2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection.
The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau
Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual
3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting
with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under
separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard
shoulder for each bound of carriageway and a utilities trough on the outer edge
of each bound of viaducts;
¡P
a grade-separated turnaround facility located
near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including,
but not limited to, meteorological enhancement measures including the
provisioning of anemometers and modification of the wind profiler station at
hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and
provisioning of security systems; and
¡P
associated civil, structural, geotechnical,
marine, environmental protection, landscaping, drainage and highways electrical
and mechanical (E&M) works, street lightings, traffic aids and sign
gantries, marine navigational aids, ship impact protection system, water mains
and fire hydrants, lightning protection system, structural health monitoring
and maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) ¡V Cinotech
Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
|
Party |
Position |
Position |
Phone
No. |
Fax
No. |
|
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
|
Mr. Colin Meadows |
3767 5801 |
|||
|
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
|
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
|
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
|
24-hour Hotline |
-- |
6898 6161 |
-- |
|
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) P81L&R - 5 pours of column
were completed.
(b) P82L - ELS excavation works is in
progress.
(c) P82R - Pile cap was completed,
column work is in progress.
(d) P83L - ELS excavation works is in
progress.
(e) P83R ¡V Column works was completed.
(f) Portal Works:
|
Pier
Location |
Progress |
|
P84 |
Formwork
erection is in progress |
|
P85 |
Falsework
and formwork erection is in progress |
|
P86 |
Portal
was concreted on 26 August 2015 |
|
P89 |
Portal
was cast on 31 July 2015. Removal of formwork and falsework is in progress |
|
P90 |
Portal
was concreted on 30 June 2015 Removal
of falsework and steel beams are in progress |
|
P91 |
Portal
was cast on 9 June 2015 Removal
of steel cross beams and brackets at L-side was completed |
|
P92 |
Portal
was concreted on 17 July 2015. Removal of falsework is in progress |
Marine Viaduct (P0 to P80)
Progress at P68
(a) P68 ¡V R3
and R6 were cast, total 10 piles were complete.
(b) One RCD was set up on R1 casing on 27 Aug
2015 for socket drilling.
Progress at P69
(a) Sheetpiling works at
R-side is in progress.
(b) Sheetpiling works at
L-side was completed. Shear pins in L-side is in progress. Fabrication of
L-side 1st and 2nd layer waling and struts works are in
progress.
Progress at P75
(a) Excavation
to formation at the L-side continues.
Pile Cap Construction
(a) Precast shells installation ¡V 6
CP1 at P5, P9, P10 and 2 CP3 at P56.
(b) Stage 1 concreting was completed
at P6, P8, P9 &P26L.
(c) Stage 1 works is in progress at
P5 and P56.
(d) Stage 2 concreting was completed
at P2R, P57, P79L and P80.
(e) Stage 2 works is in progress at
P6, P9 and P26L.
(f) Kingpost installation and
associated steel welding works for precast shelll
installation are in progress at D17L.
(g) Advanced concrete trimming
(inside casing) works were carried out at P10, D17R, D18L&R, D19L,
D20L&R, concrete trimming (inside cap shell) were carried out at P6 and P56.
(h) Submerged pile cap works with cofferdam:
|
Pier
Location |
Side |
Progress |
|
P72 |
L |
Backfilling
and removal of cofferdam completed on 20-Aug-15 |
|
R |
Backfilling
and removal of cofferdam completed on 20-Aug-15 |
|
|
P74 |
L |
Concreting
works of pile cap completed on 21-Aug-15 |
|
R |
Excavation
around the footprint of pile cap completed and additional of protection
concrete wall was casted Blinding
layer was casted on 21-Aug-15 Trimming
of pile head concrete is in progress |
|
|
P75 |
L |
Rock
excavation is in progress |
|
R |
Rock
excavation is in progress |
In-situ Column
(Single) Construction
(a) 1st lift works is in progress at P2 & P11.
(b) 1st lift concrete was poured at P11, P13, P55, P54-Ramp & P58-Ramp.
(c) 2nd lift works is in progress at P55, P54-Ramp & P58-Ramp.
(d) 2nd lift concrete was poured at P78.
(e) 3rd life works is in progress at P78.
(f) Pier head works is in progress at P54, P58 & P70.
(g) Pier head concrete was poured at P58 & P70.
Precast Column
Erection
|
Description |
Location completed in this reporting period |
Number of Units erected/ Number of Columns
completed in this reporting period |
Cumulative No. of Piers completed (up to 28th of each month) |
|
Commencement (ie. starting from 1st precast unit) |
P14, P15 |
24 (P14-P16, P21, P24, P25,
P27-P44) |
Commencement (ie. starting from 1st precast unit) |
|
Completion (ie.completed
installation of pier head unit) |
P25, P27 |
19 (P25, P27-P44) |
Completion (ie.completed
installation of pier head unit) |
|
Vertical Tendons Stressed |
P30 (50%) |
15.5 (P28, P29, P30, P32(1/2),
P33-P44) |
Vertical Tendons Stressed |
|
Grouting Vertical Tendons |
P29, P30, P35 |
14 (P28-P30, P34-P44) |
Grouting Vertical Tendons |
|
Pier Head Concrete |
P36-P38 |
9 (P36-P44) |
Pier Head Concrete |
In-situ Double Blade
Column Construction
|
Pier
Location |
Side |
Progress |
|
P17 |
L |
Poured concrete up to 4th
lift and started to construct 5th lift |
|
R |
Poured concrete up to 4th
lift and started to construct 5th lift |
|
|
P76 |
L |
Poured concrete up to 2nd
lift and 3rd lift in progress |
|
R |
Poured concrete up to 3rd
lift and started to construct pierhead |
|
|
P77 |
L |
Poured concrete up to 3rd
lift and started to construct pierhead |
|
R |
Poured concrete up to 3rd
lift and started to construct pierhead |
|
|
P79 |
L |
Commenced in this reporting
period |
|
R |
Commenced in this reporting
period |
Deck Erection
(a)
Setting up of Equipment:
|
Type of
Equipment |
Status |
|
Lifting Frames 1 (LF1) |
Assembly
of first two sets of LF1 at WA4 almost completed. Assembly
of the third and fourth set of LF1 is on-going at WA4 Completion
of assembly is targeted by end of September |
|
Lifting Frames 3 (LF3) |
First
set of LF3 has started operation at P64 Second
set of machines is being assembled at WA4 and is targeted to be completed in
early September |
|
Launching Gantry 1 (LG1) |
Segment
erection from P114 to P106 completed |
|
Launching Gantry 2 (LG2) |
No segment erection since 27
July 2015 due to machine breakdown |
(b)
Segment erection:
|
Type |
Location
of Segments erected in this reporting period |
Number
of Segments erected in this reporting period |
Cumulative
No. of Segments erected (up to
28th of each month) |
|
LG1* |
P106 |
28 |
330 |
|
LG2 |
- |
0 |
160 |
|
LF3 |
P64 |
25 |
32 |
|
Typical Span SOP |
P41,P42,
P49 |
12 |
56 |
|
Long Span SOP |
P19 |
6 |
12 |
* includes crane erection for P109
Precast Segment
(a)
Segment Casting:
-
Production affected by inclement weather (5.5 days).
-
L/S segments temporary stored at CCCC4¡¦s Machong yard.
-
Off yard storage extension is in progress.
-
All types of segment moulds (34nos) were resumed
works on 27 Aug 15.
-
6 nos. of segments at storage line 3 were toppled
on 13 July 2015. The 6 damaged segments were removed and re-casting of the new
segments are in progress.
-
Line 1 modification of L/S storage ground beam for
MCH1 segment in progress.
|
Item |
Number
in this reporting period |
Cumulative
No. of Precast Segment Completed (up to
28th of each month) |
|
Segment Cast |
93 |
2455 |
(b)
Off-site Storage:
|
Area |
No. in
Off-site Storage |
|
A1 |
134 (A) |
|
A2 |
206
(A) |
|
A3 |
237
(A, B, E) |
|
A4 |
116(L/S)
& 16(D) |
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
|
Type of
Shell |
Number
of Precast Shell Cast in this reporting period |
Cumulative
No. of Precast Shell Completed (up to
28th of each month) |
|
CP1 |
Completed |
94 |
|
CP2 |
Completed |
12 |
|
CP3 |
Completed |
14 |
|
CP4 |
Completed |
8 |
|
CP5 |
Completed |
6 |
|
CP6 |
Completed |
4 |
|
CP11 |
Completed |
1 |
|
CP12 |
Completed |
1 |
|
F1 & F1A |
0 |
2 |
|
F2 & F2A |
1 |
1 |
Precast Column &
Precast Pier Head Casting
(a)
Progress of the precast column & precast pier
head casting:
- All casting works for the 6m piers, monolithic pier heads were
completed.
- Totally 16 precast units (10 piers with 6m high, 6 monolithic pier
heads) were cast in this reporting period.
- Cumulatively 293 precast units were cast.
- Precast pier head 2-R-H would be re-cast around September.
Delivery for Precast Concrete Elements (by barge)
(a)
Precast Deck Segments:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 14
(2 barges tied up on L/S storage)
-
Number of deck segment deliveries
in this period: 21 trips
-
Cumulative number of deck
segment deliveries: 137 trips
|
Segment
Types |
Segment
Delivered in this reporting period |
Cumulative
No. of Precast Segment Delivered (up to
28th of each month) |
|
A |
45 |
269 |
|
B |
0 |
0 |
|
C |
12 |
18 |
|
D |
5 |
9 |
|
E |
36 |
378 |
(b)
Precast column units:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 2
-
Number of column unit deliveries in this period: 2
trips
-
Cumulative number of column unit deliveries: 35
trips
|
Unit
Types |
Number
of units delivered in this reporting period |
Cumulative
No. of Precast Column Delivered (up to
28th of month) |
|
3m |
0 |
23 |
|
6m |
8 |
94 |
|
PH1 |
4 |
26 |
|
PH2 |
0 |
14 |
(c)
Temporary storage of long span segments:
-
2 barges remain with long span
stored with P20 +1, +2. These barges will not unload at CCCC4 and the segments
will remain stored on the barges until required for delivery to Hong Kong which
is estimated to be mid to late September 2015.
(d)
General:
-
Delivery to LG2 has been
interrupted by mechanical failure of support jacks during this period.
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
|
Permit
/ License No. |
Valid
Period |
Status |
|
|
From |
To |
||
|
Environmental Permit (EP) |
|||
|
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
|
Consruction Noise Permit
(CNP) |
|||
|
P76 ¡V P80: GW-RS0094-15 |
03/02/2015(01:30) |
02/08/2015(08:00) |
Expired |
|
P0 ¡V P68: GW-RS0130-15 |
10/02/2015(19:00) |
08/08/2015(24:00) |
Expired |
|
Waters next to Southeast Quay: GW-RS0181-15 |
23/02/2015(19:00) |
22/08/2015(23:00) |
Expired |
|
P53 ¡V P59: GW-RS0314-15 |
31/03/2015(00:00) |
30/09/2015(07:00) |
Valid |
|
WA4: GW-RW0207-15 |
29/04/2015(19:00) |
28/10/2015(23:00) |
Valid |
|
P86: GW-RS0460-15 |
04/05/2015(00:00) |
31/08/2015(05:30) |
Valid |
|
P100 ¡V P111: GW-RS0487-15 |
07/05/2015(23:00) |
06/11/2015(07:00) |
Valid |
|
P69 ¡V P74: GW-RS0584-15 |
01/06/2015(00:00) |
30/11/2015(24:00) |
Valid |
|
P101 ¡V P114: GW-RS0715-15 |
07/07/2015(19:00) |
31/10/2015(05:30) |
Valid |
|
P0 ¡V P68: GW-RS0783-15 |
17/07/2015(19:00) |
13/01/2016(24:00) |
Valid |
|
P81 ¡V 83: GW-RS0814-15 |
30/07/2015(19:00) |
29/01/2016(24:00) |
Valid |
|
P81 ¡V 115: GW-RS0818-15 |
29 /07/2015(19:00) |
28/01/2016(23:00) |
Valid |
|
P75 ¡V 80: GW-RS0829-15 |
30 /07/2015(19:00) |
31/12/2015(24:00) |
Valid |
|
Portion A: GW-RS0884-15 |
23/08/2015 (07:00) |
22/02/2016 (23:00) |
Valid |
|
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
|
345773 |
N/A |
Receipt acknowledged by EPD |
|
|
Billing Account for Construction Waste
Disposal |
|||
|
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
|
A/C# 7016948 (Vessel Disposal) |
22/05/2015 |
31/08/2015 |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
|
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
|
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
|
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
|
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
|
Portion C:
WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
|
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
|
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
|
WA7:
WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
|
P0 ¡V P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
|
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
|
P81-P83: WT00021946-2015 |
08/07/2015 |
31/07/2020 |
Valid |
|
Marine Dumping Permit |
|||
|
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1 ¡V Open Sea Disposal) marine sediment EP/MD/15-226 |
11/02/2015 |
09/08/2015 |
Expired |
|
Cross-border dumping of dredged sediment
of Category L and Category Mp at Erzhou Island in China EP/MD/16-045 |
21/07/2015 |
20/08/2015 |
Expired |