1.
This is the 40th
monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project ¡§Contract No. HY/2011/09 ¡V
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR
Boundary and Scenic Hill¡¨ (hereinafter called
the ¡§Contract¡¨). This report documents the findings of EM&A Works conducted in May
2016.
Environmental
Monitoring and Audit Progress
2.
A summary of the monitoring
activities in this reporting month is listed in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
3rd,
9th, 13th, 19th, 25th and 31st
May 2016 |
24-hr TSP Monitoring |
3rd,
9th, 13th, 19th, 25th and 31st
May 2016 |
Noise Monitoring |
4th,
10th, 20th and 26th May 2016 |
Water Quality Monitoring |
3rd,
5th, 7th, 9th, 11th, 13th,
16th, 18th, 20th, 23rd, 25th,
28th and 30th May 2016 |
13th
and 25th May 2016 |
|
Additional Land-based Dolphin Behaviour and Movement Monitoring |
9th
and 16th May 2016 |
Environmental Site Inspection |
3rd,
10th, 17th , 24th and 31st May 2016 |
Archaeological Site Inspection |
(1) N/A |
Remark:
(1) No archaeological site
inspection was conducted in the reporting month.
Breaches of Action and
Limit Levels
3.
Summary of the
environmental exceedances of the reporting month is tabulated in Table II.
Table II Summary
Table for Events Recorded in the Reporting Month
Environmental
Monitoring |
Parameter |
No. of Exceedance |
Total No. of Exceedance |
No. of Exceedance
related to the Construction
Activities of this
Contract |
Total No. of
Exceedance related to the Construction
Activities of this
Contract |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO) (Surface & Middle) |
0 |
0 |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO) (Bottom) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
6 |
3 |
9 |
0 |
0 |
0 |
1-hour TSP Monitoring
4.
All 1-hour TSP monitoring
was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
24-hour TSP Monitoring
5.
All 24-hour TSP monitoring
was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
Construction Noise
6.
All construction noise monitoring
was conducted as scheduled in the reporting month. No Action/Limit Level
exceedance was recorded.
Water
Quality
7.
All water quality
monitoring was conducted as scheduled in the reporting month. There are six Action
Level and three Limit Level exceedances for suspended solids were recorded. No
Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.
8.
According to the investigation,
the exceedances are considered not due to the Contract due to the following
reasons:
1) No
pollution discharge was observed from the site;
2) Adverse water quality outside the site boundary and
dispersion of sediment plume
to the monitoring stations from the area outside the site boundary (i.e. works
area not under and related to HY/2011/09) were observed;
3) Sediment
plume due to natural fluctuation of shallow water was observed; and
4) Localized
sediment plume due to the rough water condition was observed.
Complaint Log
9.
No environmental complaint
was received in the reporting month.
Notification of Summons and Successful Prosecutions
10.
No notification of summons
and successful prosecution was received in the reporting month.
11.
This report has been
developed in compliance with the reporting requirements for the subsequent
monthly EM&A Report as required by the EM&A Manual for Hong Kong Link
Road (EM&A Manual).
12.
Major site activities for the coming reporting month will include:
WA4
Cross Beam
Precast Shell construction
Ancillary and Associated Facilities
E&M
installation
Preparation
works for installation of precast precast parapets
Construction
of side barriers
Marine Viaduct (P0 to P80)
Precast Column Erection
Vertical
Tendons Stressed
Grouting
Vertical Tendons
Pier Head
Concrete
Double Blade Column
Pier head
construction
Deck Erection
Segment
erection
Erection of canilever
Erection of
SOP segments, movement joint, in-situ RC works
Cross Beam
Precast Shell construction
Land Viaduct (P81 to Abutment at SHT)
Removal of
filled platform
Reinstatement
of slope area at P115
Construction
of longitudinal stitching