Table 7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
02/02/2016 |
Ensure the water pump can function properly to
pump the muddy water to the wetsep at P81. |
Rectification/improvement
was observed during the follow-up audit session on 11 February 2016. |
02/02/2016 |
To direct the wheel
washing water for treatment properly at P87. |
Rectification/improvement
was observed during the follow-up audit session on 11 February 2016. |
|
02/02/2016 |
To seal the gap at
bottom of hoarding at near the area for washing cement trucks (P110). |
Rectification/improvement
was observed during the follow-up audit session on 11 February 2016. |
|
Ecology |
02/02/2016 |
Properly erect the fencing to protect the trees
at P98. |
Rectification/improvement
was observed during the follow-up audit session on 11 February 2016. |
Air Quality |
18/02/2016 |
Clear the stockpile of
soil and debris at near the sea side at P89. |
Rectification/improvement
was observed during the follow-up audit session on 23 February 2016. |
18/02/2016 |
Properly
repair the enclosure for the grouting works at bridge surface. |
Rectification/improvement was not observed
during the follow-up audit session on 23 February 2016. Follow-up on this item is
required. |
|
23/02/2016 |
The three-side
enclosure with top shelter should be provided before commencement of grouting
works at P45. |
Rectification/improvement
was observed during the follow-up audit session on 1 March 2016. |
|
Noise |
N/A(1) |
N/A(1) |
N/A(1) |
Waste / Chemical Management |
02/02/2016 |
Clear the accumulated
rubbish at near the waste skip at P83. |
Rectification/improvement
was observed during the follow-up audit session on 11 February 2016. |
02/02/2016 |
Clear the chemical
waste container at near the discharging point at P106 (Portion C). |
Rectification/improvement
was observed during the follow-up audit session on 11 February 2016. |
|
11/02/2016 |
Clear the oily water
at the drip tray as chemical wastes at WA4 and WA3. |
Rectification/improvement
was observed during the follow-up audit session on 18 February 2016. |
|
18/02/2016 |
Clear the damage parts
of handrail at P93. |
Rectification/improvement
was observed during the follow-up audit session on 23 February 2016. |
|
18/02/2016 |
Clear the handrails at
the seawall area at P102. |
Rectification/improvement
was observed during the follow-up audit session on 23 February 2016. |
|
18/02/2016 |
Clear the accumulated
rubbish at P112. |
Rectification/improvement
was observed during the follow-up audit session on 23 February 2016. |
|
23/02/2016 |
Provide spill kit to
clear the the oil spillage properly at bridge
surface (P34 – P45). |
Rectification/improvement
was observed during the follow-up audit session on 1 March 2016. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1)
- No major environmental deficiency was identified during the site
inspection in the reporting month.
N/A(2) No archaeological site inspection
was conducted in the reporting month.