9.1
Major site activities for the coming reporting month will include:
WA4
Cross Beam Precast Shell construction
WA7
Storage area
Marine
Viaduct (P0 to P80)
Pile
Cap Construction:
Concreting works
Steel re-bar fixing for pile cap
Enhancement works
Column
Construction:
Lift concrete pouring
Pier head works
Pier head concreting
Precast
Column Erection
Installation of base units and precast units
Stressing of vertical nailing tendons
Vertical Tendons Stressed
Grouting Vertical Tendons
Pier Head Concrete
Double
Blade Column
Lifting works
Deck
Erection
Setting up of equipment
Segment erection
Precast
Segment
Segment casting
Land
Viaduct (P81 to Abutment at SHT)
Removal of filled platform
Reinstatement works
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.