2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) P81L&R - pile cap were
completed; 2 pours of column were completed in this reporting period.
(b) P82L - ELS excavation was
suspended due to settlement.
(c) P82R - excavation works are in
progress.
(d) P83L - ELS excavation is in
progress.
(e) P83R - 4 pours of column were
completed in this reporting period.
(f) P84L&R - column head were
completed
(g) Portal Works:
Pier
Location |
Progress |
P84 |
Steel
bracket and girders erection completed; Pier
head construction is in progress |
P86 |
Installation
of steel bracket and girder system is in progress |
P87 |
Removal
of formwork & falsework is in progress |
P88 |
Removal
of falsework & steel bracket system was
completed. |
P89 |
Erection
of soffit formwork was completed, formwork & falsework
erection is in progress |
P90 |
Steel
fixing is in progress, target for concreting on 30 June 2015 |
P91 |
Portal
was cast on 9 June 2015. Nailing work and removal of formwork is in progress |
P92 |
Erection
of formwork and kickers were completed; Steel
fixing to start |
P93 |
Removal
of steel cross beams were completed |
Marine Viaduct (P0 to P80)
Piling Testing, Coring and
Grouting (locations other than P68 & P75):
(a) Inter-face coring tests were carried out at D18.
(b) Full depth coring test was carried at D20-L3.
(c) Sonic test was carried out at D18.
(d) Grouting work was carried out at D17.
Progress at P68
(a) Casing installation at R3 to R5 and L2 &
L5.
(b) P68- L3, L4 and L6 were cast.
(c) P68-L1 excavation was completed with installed rebar cage for concreting
at the end of June 2015.
(d) Two RCD were set up onto R5 and L5
casings at end of June 2015 for commencing of socket drilling.
Progress at P69
(a)
Setting up for cofferdam construction work was
completed at early June and working platform construction was commenced.
(b)
Right hand side (RHS) working platform was
completed and installation of sheetpiles on RHS
cofferdam in progress.
(c)
Left hand side (LHS) working platform construction
was completed at the end of June.
Progress at P75
(a)
RHS concrete plug was concreted.
(b)
RCD guide frame was installed on the RHS box.
(c)
RCD guide frame was installed on the RHS box.
(d)
RCD excavation is in progress at R2 and R4.
(e)
Excavation to formation at the LHS continued.
Disposal from
Marine Works
(a)
The disposals in this reporting
period are shown in below table.
Disposal
Location |
No of
Trip |
Type of
Materials |
TM38 |
0 |
Inert Materials |
TMCLK |
0 |
Inert Materials |
HK Open Sea Mud Pits |
0 |
Types II Marine Mud |
Cross Boundary Disposal |
0 |
Type I Marine Mud |
Pilecap
Construction:
(a) Precast shells installed in this reporting period - two CP3 at P55; Four
CP6 at P79 and P80; Four CP1 at P6 and P8; One CP12 at P26L.
(b) Stage 1 concreting was completed
at P11, P26R & P55.
(c) Stage 1
works is in progress at P79.
(d) Stage 2 concreting was completed at P2L, P7, P11, P13, P26R & P58L.
(e) Stage 2
works is in progress at P55.
(f) Kingpost installation and associated steel welding works for precast
shell installation are in progress at P9.
(g) Advanced concrete
trimming (inside casing) works were carried out at P5, P6, P8, P9, P56 &
P57 and concrete trimming (inside cap shell) at P55.
(h) Submerged pile cap works with
cofferdam:
Pier Location |
Side |
Progress |
P73 |
L |
Backfilling
and removal of cofferdam completed on 19-Jun-15 |
R |
Backfilling
and removal of cofferdam completed on 19-Jun-15 |
|
P74 |
L |
Grouting
works around bored pile is in progress |
R |
Drilling
of grouting holes is in progress |
|
P75 |
L |
Rock
excavation is in progress |
R |
Rock
excavation is in progress |
In-situ Column
Construction
(a) 1st lift works is in progress at P1, P3, P4, P7, P15, P23, P58 & P78.
(b) 1st lift concrete was poured at P1, P3, P4, P23, P54,
P53-Ramp, P59-Ramp, and P78.
(c) 2nd lift works is in progress at P54, P53-Ramp, P59-Ramp and
P78.
(d) 2nd lift concrete was poured at P70.
(e) Pier head works is in progress at P70.
(f) Pier head concreting: NIL.
Precast Column
Erection
Description |
Location completed in this
reporting period |
Number of Units erected/
Number of Columns completed in this reporting period |
Cumulative No. of Piers
completed (up to 28th of each month) |
Precast Column Segment |
P25 |
2 |
20 (P21, P25, P27-P44) |
Precast Column Pier Head |
P28, P29 |
4 |
17 (P28-P44) |
Vertical Tendons Stressed |
P28, P29, P34 |
6 |
12.5 (P28, P29, P34, P35(1/2),
P36-P44) |
Grouting Vertical Tendons |
P36, P37, P38, P39 |
8 |
9 (P36-P44) |
Pier Head Concrete |
P40, P41, P42 |
6 |
5 (P40-P44) |
In-situ Double Blade
Column Construction
Pier Location |
Side |
Progress |
P17 |
L |
1st
lift in progress |
R |
1st
lift in progress |
|
P18 |
L |
Poured
concrete up to 5th lift and 6th lift in progress |
R |
Poured
concrete up to 5th lift and 6th lift in progress |
|
P72 |
L |
Poured
concrete to 2nd lift and pierhead in
progress |
R |
Poured
concrete to 2nd lift and pierhead in
progress |
|
P77 |
L |
Works
commenced |
R |
Works
commenced |
|
P77 |
L |
1st
lift in progress |
R |
Poured
concrete to 1st lift and 2nd lift in progress |
Marine Portal
(a) Dismantling of scaffolding at Portal P52 completed. Removal of temporary
supporting platform is in progress.
(b) Temporary bearing wall of Portal P60 casted. Dismantling of soffit
platform is in progress.
Deck Erection
(a)
Setting up of Equipment:
Type of Equipment |
Status |
Lifting Frames 1 (LF1) |
Assembly
of first set of LF1 almost completed. Assembly
of the second to fourth set of LF1 is on-going at WA4; Steelwork
for the 3rd and 4th set of Lifting Frames is under
fabrication with some deliveries commenced. |
Lifting Frames 3 (LF3) |
Fabrication
of LF3 in China is almost completed for 8 sets. Most of the major components
have been completed and have been delivered to site. Assembly of the first 2 sets of LF3 is
completed. The 3rd and 4th sets are almost completed at
WA4. Assembly of the 5th to 7th sets have been
commenced at WA4 and they are targeted to be completed by mid-July. |
Launching Gantry 1 (LG1) |
Segment
erection to P112L & P111L completed in his reporting period, LG1
launching to P108. |
Launching Gantry 2 (LG2) |
Erection
of P46 to P48 completed (120 segments in total), launching back and forward
to P45. |
(b)
Segment erection:
Type |
Location
of Segments erected in this reporting period |
Number
of Segments erected in this reporting period |
Cumulative
No. of Segments erected (up to
28th of each month) |
LG1 |
P108R & P111L & P112L |
22 |
242 |
LG2 |
P48 |
40 |
120 |
SOP |
- |
- |
36 |
Precast Segment
(a)
Segment Casting:
-
Storage for long span & type D segments is
still a key concern.
-
Production affected by inclement weather (5 days).
-
2 nos. of type D & 4 nos. of type CH mould were
suspended due to storage problem.
Item |
Number
in this reporting period |
Cumulative
No. of Precast Segment Completed (up to
28th of each month) |
Segment Cast |
172 |
2261 |
(b)
Off-site Storage:
Area |
No. in
Off-site Storage |
A1 |
134 |
A2 |
207 |
A3 |
236 |
A4 |
- |
Remarks: A fourth off-site storage
facilities was identified for long span segments and preparation works was
completed. Segments are to be delivered.
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of
Shell |
Number
of Precast Shell Cast in this reporting period |
Cumulative
No. of Precast Shell Completed (up to
28th of each month) |
CP1 |
4 |
94 |
CP2 |
Completed |
12 |
CP3 |
0 |
12 |
CP4 |
Completed |
8 |
CP5 |
Completed |
6 |
CP6 |
Completed |
4 |
CP11 |
Completed |
1 |
CP12 |
Completed |
1 |
F1 |
1 |
1 |
Precast Column &
Precast Pier Head Casting
(a)
Progress of the precast column & precast pier
head casting:
- All casting
works for the based column were completed and the moulds were dismantled. 4
moulds (2 piers and 2 pier heads) are now in service for precasting
works.
- Totally
25 precast elements (19 piers with 6m high, 3 monolithic pier heads and 3 pier heads
with bearing support) were cast in this reporting period.
- All the 3m high piers were completed in this period (in total 39 elements).
- Cumulatively 254
precast elements were cast.
Delivery for Precast Concrete Elements (by barge)
(a)
Precast Deck Segments:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 13
(3 barges tied up on L/S storage)
-
Number of deck segment
deliveries in this period: 10 trips
-
Cumulative number of deck
segment deliveries: 95 trips
Segment
Types |
Segment
Delivered in this reporting period |
Cumulative
No. of Precast Segment Delivered (up to
28th of each month) |
A |
42 |
172 |
B |
0 |
0 |
C |
0 |
0 |
D |
0 |
0 |
E |
10 |
262 |
(b)
Precast column units:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 2
-
Number of column unit deliveries in this period: 3
trips
-
Cumulative number of column unit deliveries: 30
trips
Unit
Types |
Number
of units delivered in this reporting period |
Cumulative
No. of Precast Column Delivered (up to
28th of month) |
3m |
1 |
19 |
6m |
17 |
73 |
PH1 |
0 |
20 |
PH2 |
4 |
14 |
(c)
Temporary storage of long span segments:
-
Barge #968 was not able to delivery long span
segments at mid-June caused impacts on the scheduling of deliveries.
(d)
General:
-
Delays in the segment unloading has impacts on the
delivery cycle time to the extent that there are number of barges overstayed
for 14 days in Hong Kong.
-
First delivery of long span segment for P20’s SOP
(type CH) arrived in Hong Kong before end of June.
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental protection
for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
WA7: GW-RW1024-14 |
13/01/2015(19:00) |
12/07/2015(07:00) |
Valid |
P76 – P80: GW-RS0094-15 |
03/02/2015(01:30) |
02/08/2015(08:00) |
Valid |
P81 – P114: GW-RS0122-15 |
06/02/2015(19:00) |
05/08/2015(23:00) |
Valid |
P0 – P68: GW-RS0130-15 |
10/02/2015(19:00) |
08/08/2015(24:00) |
Valid |
Waters next to Southeast Quay: GW-RS0181-15 |
23/02/2015(19:00) |
22/08/2015(23:00) |
Valid |
P53 – P59: GW-RS0314-15 |
31/03/2015(00:00) |
30/09/2015(07:00) |
Valid |
P69 – P74: GW-RS0333-15 |
31/03/2015(00:00) |
30/09/2015(24:00) |
Cancelled
on 1 June 2015 |
P101 – P114: GW-RS0364-15 |
08/04/2015(19:00) |
07/07/2015(05:30) |
Valid |
WA4: GW-RW0207-15 |
29/04/2015(19:00) |
28/10/2015(23:00) |
Valid |
P86: GW-RS0460-15 |
04/05/2015(00:00) |
31/08/2015(05:30) |
Valid |
P100 – P111: GW-RS0487-15 |
07/05/2015(23:00) |
06/11/2015(07:00) |
Valid |
P75 – P80: GW-RS0508-15 |
13/05/2015(19:00) |
12/07/2015(24:00) |
Valid |
P69 – P74: GW-RS0584-15 |
01/06/2015(00:00) |
30/11/2015(24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
A/C# 7016948 (Vessel Disposal) |
22/05/2015 |
31/08/2015 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C:
WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7:
WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1 – Open Sea Disposal) marine sediment EP/MD/15-226 |
11/02/2015 |
09/08/2015 |
Valid |
Cross-border dumping of dredged sediment
of Category L and Category Mp at Erzhou Island in China EP/MD/16-009 |
03/05/2015 |
02/06/2015 |
Expired |
Cross-border dumping of dredged sediment
of Category L and Category Mp at Erzhou Island in China EP/MD/16-022 |
03/06/2015 |
30/06/2015 |
Valid |