2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

¡P           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

¡P           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

¡P           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

¡P           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer¡¦s Representative (SOR) ¡V Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor ¡VDragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) ¡V Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Ramboll Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Environ Hong Kong Limited (Ramboll Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor¡¦s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      P81R - Pier head was completed.

(b)     P82L - Pile cap was completed.

(c)      P82R - 5 pours of column were completed, pier head is to be constructed.

(d)     P83L - 1 pour of column was completed.

(e)      Portal Works:

Pier Location

Progress

P84

Portal concrete was poured on 14 October 2015. Removal of vertical formwork and temporary nailing works are in progress

P85

Removal of formwork and falsework is in progress

P86

Removal of steel bracket system was completed

P115

Installation of reinforcement to lower bearing plinth of AB-B3 was completed

 

Marine Viaduct (P0 to P80)

Progress at P68

(a) Pile testing works is completed.

(b) Right hand side (RHS): cofferdam sheetpiling in progress.

 

Progress at P69

(a)    RHS: 1st and 2nd waling and struts installed with excavation started.

(b)   Left hand side (LHS): Excavation in progress.

 

Progress at P75

(a)    RHS: Pile testing completed.

(b)   LHS: Piles no. L1, L3 and L4 casted. L2 RCD excavation in progress

 

Pile Cap Construction

(a)    Precast shells installation ¡V 4 dolphin type F1, F2, F1A and F2A shells at D17 and D18

(b)   Stage 1 concreting was completed at D17-F1, D17-F2 & D18-F2A.

(c)    Stage 1 works ¡V Nil

(d)   Stage 2 concreting - Nil

(e)    Stage 2 works ¡V D17-F2 & D17-F1

(f)    Kingpost installation and associated steel welding works for precast shell installation are in progress at D19-F2.

(g)   Advanced concrete trimming (inside casing) works: - Nil.

(h)   Concrete trimming (inside cap shell): - Nil

(i)     Submerged pile cap works with cofferdam:

Pier Location

Side

Progress

P75

L

Rock excavation is in progress

R

Rock excavation is in progress

P77

L

Backfilling and removal of cofferdam start on 13-Oct-15

R

Backfilling and removal of cofferdam start on 13-Oct-15

 

In-situ Column (Single) Construction

(a)    1st lift works is in progress at P8, P9, P10, P55-Ramp, P56,  P57, P57-Ramp and P75.

(b)   1st lift concrete was poured at P8, P26, P55 Ramp, P57, P57 Ramp and P74.

(c)    2nd lift works is in progress: P74 and P55 Ramp

(d)   2nd lift concrete pouring: Nil.

(e)    4th life works is in progress at P78.

(f)    Pier head works is in progress at P55.

 

Precast Column Erection

Description

Location completed in this reporting period

Number of Units erected/ Number of Columns completed in this reporting period

Cumulative No. of Piers completed

(up to 28th of each month)

Commencement

(i.e. starting from 1st precast unit)

P22

25 (P13 - P16, P21, P22, P24, P25, P27 - P44)

Commencement

(i.e. starting from 1st precast unit)

Completion

(i.e. completed installation of pier head unit)

P14-P16

23 (P14-P16, P24,P25, P27 - P44)

Completion

(i.e. completed installation of pier head unit)

Vertical Tendons Stressed

P25, P31

18 (P25, P28-P44)

Vertical Tendons Stressed

Grouting Vertical Tendons

P31

17 (P28-P44)

Grouting Vertical Tendons

Pier Head Concrete

P29, P33

13 (P29, P33 - P44)

Pier Head Concrete


 

In-situ Double Blade Column Construction

Pier Location

Side

Progress

P17

L

All cast in October 2015, total 7 lifts

R

All cast in October 2015, total 7 lifts

P76

L

All cast in October 2015, total 4 lifts (including pierhead)

P79

L

Poured concrete up to 1st lift and 2nd lift in progress

R

Poured concrete up to 1st lift and 2nd lift in progress

P80

L

Poured concrete up to 1st lift and started for 2nd lift

R

Poured concrete up to 1st lift and started for 2nd lift

 

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

 

Lifting Frames 1 (LF1)

First set of LF1 assembly completed

Second set of LF1 assembly almost completed

 

Lifting Frames 3

(LF3)

Segment erection on going at P63 and P65

New set installed at P62

 

Launching Gantry 1 (LG1)

Segment erection from P114 to P104 completed;

Segment erection on going at P103 and P102.

 

Launching Gantry 2

 

(LG2)

Eden portal gantry repaired

 

(b)     Segment erection:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

LG1*

P102, P103, P104

33

399

LG2

P43

40

240

LF3

P63, P64, P65

36

85

Typical Span SOP

P38, P35 and P34

12

80

Long Span SOP

P72

6

24

          *  includes  crane erection for P109

 

Precast Segment

(a)      Segment Casting:

-            Production affected by inclement weather (0 days).

-            Long span (L/S) segments temporary stored at CCCC4¡¦s Machong yard (A4).

-            Off yard storage extension (A2 & A3) for typical segments completed.

-            Line 1 & 6 modification of L/S storage ground beam for MCH1 segment in progress.

-            Additional line 0 storage for L/S segments is under construction.

-            L/S segments of P71 are loading on barges for temporary storage.

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

174

2831

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

CP1

Completed

94

CP2

Completed

12

CP3

Completed

14

CP4

Completed

8

CP5

Completed

6

CP6

Completed

4

CP11

Completed

1

CP12

Completed

1

F1 & F1A

1

3

F2 & F2A

2

4

 

Delivery for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-             Number of additional barges engaged in this period: 0

-             Number of deck segment deliveries in this period: 23 trips

-             Cumulative number of deck segment deliveries: 194 trips

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

76

410

B

0

0

C

2

24

D

5

17

E

24

450


(b)     Precast column units:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 1

-             Number of column unit deliveries in this period: 3 trips

-             Cumulative number of column unit deliveries: 41 trips

 

Unit Types

Number of units delivered in this reporting period

Cumulative No. of Precast Column Delivered

(up to 28th of month)

3m

4

27

6m

8

118

PH1

0

28

PH2

6

20

 

(c)      Temporary storage of long span segments:

-            2 barges remain with long span stored with segments for P20.

-            2 barges have been loaded with segments for P19 for temporary long span storage.

-            Four additional barges have been engaged to load P71 long span segments as temporary long span storage, of which three barges are have been loaded with P71 segments. The remaining barge (4th) is waiting for the arrival of the temporary support steal before loading can proceed.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/D

22/12/2014

N/A

Valid

Consruction Noise Permit (CNP)

WA4: GW-RW0207-15

29/04/2015(19:00)

28/10/2015(23:00)

Expired

P100 ¡V P111: GW-RS0487-15

07/05/2015(23:00)

06/11/2015(07:00)

Valid

P101 ¡V P114: GW-RS0715-15

07/07/2015(19:00)

31/10/2015(05:30)

Valid

P81 ¡V 83: GW-RS0814-15

30/07/2015(19:00)

29/01/2016(24:00)

Valid

P81 ¡V 115: GW-RS0818-15

29 /07/2015(19:00)

28/01/2016(23:00)

Valid

P75 ¡V 80: GW-RS0829-15

30 /07/2015(19:00)

31/12/2015(24:00)

Valid

Portion A: GW-RS0884-15

23/08/2015 (07:00)

22/02/2016 (23:00)

Valid

P0 ¡V P68: GW-RS0931-15

24/08/2015(19:00)

23/02/2016(24:00)

Cancelled on 6 October 2015

P69 ¡V P74: GW-RS0967-15

08/09/2015(19:00)

07/03/2016(24:00)

Valid

P86: GW-RS1015-15

01/10/2015(00:00)

30/11/2015(05:30)

Valid

P0 ¡V P68: GW-RS1075-15

06/10/2015(19:00)

05/04/2016(24:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

26/08/2015

30/11/2015

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 ¡V P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

P81-P83: WT00021946-2015

08/07/2015

31/07/2020

Valid

Marine Dumping Permit

Cross-border dumping of dredged sediment of Category L and Category Mp at Erzhou Island in China

EP/MD/16-066

08/09/2015

07/10/2015

 

 

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment at The Brothers Contaminated Mud Pits

EP/MD/16-088

09/10/2015

31/12/2015

 

 

Valid