Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

01/09/2015

Sedimentation facilities according to the wastewater discharge license at P81 and P82 was not operated. The Contractor was reminded to rectify it as soon as possible.

Rectification/improvement

was not observed during the

follow-up audit sessions. Further follow-up on this item is required.

01/09/2015

To check the designated discharging location for treated effluent at Portion C.

Rectification/improvement was observed during the follow-up audit session on 8 September 2015.

08/09/2015

Properly deploy the silt curtain at P74, P69 and P70.

Rectification/improvement was observed during the follow-up audit session on 15 September 2015.

08/09/2015

Ensure the wetsep at P81 is functioning properly to treat the muddy water.

Rectification/improvement

was not observed during the

follow-up audit sessions. Further follow-up on this item is required.

15/09/2015

Clear the accumulated concrete debris at the platform at P20.

Rectification/improvement was observed during the follow-up audit session on 22 September 2015.

15/09/2015

Clear the discarded iron bar at the seawall area at P100.

Rectification/improvement was observed during the follow-up audit session on 22 September 2015.

15/09/2015

Clear the foam box and wooden board at the seawall area at P96.

Rectification/improvement was observed during the follow-up audit session on 22 September 2015.

30/09/2015

Floating rubbish was observed near P75. The Contractor was reminded to clear it properly.

Rectification/improvement was observed during the follow-up audit session on 6 October 2015.

30/09/2015

The Contractor was reminded to improve the discharge quality at P82/P83.

Rectification/improvement

was not observed during the

follow-up audit sessions. Further follow-up on this item is required.

Ecology

01/09/2015

To erect the fencing for protecting tree and clear the construction wastes / materials within the tree protection zone at between P86&P87, P91 and S8 entrance.

Rectification/improvement was not observed during the follow-up audit session on 15 September 2015.

22/09/2015

To remove the construction materials under the retained trees and provide a proper tree protection zone.

Rectification/improvement was observed during the follow-up audit session on 30 September 2015.

Air Quality

01/09/2015

Provide maintenance of the crane to avoid emitting heavy smoke at P71.

Rectification/improvement was observed during the follow-up audit session on 8 September 2015.

15/09/2015

Provide water spray for the dry exposed site area at Portion C.

Rectification/improvement was observed during the follow-up audit session on 22 September 2015.

Noise

01/09/2015

To close the door of the crane at P71.

Rectification/improvement was observed during the follow-up audit session on 8 September 2015.

Waste / Chemical Management

01/09/2015

To seal the hole of the drip tray at P71.

Rectification/improvement was observed during the follow-up audit session on 8 September 2015.

01/09/2015

Provide spill kit for oil leakage at P71.

Rectification/improvement was observed during the follow-up audit session on 8 September 2015.

01/09/2015

Properly store the chemical containers at between P105 and P106.

Rectification/improvement was observed during the follow-up audit session on 8 September 2015.

08/09/2015

Provide spill kit at the platform at P74.

Rectification/improvement was observed during the follow-up audit session on 15 September 2015.

08/09/2015

Clear the construction wastes at P70.

Rectification/improvement was observed during the follow-up audit session on 15 September 2015.

08/09/2015

Clear the oil spillage and maintenance of equipment are required to avoid oil leakage at P69.

Rectification/improvement was observed during the follow-up audit session on 15 September 2015.

08/09/2015

Clear the damaged handrail at near the seawall area at P87.

Rectification/improvement was observed during the follow-up audit session on 15 September 2015.

15/09/2015

Clear the rubbish which was not disposed properly at the platform at P20.

Rectification/improvement was observed during the follow-up audit session on 22 September 2015.

15/09/2015

Provide drip tray for the chemical containers at the platform at P20.

Rectification/improvement was observed during the follow-up audit session on 22 September 2015.

22/09/2015

Properly store the chemical containers at Portion C.

Rectification/improvement was observed during the follow-up audit session on 30 September 2015.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

08/09/2015

Provide valid construction noise permit at P70.

Rectification/improvement was observed during the follow-up audit session on 15 September 2015.

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

21/09/2015

N/A(1)

N/A(1)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.