9              FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Cross Beam Precast Shell construction

 

Ancillary and Associated Facilities

Ÿ   E&M installation

Ÿ   E&M ducting installation

Ÿ   Installation of precast parapets

Ÿ   Construction of median and side barriers

Ÿ   Construction of sign gantry footing

 

Marine Viaduct (P0 to P80)

Precast Column Erection

Ÿ   Vertical Tendons Stressed

Ÿ   Grouting Vertical Tendons

Ÿ   Pier Head Concrete

Double Blade Column

Ÿ   Pier head construction

 

Deck Erection

Ÿ   Segment erection

Ÿ   Erection of SOP segments, movement joint, in-situ RC works

Radar platform erection

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81-P84)

Ÿ   Removal of filled platform

Ÿ   Reinstatement of slope area and drainage

Ÿ   Construction of longitudinal stitching

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.