Table 7.1 Observations
and Recommendations of Site Audit
|
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
|
Water Quality |
03/05/2016 |
Clear the rubbish in
the sedimentation tank at near P110. |
Rectification/improvement was observed during
the follow-up audit session on 10 May 2016. |
|
10/05/2016 |
Provide
mitigation measures to avoid to leakage of wastewater at ro-ro barge to the
sea (Kam Shun 338) |
Rectification/improvement was observed during
the follow-up audit session on 17 May 2016. |
|
|
10/05/2016 |
Properly
deploy the silt curtain at P68. |
Rectification/improvement was observed during
the follow-up audit session on 17 May 2016. |
|
|
17/05/2016 |
Muddy
water should be cleared near P37 (deck-surface) to prevent discharging into
the sea. |
Rectification/improvement was observed during
the follow-up audit session on 24 May 2016. |
|
|
17/05/2016 |
Wastewater
should be treated properly before discharging into the designated discharging
point at P94. |
Rectification/improvement was observed during
the follow-up audit session on 24 May 2016. |
|
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
|
Air Quality |
03/05/2016 |
Properly cover the stockpile of dusty material at P86. |
Rectification/improvement was observed during
the follow-up audit session on 10 May 2016. |
|
24/05/2016 |
Clear the oil leakage and dusty materials
around the segment carrier at P41 (deck-surface). |
Rectification/improvement was observed during
the follow-up audit session on 31 May 2016. |
|
|
Noise |
N/A(1) |
N/A(1) |
N/A(1) |
|
Waste / Chemical Management |
03/05/2016 |
Clear the accumulated rubbish at between
P82 and P83. |
Rectification/improvement was observed during
the follow-up audit session on 10 May 2016. |
|
03/05/2016 |
Proper container and drip tray should be
provided for storing chemical oil at P91, P93 and P108. |
Rectification/improvement was observed during
the follow-up audit session on 10 May 2016. |
|
|
03/05/2016 |
Clear the chemical oil container that
without cover at P112. (deck-surface) |
Rectification/improvement was observed during
the follow-up audit session on 10 May 2016. |
|
|
10/05/2016 |
Properly store the chemical containers at
near the site office containers at WA4. |
Rectification/improvement was observed during
the follow-up audit session on 17 May 2016. |
|
|
10/05/2016 |
Clear the oil spillage at the platform at
P69. |
Rectification/improvement was observed during
the follow-up audit session on 17 May 2016. |
|
|
10/05/2016 |
Clear the accumulated chemical containers
as chemical wastes at P62 (deck-surface). |
Rectification/improvement was observed during
the follow-up audit session on 17 May 2016. |
|
|
17/05/2016 |
To clear the oil stain properly as chemical
waste at the section between P39 and P40. (deck-suface) |
Rectification/improvement was observed during
the follow-up audit session on 24 May 2016. |
|
|
24/05/2016 |
Clear the oil leakage and provide drip tray
for the oil drum at between P47 & P46 (deck-surface). |
Rectification/improvement was observed during
the follow-up audit session on 31 May 2016. |
|
|
24/05/2016 |
Clear the oil leakage and dusty materials
around the segment carrier at P41 (deck-surface). |
Rectification/improvement was observed during
the follow-up audit session on 31 May 2016. |
|
|
24/05/2016 |
Clear the oil leakage around the steel
container at P30 (deck-surface). |
Rectification/improvement was observed during
the follow-up audit session on 31 May 2016. |
|
|
31/05/2016 |
Properly store the chemicals at P71
(deck-surface) to avoid falling at height. |
Rectification/improvement was observed during
the follow-up audit session on 7 June 2016. |
|
|
31/05/2016 |
Provide spill kit (i.e. oil absorbent) at
P17 (deck-surface). |
Rectification/improvement was observed during
the follow-up audit session on 7 June 2016. |
|
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
|
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
|
Other |
N/A(1) |
N/A(1) |
N/A(1) |
|
Cultural
Heritage (Sha Lo
Wan (West) Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.
N/A(2) No archaeological site inspection
was conducted in the reporting month.