7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 7th, 14th, 21st and 28th July 2015 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 28th July 2015. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 10th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 23th June 2015 and next inspection will be conducted in September 2015.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1   Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

07/07/2015

To repair the damaged silt curtain at P74.

Rectification/improvement was observed during the follow-up audit session on 14 July 2015.

07/07/2015

Muddy sediment was observed discharged into the sea at P75. The Contractor was reminded to dispose it properly.

Rectification/improvement was observed during the follow-up audit session on 14 July 2015.

14/07/2015

Clear the waste materials at the platform at P20 to avoid falling into the sea.

Rectification/improvement was observed during the follow-up audit session on 21 July 2015.

14/07/2015

Provide mitigation measures to avoid the leakage of water from site to the public road (near P111).

Rectification/improvement was observed during the follow-up audit session on 21 July 2015.

21/07/2015

Provision of sedimentation facilities according to effluent discharge license at P81 and P82.

Rectification/improvement was not observed during the follow-up audit session on 28 July 2015.

21/07/2015

Provide mitigation measures to avoid muddy water directly discharge to the gullies at between P82 and P83.

Rectification/improvement was observed during the follow-up audit session on 28 July 2015.

28/07/2015

Provide mitigation measures to avoid the fine materials falling into the sea through the gap at the platform at P7.

Rectification/improvement was observed during the follow-up audit session on 4 August 2015.

28/07/2015

Clear the loose material at the platform at P78.

Rectification/improvement was observed during the follow-up audit session on 4 August 2015.

28/07/2015

Properly repair the damaged part of silt curtain at P78.

Rectification/improvement was observed during the follow-up audit session on 4 August 2015.

Ecology

21/07/2015

To remove the construction wastes at near the trees at P90.

Rectification/improvement was observed during the follow-up audit session on 28 July 2015.

Air Quality

07/07/2015

To provide proper shelter (3 sides and on top) for dusty materials at P74.

Rectification/improvement was observed during the follow-up audit session on 14 July 2015.

Noise

28/07/2015

Provide noise emission label for the air compressor at P7.

Rectification/improvement was observed during the follow-up audit session on 4 August 2015.

28/07/2015

Provide acoustic decoupling measures for the generator on barge at P7.

Rectification/improvement was observed during the follow-up audit session on 4 August 2015.

28/07/2015

Ensure the noise enclosure is fully enclosed the equipment at P78.

Rectification/improvement was observed during the follow-up audit session on 4 August 2015.

Waste / Chemical Management

07/07/2015

Clear the oil stains at P74.

Rectification/improvement was observed during the follow-up audit session on 14 July 2015.

14/07/2015

Provide tarpaulin sheet at underneath of pressure relief joint to avoid oil spillage at P20.

Rectification/improvement was observed during the follow-up audit session on 21 July 2015.

14/07/2015

Provide drip tray for the generator at P20.

Rectification/improvement was observed during the follow-up audit session on 21 July 2015.

14/07/2015

Clear the rubbish at near container office (P113).

Rectification/improvement was observed during the follow-up audit session on 21 July 2015.

21/07/2015

Clear the accumulated construction wastes at P84 and P85.

Rectification/improvement was observed during the follow-up audit session on 28 July 2015.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark:       N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 293m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.