2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

¡P           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

¡P           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

¡P           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

¡P           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer¡¦s Representative (SOR) ¡V Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor ¡VDragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) ¡V Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Ramboll Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Environ Hong Kong Limited (Ramboll Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor¡¦s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      P81L&R - 5 pours of column were completed.

(b)     P82L - ELS excavation works is in progress.

(c)      P82R - Pile cap was completed, column work is in progress.

(d)     P83L - ELS excavation works is in progress.

(e)      P83R ¡V Column works was completed.

(f)      Portal Works:

Pier Location

Progress

P84

Formwork erection is in progress

P85

Falsework and formwork erection is in progress

P86

Portal was concreted on 26 August 2015

P89

Portal was cast on 31 July 2015. Removal of formwork and falsework is in progress

P90

Portal was concreted on 30 June 2015

Removal of falsework and steel beams are in progress

P91

Portal was cast on 9 June 2015

Removal of steel cross beams and brackets at L-side was completed

P92

Portal was concreted on 17 July 2015. Removal of falsework is in progress

 

Marine Viaduct (P0 to P80)

Progress at P68

(a) P68 ¡V R3 and R6 were cast, total 10 piles were complete.

(b)  One RCD was set up on R1 casing on 27 Aug 2015 for socket drilling.

 

Progress at P69

(a)    Sheetpiling works at R-side is in progress.

(b)   Sheetpiling works at L-side was completed. Shear pins in L-side is in progress. Fabrication of L-side 1st and 2nd layer waling and struts works are in progress.

 


Progress at P75

(a)    Excavation to formation at the L-side continues.

 

Pile Cap Construction

(a)    Precast shells installation ¡V 6 CP1 at P5, P9, P10 and 2 CP3 at P56.

(b)   Stage 1 concreting was completed at P6, P8, P9 &P26L.

(c)    Stage 1 works is in progress at P5 and P56.

(d)   Stage 2 concreting was completed at P2R, P57, P79L and P80.

(e)    Stage 2 works is in progress at P6, P9 and P26L.

(f)    Kingpost installation and associated steel welding works for precast shelll installation are in progress at D17L.

(g)   Advanced concrete trimming (inside casing) works were carried out at P10, D17R, D18L&R, D19L, D20L&R, concrete trimming (inside cap shell) were carried out at P6 and P56.

 (h)       Submerged pile cap works with cofferdam:

Pier Location

Side

Progress

P72

L

Backfilling and removal of cofferdam completed on 20-Aug-15

R

Backfilling and removal of cofferdam completed on 20-Aug-15

P74

L

Concreting works of pile cap completed on 21-Aug-15

R

Excavation around the footprint of pile cap completed and additional of protection concrete wall was casted

Blinding layer was casted on 21-Aug-15

Trimming of pile head concrete is in progress

P75

L

Rock excavation is in progress

R

Rock excavation is in progress

 

In-situ Column (Single) Construction

(a)    1st lift works is in progress at P2 & P11.

(b)   1st lift concrete was poured at P11, P13, P55, P54-Ramp & P58-Ramp.

(c)    2nd lift works is in progress at P55, P54-Ramp & P58-Ramp.

(d)   2nd lift concrete was poured at P78.

(e)    3rd life works is in progress at P78.

(f)    Pier head works is in progress at P54, P58 & P70.

(g)   Pier head concrete was poured at P58 & P70.

 

Precast Column Erection

Description

Location completed in this reporting period

Number of Units erected/ Number of Columns completed in this reporting period

Cumulative No. of Piers completed

(up to 28th of each month)

Commencement

(ie. starting from 1st precast unit)

P14, P15

24 (P14-P16, P21, P24, P25, P27-P44)

Commencement

(ie. starting from 1st precast unit)

Completion

(ie.completed installation of pier head unit)

P25, P27

19 (P25, P27-P44)

Completion

(ie.completed installation of pier head unit)

Vertical Tendons Stressed

P30 (50%)

15.5 (P28, P29, P30, P32(1/2), P33-P44)

Vertical Tendons Stressed

Grouting Vertical Tendons

P29, P30, P35

14 (P28-P30, P34-P44)

Grouting Vertical Tendons

Pier Head Concrete

P36-P38

9 (P36-P44)

Pier Head Concrete

 

In-situ Double Blade Column Construction

Pier Location

Side

Progress

P17

L

Poured concrete up to 4th lift and started to construct 5th lift

R

Poured concrete up to 4th lift and started to construct 5th lift

P76

L

Poured concrete up to 2nd lift and 3rd lift in progress

R

Poured concrete up to 3rd lift and started to construct pierhead

P77

L

Poured concrete up to 3rd lift and started to construct pierhead

R

Poured concrete up to 3rd lift and started to construct pierhead

P79

L

Commenced in this reporting period

R

Commenced in this reporting period

 

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

 

Lifting Frames 1 (LF1)

Assembly of first two sets of LF1 at WA4 almost completed.

Assembly of the third and fourth set of LF1 is on-going at WA4

Completion of assembly is targeted by end of September

 

Lifting Frames 3

(LF3)

First set of LF3 has started operation at P64

Second set of machines is being assembled at WA4 and is targeted to be completed in early September

 

Launching Gantry 1 (LG1)

Segment erection from P114 to P106 completed

 

Launching Gantry 2

 

(LG2)

No segment erection since 27 July 2015 due to machine breakdown

 


 

(b)     Segment erection:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

LG1*

P106

28

330

LG2

-

0

160

LF3

P64

25

32

Typical Span SOP

P41,P42, P49

12

56

Long Span SOP

P19

6

12

          *  includes  crane erection for P109

 

Precast Segment

(a)      Segment Casting:

-            Production affected by inclement weather (5.5 days).

-            L/S segments temporary stored at CCCC4¡¦s Machong yard.

-            Off yard storage extension is in progress.

-            All types of segment moulds (34nos) were resumed works on 27 Aug 15.

-            6 nos. of segments at storage line 3 were toppled on 13 July 2015. The 6 damaged segments were removed and re-casting of the new segments are in progress.

-            Line 1 modification of L/S storage ground beam for MCH1 segment in progress.

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

93

2455

 

(b)     Off-site Storage:

Area

No. in Off-site Storage

A1

134 (A)

A2

206 (A)

A3

237 (A, B, E)

A4

116(L/S) & 16(D)

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

CP1

Completed

94

CP2

Completed

12

CP3

Completed

14

CP4

Completed

8

CP5

Completed

6

CP6

Completed

4

CP11

Completed

1

CP12

Completed

1

F1 & F1A

0

2

F2 & F2A

1

1

 

Precast Column & Precast Pier Head Casting

(a)      Progress of the precast column & precast pier head casting:

-     All casting works for the 6m piers, monolithic pier heads were completed.

-      Totally 16 precast units (10 piers with 6m high, 6 monolithic pier heads) were cast in this reporting period.

-      Cumulatively 293 precast units were cast.

-      Precast pier head 2-R-H would be re-cast around September.

Delivery  for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 14 (2 barges tied up on L/S storage)

-             Number of deck segment deliveries in this period: 21 trips

-             Cumulative number of deck segment deliveries: 137 trips

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

45

269

B

0

0

C

12

18

D

5

9

E

36

378

(b)     Precast column units:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 2

-             Number of column unit deliveries in this period: 2 trips

-             Cumulative number of column unit deliveries: 35 trips

 

Unit Types

Number of units delivered in this reporting period

Cumulative No. of Precast Column Delivered

(up to 28th of month)

3m

0

23

6m

8

94

PH1

4

26

PH2

0

14

 

(c)      Temporary storage of long span segments:

-            2 barges remain with long span stored with P20 +1, +2. These barges will not unload at CCCC4 and the segments will remain stored on the barges until required for delivery to Hong Kong which is estimated to be mid to late September 2015.

(d)     General:

-       Delivery to LG2 has been interrupted by mechanical failure of support jacks during this period.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/D

22/12/2014

N/A

Valid

Consruction Noise Permit (CNP)

P76 ¡V P80: GW-RS0094-15

03/02/2015(01:30)

02/08/2015(08:00)

Expired

P0 ¡V P68: GW-RS0130-15

10/02/2015(19:00)

08/08/2015(24:00)

Expired

Waters next to Southeast Quay: GW-RS0181-15

23/02/2015(19:00)

22/08/2015(23:00)

Expired

P53 ¡V P59: GW-RS0314-15

31/03/2015(00:00)

30/09/2015(07:00)

Valid

WA4: GW-RW0207-15

29/04/2015(19:00)

28/10/2015(23:00)

Valid

P86: GW-RS0460-15

04/05/2015(00:00)

31/08/2015(05:30)

Valid

P100 ¡V P111: GW-RS0487-15

07/05/2015(23:00)

06/11/2015(07:00)

Valid

P69 ¡V P74: GW-RS0584-15

01/06/2015(00:00)

30/11/2015(24:00)

Valid

P101 ¡V P114: GW-RS0715-15

07/07/2015(19:00)

31/10/2015(05:30)

Valid

P0 ¡V P68: GW-RS0783-15

17/07/2015(19:00)

13/01/2016(24:00)

Valid

P81 ¡V 83: GW-RS0814-15

30/07/2015(19:00)

29/01/2016(24:00)

Valid

P81 ¡V 115: GW-RS0818-15

29 /07/2015(19:00)

28/01/2016(23:00)

Valid

P75 ¡V 80: GW-RS0829-15

30 /07/2015(19:00)

31/12/2015(24:00)

Valid

Portion A: GW-RS0884-15

23/08/2015 (07:00)

22/02/2016 (23:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

22/05/2015

31/08/2015

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 ¡V P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

P81-P83: WT00021946-2015

08/07/2015

31/07/2020

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1 ¡V Open Sea Disposal)  marine sediment

EP/MD/15-226

11/02/2015

09/08/2015

 

 

Expired

Cross-border dumping of dredged sediment of Category L and Category Mp at Erzhou Island in China

EP/MD/16-045

21/07/2015

20/08/2015

 

 

Expired