9.1
Major site activities for the coming reporting month will include:
WA4
Fabrication of lifting frames
Deliveries of frame structures
WA7
Fabrication of cofferdam frame structures
Marine
Viaduct (P0 to P80)
Remove rockfill
platform for rock breaking for
cofferdam installation
Completed concrete plug, cutting steel casing
and blinding concrete
Enhancement work to cofferdam to improve water
tightness
Pile testing
Pile
Cap Construction:
Installation of precast cap shells
Concreting
Kingpost installation and associated steel
welding works
Concreting trimming
Column
Construction:
Lifting works
Lift concreting
Pier head works
Pier head concreting
Precast
Column Erection
Installation of base units and precast units
Stressing of vertical nailing tendons
Vertical Tendons Stressed
Grouting Vertical Tendons
Pier Head Concrete
Deck
Erection
Setting up of equipment
Segment erection
Precast
Segment
Segment casting
Land
Viaduct (P81 to Abutment at Scenic Hill Tunnel (SHT))
Commencement of reinstatement works
Removal of falsework
Removal of steel bracket system
Construction of upper bearing plinths
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.