EXECUTIVE SUMMARY

Introduction

1.              This is the 40th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project ¡§Contract No. HY/2011/09 ¡V Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR Boundary and Scenic Hill¡¨ (hereinafter called the ¡§Contract¡¨). This report documents the findings of EM&A Works conducted in May 2016.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

3rd, 9th, 13th, 19th, 25th and 31st May 2016

24-hr TSP Monitoring

3rd, 9th, 13th, 19th, 25th and 31st May 2016

Noise Monitoring

4th, 10th, 20th and 26th May 2016

Water Quality Monitoring

3rd, 5th, 7th, 9th, 11th, 13th, 16th, 18th, 20th, 23rd, 25th, 28th and 30th May 2016

Dolphin Monitoring (Line-transect Vessel Surveys)

13th and 25th May 2016

Additional Land-based Dolphin Behaviour and Movement Monitoring

9th  and 16th May 2016

Environmental Site Inspection

3rd, 10th, 17th , 24th and 31st May 2016

Archaeological Site Inspection

(1)  N/A

             Remark:       (1)   No archaeological site inspection was conducted in the reporting month.

 

 

 


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

Total No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Total No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

0

0

24-hr TSP

0

0

0

0

0

0

Noise

Leq(30min)

0

0

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids (SS)

6

3

9

0

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 


Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are six Action Level and three Limit Level exceedances for suspended solids were recorded. No Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.

8.              According to the investigation, the exceedances are considered not due to the Contract due to the following reasons:

1)      No pollution discharge was observed from the site;

2)      Adverse water quality outside the site boundary and dispersion of sediment plume to the monitoring stations from the area outside the site boundary (i.e. works area not under and related to HY/2011/09) were observed;

3)      Sediment plume due to natural fluctuation of shallow water was observed; and 

4)      Localized sediment plume due to the rough water condition was observed.

Complaint Log

 

9.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

 

WA4

Ÿ   Cross Beam Precast Shell construction

 

Ancillary and Associated Facilities

Ÿ   E&M installation

Ÿ   Preparation works for installation of precast precast parapets

Ÿ   Construction of side barriers

 


Marine Viaduct (P0 to P80)

Precast Column Erection

Ÿ   Vertical Tendons Stressed

Ÿ   Grouting Vertical Tendons

Ÿ   Pier Head Concrete

Double Blade Column

Ÿ   Pier head construction

 

Deck Erection

Ÿ   Segment erection

Ÿ   Erection of canilever

Ÿ   Erection of SOP segments, movement joint, in-situ RC works

Ÿ   Cross Beam Precast Shell construction

 

Land Viaduct (P81 to Abutment at SHT)

Ÿ   Removal of filled platform

Ÿ   Reinstatement of slope area at P115

Ÿ   Construction of longitudinal stitching