7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 3rd, 10th, 17th and 25th November 2015 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 25th November 2015. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 11th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 21st September 2015 and next inspection will be conducted in December 2015.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

03/11/2015

Muddy water was observed outside the silt curtain at P69. The Contractor was reminded to enhance the water quality mitigation measures (e.g. provide double layer silt curtain etc) to minimize the water quality impact.

Rectification/improvement was observed during the follow-up audit session on 10 November 2015.

03/11/2015

Clear the deposited sand / sediment at the pontoon and Tapbo 329 at near P69.

Rectification/improvement was observed during the follow-up audit session on 10 November 2015.

03/11/2015

Replace the worn sand bags to protect the gully at between P82 and P83.

Rectification/improvement was observed during the follow-up audit session on 10 November 2015.

03/11/2015

Ensure the wetsep at near P82 is functioning properly.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

03/11/2015

Properly deploy the silt curtain at P106 and P98.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

03/11/2015

To direct the wastewater from the grouting mixing to the sedimentation tank at near P107.

Rectification/improvement was observed during the follow-up audit session on 10 November 2015.

10/11/2015

Clear the sedimentation tank to ensure it can function properly at P106 (Portion C).

Rectification/improvement was observed during the follow-up audit session on 17 November 2015.

10/11/2015

Clear the handrail at the seawall area at P106 (Portion A).

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

10/11/2015

Properly deploy the silt curtain at P106.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

10/11/2015

Clear the U-Channel at P102.

Rectification/improvement was not observed during the follow-up audit session. Further follow-up on this item is required.

10/11/2015

Ensure the wetsep at P82 can function properly before discharging the treated water.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

17/11/2015

Provide sufficient skip for temporary storage of concrete waste at Tung Shun 329.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

17/11/2015

Properly deploy the silt curtain at P106, P75, P81 and P68.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

17/11/2015

Ensure the wetsep at P82 can function properly before discharging the treated water.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

17/11/2015

Clear the construction wastes (handrail) at the seawall area at P103 and P106 (Portion A).

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

Ecology

03/11/2015

To erect the fencing for protecting the trees at P91.

Rectification/improvement was not observed during the follow-up audit session on 10 November 2015. Further follow-up on this item is required.

10/11/2015

Properly erect the fencing to protect the trees at P91 and P98.

Rectification/improvement was not observed during the follow-up audit session. Further follow-up on this item is required.

17/11/2015

Properly erect the fencing to protect the trees at P91 and P98.

Rectification/improvement at P91 was observed during the follow-up audit session on 25 November 2015. However, rectification/improvement at P98 was not observed during the follow-up audit session. Further follow-up on this item is required.

Air Quality

10/11/2015

Provide water spray for the excavation works at near P111 and dry exposed area at near P110.

Rectification/improvement was observed during the follow-up audit session on 17 November 2015.

17/11/2015

Properly cover the cement bags (>20 bags) and proper enclosures for grouting works at P113 (bridge-deck).

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

Noise

N/A(1)

N/A(1)

N/A(1)

Waste / Chemical Management

03/11/2015

Oil spillage was still observed at the platform at P69. The Contractor was reminded that oil leakage from the mobile crane should be avoided and sufficient spill kit should be provided on site.

Rectification/improvement was observed during the follow-up audit session on 17 November 2015.

03/11/2015

Provide drip tray for the chemical containers at near P105 and P110.

Rectification/improvement was observed during the follow-up audit session on 10 November 2015.

10/11/2015

Clear the accumulated wastes at P83.

Rectification/improvement was observed during the follow-up audit session on 17 November 2015.

10/11/2015

Clear the U-Channel at P102.

Rectification/improvement was not observed during the follow-up audit session. Further follow-up on this item is required.

17/11/2015

Provide drip tray for the chemical containers at P70.

Rectification/improvement was observed during the follow-up audit session on 25 November 2015.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark:     N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 470m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.