Table 7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
01/09/2015 |
Sedimentation facilities according to the
wastewater discharge license at P81 and P82 was not operated. The Contractor
was reminded to rectify it as soon as possible. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
01/09/2015 |
To check the designated discharging location for
treated effluent at Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 8 September 2015. |
|
08/09/2015 |
Properly deploy the silt curtain at P74, P69 and
P70. |
Rectification/improvement
was observed during the follow-up audit session on 15 September 2015. |
|
08/09/2015 |
Ensure the wetsep at P81 is functioning properly
to treat the muddy water. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
15/09/2015 |
Clear the accumulated concrete debris at the
platform at P20. |
Rectification/improvement
was observed during the follow-up audit session on 22 September 2015. |
|
15/09/2015 |
Clear the discarded iron bar at the seawall area
at P100. |
Rectification/improvement
was observed during the follow-up audit session on 22 September 2015. |
|
15/09/2015 |
Clear the foam box and wooden board at the
seawall area at P96. |
Rectification/improvement
was observed during the follow-up audit session on 22 September 2015. |
|
30/09/2015 |
Floating rubbish was observed near P75. The
Contractor was reminded to clear it properly. |
Rectification/improvement
was observed during the follow-up audit session on 6 October 2015. |
|
30/09/2015 |
The Contractor was reminded to improve the
discharge quality at P82/P83. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
Ecology |
01/09/2015 |
To erect the fencing for protecting tree and
clear the construction wastes / materials within the tree protection zone at
between P86&P87, P91 and S8 entrance. |
Rectification/improvement
was not observed during the follow-up audit session on 15 September 2015. |
22/09/2015 |
To remove the construction materials under the
retained trees and provide a proper tree protection zone. |
Rectification/improvement
was observed during the follow-up audit session on 30 September 2015. |
|
Air Quality |
01/09/2015 |
Provide maintenance of the crane to avoid
emitting heavy smoke at P71. |
Rectification/improvement
was observed during the follow-up audit session on 8 September 2015. |
15/09/2015 |
Provide water spray
for the dry exposed site area at Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 22 September 2015. |
|
Noise |
01/09/2015 |
To close the door of the crane at P71. |
Rectification/improvement
was observed during the follow-up audit session on 8 September 2015. |
Waste / Chemical Management |
01/09/2015 |
To seal the hole of
the drip tray at P71. |
Rectification/improvement
was observed during the follow-up audit session on 8 September 2015. |
01/09/2015 |
Provide spill kit for oil leakage at P71. |
Rectification/improvement
was observed during the follow-up audit session on 8 September 2015. |
|
01/09/2015 |
Properly store the chemical containers at between
P105 and P106. |
Rectification/improvement
was observed during the follow-up audit session on 8 September 2015. |
|
08/09/2015 |
Provide spill kit at
the platform at P74. |
Rectification/improvement
was observed during the follow-up audit session on 15 September 2015. |
|
08/09/2015 |
Clear the construction wastes at P70. |
Rectification/improvement
was observed during the follow-up audit session on 15 September 2015. |
|
08/09/2015 |
Clear the oil spillage and maintenance of
equipment are required to avoid oil leakage at P69. |
Rectification/improvement
was observed during the follow-up audit session on 15 September 2015. |
|
08/09/2015 |
Clear the damaged handrail at near the seawall
area at P87. |
Rectification/improvement
was observed during the follow-up audit session on 15 September 2015. |
|
15/09/2015 |
Clear the rubbish
which was not disposed properly at the platform at P20. |
Rectification/improvement
was observed during the follow-up audit session on 22 September 2015. |
|
15/09/2015 |
Provide drip tray for the chemical containers at
the platform at P20. |
Rectification/improvement
was observed during the follow-up audit session on 22 September 2015. |
|
22/09/2015 |
Properly store the chemical containers at Portion
C. |
Rectification/improvement
was observed during the follow-up audit session on 30 September 2015. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
08/09/2015 |
Provide valid
construction noise permit at P70. |
Rectification/improvement
was observed during the follow-up audit session on 15 September 2015. |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological Site) |
21/09/2015 |
N/A(1) |
N/A(1) |
Remark: N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.