Table
7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water
Quality |
N/A(1) |
N/A(1) |
N/A(1) |
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air
Quality |
07/06/2016 |
Properly
check and repair the generator at P47 (deck-surface) to avoid heavy smoke
emission. |
Rectification/improvement
was observed during the follow-up audit session on 14 June 2016. |
Noise |
N/A(1) |
N/A(1) |
N/A(1) |
Waste / Chemical Management |
07/06/2016 |
Clear
the accumulated rubbish at P48 (deck-surface). |
Rectification/improvement
was observed during the follow-up audit session on 14 June 2016. |
07/06/2016 |
Clear
the construction waste and rubbish at the gully near the grouting plant at
P49 (deck-surface). |
Rectification/improvement
was observed during the follow-up audit session on 14 June 2016. |
|
14/06/2016 |
To
provide proper label for chemical containers at Portion C and provide bund
for chemical waste storage area to prevent leakage. |
Rectification/improvement
was not observed during the follow-up audit session on 21 June 2016. Further follow-up on
this item is required. |
|
14/06/2016 |
To
provide a drip tray for oil drum near P109 and label it properly. |
Rectification/improvement
was observed during the follow-up audit session on 21 June 2016. |
|
14/06/2016 |
Accumulated
general refuse should be disposed of properly near P83. |
Rectification/improvement
was observed during the follow-up audit session on 21 June 2016. |
|
21/06/2016 |
Clear
the accumulated wastes at P79. |
Rectification/improvement
was observed during the follow-up audit session on 28 June 2016. |
|
21/06/2016 |
Clear
the stagnant water at drip tray to maintain its capacity at P16. |
Rectification/improvement
was observed during the follow-up audit session on 28 June 2016. |
|
28/06/2016 |
Clear
the rubbish in front of the mobile crane at P68. |
Rectification/improvement
was observed during the follow-up audit session on 5 July 2016. |
|
28/06/2016 |
Clear
the oil spillage properly at P68. |
Rectification/improvement
was observed during the follow-up audit session on 5 July 2016. |
|
28/06/2016 |
Provide
proper container and drip tray for temporary storage of chemicals. |
Rectification/improvement
was observed during the follow-up audit session on 5 July 2016. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological
Site) |
28/06/2016 |
N/A(1) |
N/A(1) |
Remark: N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.