9.1
Major site activities for the coming reporting month will include:
WA4
Cross Beam Precast Shell construction
Viaduct
Facilities
Precast gullies installation
Marine
Viaduct (P0 to P80)
Pile
Cap Construction:
Concreting works
Steel re-bar fixing for pile cap
Trimming of pile head concrete
Column
Construction:
in-situ standard column construction
Precast
Column Erection
Installation of precast units and pier head
unit
Stressing of vertical nailing tendons
Vertical Tendons Stressed
Grouting Vertical Tendons
Pier Head Concrete
Double
Blade Column
Pier head construction
Deck
Erection
Segment erection
Precast
Segment
Segment casting
Land
Viaduct (P81 to Abutment at SHT)
Removal of filled platform
Reinstatement of vertical seawall
Removal of falsework concrete footings
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.