9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Cross Beam Precast Shell construction

 

WA7

Ÿ   Storage area

 

Marine Viaduct (P0 to P80)

Pile Cap Construction:

Ÿ   Concreting works

Ÿ   Steel re-bar fixing for pile cap

Ÿ   Enhancement works

 

Column Construction:

Ÿ   Lift concrete pouring

Ÿ   Pier head works

Ÿ   Pier head concreting

 

Precast Column Erection

Ÿ   Installation of base units and precast units

Ÿ   Stressing of vertical nailing tendons

Ÿ   Vertical Tendons Stressed

Ÿ   Grouting Vertical Tendons

Ÿ   Pier Head Concrete

 

Double Blade Column

Ÿ   Lifting works

 

Deck Erection

Ÿ   Setting up of equipment

Ÿ   Segment erection

 

Precast Segment

Ÿ   Segment casting

 

Land Viaduct (P81 to Abutment at SHT)

Ÿ   Removal of filled platform

Ÿ   Reinstatement works

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.