (b)  P68- L3, L4 and L6 were cast.

(c)  P68-L1 excavation was completed with installed rebar cage for concreting at the end of June 2015.

(d)  Two RCD were set up onto R5 and L5 casings at end of June 2015 for commencing of socket drilling.

 

Progress at P69

(a)     Setting up for cofferdam construction work was completed at early June and working platform construction was commenced.

(b)    Right hand side (RHS) working platform was completed and installation of sheetpiles on RHS cofferdam in progress.

(c)     Left hand side (LHS) working platform construction was completed at the end of June.

Progress at P75

(a)     RHS concrete plug was concreted.

(b)    RCD guide frame was installed on the RHS box.

(c)     RCD guide frame was installed on the RHS box.

(d)    RCD excavation is in progress at R2 and R4.

(e)     Excavation to formation at the LHS continued.

Disposal from Marine Works

(a)    The disposals in this reporting period are shown in below table.

Disposal Location

No of Trip

Type of Materials

TM38

0

Inert Materials

TMCLK

0

Inert Materials

HK Open Sea Mud Pits

0

Types II Marine Mud

Cross Boundary Disposal

0

Type I Marine Mud

Pilecap Construction:

(a)  Precast shells installed in this reporting period - two CP3 at P55; Four CP6 at P79 and P80; Four CP1 at P6 and P8; One CP12 at P26L.

(b)   Stage 1 concreting was completed at P11, P26R & P55.

(c)  Stage 1 works is in progress at P79.

(d) Stage 2 concreting was completed at P2L, P7, P11, P13, P26R & P58L.

(e)  Stage 2 works is in progress at P55.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P9.

(g) Advanced concrete trimming (inside casing) works were carried out at P5, P6, P8, P9, P56 & P57 and concrete trimming (inside cap shell) at P55.

(h) Submerged pile cap works with cofferdam:

Pier Location

Side

Progress

P73

L

Backfilling and removal of cofferdam completed on 19-Jun-15

R

Backfilling and removal of cofferdam completed on 19-Jun-15

P74

L

Grouting works around bored pile is in progress

R

Drilling of grouting holes is in progress

P75

L

Rock excavation is in progress

R

Rock excavation is in progress

 

In-situ Column Construction

(a)    1st lift works is in progress at P1, P3, P4, P7, P15, P23, P58 & P78.

(b)   1st lift concrete was poured at P1, P3, P4, P23, P54, P53-Ramp, P59-Ramp, and P78.

(c)    2nd lift works is in progress at P54, P53-Ramp, P59-Ramp and P78.

(d)   2nd lift concrete was poured at P70.

(e)    Pier head works is in progress at P70.

(f)    Pier head concreting: NIL.

 

Precast Column Erection

Description

Location completed in this reporting period

Number of Units erected/ Number of Columns completed in this reporting period

Cumulative No. of Piers completed

(up to 28th of each month)

Precast Column Segment

P25

2

20 (P21, P25, P27-P44)

Precast Column Pier Head

P28, P29

4

17 (P28-P44)

Vertical Tendons Stressed

P28, P29, P34

6

12.5 (P28, P29, P34, P35(1/2), P36-P44)

Grouting Vertical Tendons

P36, P37, P38, P39

8

9 (P36-P44)

Pier Head Concrete

P40, P41, P42

6

5 (P40-P44)

 

 


In-situ Double Blade Column Construction

Pier Location

Side

Progress

P17

L

1st lift in progress

R

1st lift in progress

P18

L

Poured concrete up to 5th lift and 6th lift in progress

R

Poured concrete up to 5th lift and 6th lift in progress

P72

L

Poured concrete to 2nd lift and pierhead in progress

R

Poured concrete to 2nd lift and pierhead in progress

P77

L

Works commenced

R

Works commenced

P77

L

1st lift in progress

R

Poured concrete to 1st lift and 2nd lift in progress

 

Marine Portal

(a)    Dismantling of scaffolding at Portal P52 completed. Removal of temporary supporting platform is in progress.

(b)   Temporary bearing wall of Portal P60 casted. Dismantling of soffit platform is in progress.

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

 

Lifting Frames 1 (LF1)

Assembly of first set of LF1 almost completed.

Assembly of the second to fourth set of LF1 is on-going at WA4;

Steelwork for the 3rd and 4th set of Lifting Frames is under fabrication with some deliveries commenced.

 

Lifting Frames 3

(LF3)

Fabrication of LF3 in China is almost completed for 8 sets. Most of the major components have been completed and have been delivered to site.  Assembly of the first 2 sets of LF3 is completed. The 3rd and 4th sets are almost completed at WA4. Assembly of the 5th to 7th sets have been commenced at WA4 and they are targeted to be completed by mid-July.

 

Launching Gantry 1 (LG1)

Segment erection to P112L & P111L completed in his reporting period, LG1 launching to P108.

 

Launching Gantry 2

 

(LG2)

Erection of P46 to P48 completed (120 segments in total), launching back and forward to P45.

 

(b)     Segment erection:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

LG1

P108R & P111L & P112L

22

242

LG2

P48

40

120

SOP

-

-

36

 

Precast Segment

(a)      Segment Casting:

-             Storage for long span & type D segments is still a key concern.

-             Production affected by inclement weather (5 days).

-            2 nos. of type D & 4 nos. of type CH mould were suspended due to storage problem.

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

172

2261

 

(b)     Off-site Storage:

Area

No. in Off-site Storage

A1

134

A2

207

A3

236

A4

-

Remarks: A fourth off-site storage facilities was identified for long span segments and preparation works was completed. Segments are to be delivered.

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

CP1

4

94

CP2

Completed

12

CP3

0

12

CP4

Completed

8

CP5

Completed

6

CP6

Completed

4

CP11

Completed

1

CP12

Completed

1

F1

1

1

 

Precast Column & Precast Pier Head Casting

(a)      Progress of the precast column & precast pier head casting:

-     All casting works for the based column were completed and the moulds were dismantled. 4 moulds (2 piers and 2 pier heads) are now in service for precasting works.

-      Totally 25 precast elements (19 piers with 6m high, 3 monolithic pier heads and 3 pier heads with bearing support) were cast in this reporting period. 

-      All the 3m high piers were completed in this period (in total 39 elements).

-      Cumulatively 254 precast elements were cast.

Delivery  for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 13 (3 barges tied up on L/S storage)

-             Number of deck segment deliveries in this period: 10 trips

-             Cumulative number of deck segment deliveries: 95 trips

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

42

172

B

0

0

C

0

0

D

0

0

E

10

262

(b)     Precast column units:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 2

-             Number of column unit deliveries in this period: 3 trips

-             Cumulative number of column unit deliveries: 30 trips

Unit Types

Number of units delivered in this reporting period

Cumulative No. of Precast Column Delivered

(up to 28th of month)

3m

1

19

6m

17

73

PH1

0

20

PH2

4

14

 

(c)      Temporary storage of long span segments:

-       Barge #968 was not able to delivery long span segments at mid-June caused impacts on the scheduling of deliveries.

(d)     General:

-       Delays in the segment unloading has impacts on the delivery cycle time to the extent that there are number of barges overstayed for 14 days in Hong Kong.

-       First delivery of long span segment for P20’s SOP (type CH) arrived in Hong Kong before end of June.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/D

22/12/2014

N/A

Valid

Consruction Noise Permit (CNP)

WA7: GW-RW1024-14

13/01/2015(19:00)

12/07/2015(07:00)

Valid

P76 – P80: GW-RS0094-15

03/02/2015(01:30)

02/08/2015(08:00)

Valid

P81 – P114: GW-RS0122-15

06/02/2015(19:00)

05/08/2015(23:00)

Valid

P0 – P68: GW-RS0130-15

10/02/2015(19:00)

08/08/2015(24:00)

Valid

Waters next to Southeast Quay: GW-RS0181-15

23/02/2015(19:00)

22/08/2015(23:00)

Valid

P53 – P59: GW-RS0314-15

31/03/2015(00:00)

30/09/2015(07:00)

Valid

P69 – P74: GW-RS0333-15

31/03/2015(00:00)

30/09/2015(24:00)

Cancelled on 1 June 2015

P101 – P114: GW-RS0364-15

08/04/2015(19:00)

07/07/2015(05:30)

Valid

WA4: GW-RW0207-15

29/04/2015(19:00)

28/10/2015(23:00)

Valid

P86: GW-RS0460-15

04/05/2015(00:00)

31/08/2015(05:30)

Valid

P100 – P111: GW-RS0487-15

07/05/2015(23:00)

06/11/2015(07:00)

Valid

P75 – P80: GW-RS0508-15

13/05/2015(19:00)

12/07/2015(24:00)

Valid

P69 – P74: GW-RS0584-15

01/06/2015(00:00)

30/11/2015(24:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

22/05/2015

31/08/2015

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1 – Open Sea Disposal)  marine sediment

EP/MD/15-226

11/02/2015

09/08/2015

 

 

Valid

Cross-border dumping of dredged sediment of Category L and Category Mp at Erzhou Island in China

EP/MD/16-009

03/05/2015

02/06/2015

 

 

Expired

Cross-border dumping of dredged sediment of Category L and Category Mp at Erzhou Island in China

EP/MD/16-022

03/06/2015

30/06/2015

 

 

Valid