1.
This is the 38th monthly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project
¡§Contract No. HY/2011/09 ¡V Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR Boundary
and Scenic Hill¡¨ (hereinafter called the ¡§Contract¡¨). This report documents the findings of EM&A Works conducted in March
2016.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting month is listed
in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr
TSP Monitoring |
2nd, 8th,
14th, 18th, 24th and 30th March
2016 |
24-hr
TSP Monitoring |
2nd, 8th,
14th, 18th, 24th and 30th March
2016 |
Noise
Monitoring |
3rd, 9th,
15th, 21st and 31st March 2016 |
Water
Quality Monitoring |
2nd, 5th,
7th, 9th, 11th, 14th, 16th,
19th, 21st, 23rd, 25th, 29th
and 31st March 2016 |
4th and 14th
March 2016 |
|
Additional
Land-based Dolphin Behaviour and Movement
Monitoring |
2nd and 16th March 2016 |
Environmental
Site Inspection |
1st, 8th,
15th, 22nd and 29th March 2016 |
Archaeological
Site Inspection |
29th March 2016 |
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of the reporting month is
tabulated in Table II.
Table II Summary
Table for Events Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Exceedance |
Total
No. of Exceedance |
No. of Exceedance related to the Construction Activities of this Contract |
Total No. of Exceedance related to the Construction Activities of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
0 |
0 |
0 |
0 |
0 |
0 |
1-hour
TSP Monitoring
4.
All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
24-hour
TSP Monitoring
5.
All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
Construction
Noise
6.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was recorded.
Water Quality
7.
All water quality monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level exceedance was recorded.
Complaint Log
8.
No environmental complaint was received in the reporting month.
Notification of
Summons and Successful Prosecutions
9.
No notification of summons and successful prosecution was received in
the reporting month.
10.
This report has been developed in compliance with the reporting
requirements for the subsequent monthly EM&A Report as required by the
EM&A Manual for Hong Kong Link Road (EM&A Manual).
11.
Major site activities for
the coming reporting month will include:
WA4
Cross Beam Precast Shell construction
Viaduct
Facilities
Precast gullies installation
Marine
Viaduct (P0 to P80)
Pile
Cap Construction:
Concreting works
Steel re-bar fixing for pile cap
Trimming of pile head concrete
Column
Construction:
in-situ standard column construction
Precast
Column Erection
Installation of precast units and pier head
unit
Stressing of vertical nailing tendons
Vertical Tendons Stressed
Grouting Vertical Tendons
Pier Head Concrete
Double
Blade Column
Pier head construction
Deck
Erection
Segment erection
Precast
Segment
Segment casting
Land
Viaduct (P81 to Abutment at SHT)
Removal of filled platform
Reinstatement of vertical seawall
Removal of falsework concrete footings