9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Cross Beam Precast Shell construction

 

Ancillary and Associated Facilities

Ÿ   Precast gullies installation

Ÿ   E&M installation

Ÿ   Deck void lighting installation

Ÿ   Precast parapets installation

Ÿ   Construction of side barriers

 

Marine Viaduct (P0 to P80)

Pile Cap Construction:

Ÿ   Concreting works

Ÿ   Re-bar fixing for pile cap

Precast Column Erection

Ÿ   Installation of pier head unit

Ÿ   Vertical Tendons Stressed

Ÿ   Grouting Vertical Tendons

Ÿ   Pier Head Concrete

 

Double Blade Column

Ÿ   Pier head construction

 

Deck Erection

Ÿ   Segment erection

 

Precast Segment

Ÿ   Segment casting

 

Land Viaduct (P81 to Abutment at SHT)

Ÿ   Removal of filled platform

Ÿ   Reinstatement of vertical seawall

Ÿ   Removal of falsework and reinstatement of slope area at P115

Ÿ   Construction of longitudinal stitching

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.