7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 4th, 11th, 18th and 25th August 2015 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 25th August 2015. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 10th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 23th June 2015 and next inspection will be conducted in September 2015.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1        Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

04/08/2015

To repair the damaged silt curtain at P69.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

04/08/2015

Properly deploy the silt curtain at P68.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

04/08/2015

Clear the foam box and wooden board within the silt curtain at near P107.

Rectification/improvement was observed during the follow-up audit session on 11 August 2015.

11/08/2015

Provide bund at the boundary of WA4 to avoid the muddy water discharging into the sea.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

11/08/2015

Clear the rubbish at the seawall area near P98.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

11/08/2015

Properly deploy the silt curtain at P68 and P69.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

18/08/2015

Clear the concrete debris at P17 and P20.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

25/08/2015

Clear the loose material which hanging at the boundary of P54.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

25/08/2015

Clear the concrete materials at the platform and repair the iron wire gauze at P58.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

25/08/2015

Properly deploy the silt curtain at P74.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

N/A(1)

N/A(1)

N/A(1)

Noise

18/08/2015

Provide noise emission label for the air compressor at P20.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

Waste / Chemical Management

04/08/2015

To store and dispose the empty chemical containers at P70 properly.

Rectification/improvement was observed during the follow-up audit session on 11 August 2015.

04/08/2015

Clear the oil spillage at P70.

Rectification/improvement was observed during the follow-up audit session on 11 August 2015.

04/08/2015

Clear the accumulated rubbish at near the site entrance (P111).

Rectification/improvement was observed during the follow-up audit session on 11 August 2015.

04/08/2015

Properly repair the scissor platform (segment carrier) to avoid oil leakage at near P108.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

11/08/2015

Provide drip tray for the chemical container at WA4 and Portion C.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

11/08/2015

Clear the oil spillage at near P112.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

11/08/2015

Properly repair the scissor platform (segment carrier) to avoid oil leakage at near P108.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

11/08/2015

Clear the accumulated rubbish at near P107.

Rectification/improvement was observed during the follow-up audit session on 18 August 2015.

18/08/2015

Clear the oil leakage and provide drip tray for the oil container at P17.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

18/08/2015

Clear the rubbish at the roro barge next to P17.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

18/08/2015

Clear the oil spillage at the roro barge next to P17.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

18/08/2015

Provide drip tray for the chemical containers at P20.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

18/08/2015

Clear the stagnant water at the drip tray at P20.

Rectification/improvement was observed during the follow-up audit session on 25 August 2015.

25/08/2015

Clear the rubbish at the barge next to P58.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

25/08/2015

Provide drip tray for the chemical containers at the barge next to P58 and at P58.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

25/08/2015

Clear the oil spillage as chemical waste at the barge next to P58.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

25/08/2015

Clear the contaminated sand around the generator at P74.

Rectification/improvement was observed during the follow-up audit session on 1 September 2015.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 764m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.