Table 7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
06/10/2015 |
The wastewater which pumping out from the pit
area near P111 should be properly treated before discharging out. |
Rectification/improvement
was observed during the follow-up audit session on 13 October 2015. |
06/10/2015 |
To replace the worn sand bags for protecting the
gully at P82. |
Rectification/improvement
was observed during the follow-up audit session on 13 October 2015. |
|
13/10/2015 |
Leakage of muddy water was observed from the
cofferdam at P69. The Contractor was reminded to repair the damaged silt
curtain to prevent the muddy water discharging to the sea. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
13/10/2015 |
Properly deploy the silt curtain at P82 and P106. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
20/10/2015 |
Muddy water was observed outside the silt curtain
at P69. The Contractor was reminded to check the source of leakage and
provide mitigation measures to rectify this deficiency as soon as possible. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
20/10/2015 |
The drainage system at Portion C and P82 should
be reviewed and re-arranged to ensure all wastewater from site is collected
and treated before discharging out. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
20/10/2015 |
To seal the base of water barrier with cement at
P110. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
Ecology |
06/10/2015 |
To erect the fencing for protecting trees at P102
and P91. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
13/10/2015 |
To erect the fencing
for protecting trees at P102 and P91. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
Air Quality |
06/10/2015 |
Clear the used cement bags at P110 or store it
properly (i.e. cover with tarpaulin etc.) before disposal. |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
13/10/2015 |
Properly cover the
cement bags (<20bags) with tarpaulin sheet at P110. (bridge-deck) |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
|
13/10/2015 |
Clear the used cement
bags regularly or store it properly (i.e. cover with tarpaulin sheet) before
disposal at P110. (bridge-deck) |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
|
20/10/2015 |
Ensure the grout
mixing area is fully enclosed with 3 sides and top shelter at P108
(bridge-deck). |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
28/10/2015 |
Debagged cement bags
were observed not covered properly at P79. The Contractor was reminded to
properly cover the debagged cement bags, e.g. sheltered on top and 3 sides. |
Rectification/improvement
was observed during the follow-up audit session on 3 November 2015. |
|
Noise |
N/A(1) |
N/A(1) |
N/A(1) |
Waste / Chemical Management |
06/10/2015 |
Clear the accumulated rubbish at near P107 and
P84. |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
06/10/2015 |
Provide drip tray for the chemical containers at
P84. |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
|
13/10/2015 |
Oil leakage from the mobile crane and excavator
was observed at P69 and P100 respectively. The Contractor was reminded to
repair the equipment to avoid further oil leakage. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
13/10/2015 |
Clear the accumulated rubbish / construction
wastes at P85, P86 and P87. |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
|
13/10/2015 |
Provide drip tray for the chemical containers at
P86. |
Rectification/improvement
was observed during the follow-up audit session on 20 October 2015. |
|
20/10/2015 |
Oil leakage from the mobile crane was observed at
P69. The Contractor was reminded to clear the oil spillage properly and
repair the mobile crane to avoid further oil leakage. |
Rectification/improvement was not observed during the follow-up audit sessions. Further follow-up on this item is required. |
|
28/10/2015 |
Oil container was
observed without label and proper drip tray at P45(LG2) and P54. The Contractor
was reminded to provide drip trays for oil containers and label it properly. |
Rectification/improvement
was observed during the follow-up audit session on 3 November 2015. |
|
28/10/2015 |
General refuse was
observed to accumulate at P54. The Contractor was reminded to clear the
accumulated waste. |
Rectification/improvement
was observed during the follow-up audit session on 3 November 2015. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.
N/A(2)
No archaeological site inspection was conducted in the reporting month.