7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 5th, 12th, 19th and 26th July 2016 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 26th July 2016. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 14th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 28th June and next inspection will be conducted in September 2016.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

12/07/2016

Clear the mud trails and provide wheel-wash to vehicles using site exit (S8).

Rectification/improvement was observed during the follow-up audit session on 19 July 2016.

19/07/2016

Clear the handrail within the silt curtain at P89.

Rectification/improvement was observed during the follow-up audit session on 26 July 2016.

19/07/2016

Clear the floating rubbish which enter to the site through the gap of silt curtain at between P83 and P84. The silt curtain should also be repaired to avoid the gap accordingly.

Rectification/improvement was observed during the follow-up audit session on 26 July 2016.

26/07/2016

Properly collect the concrete wash water for further treatment at P79 to avoid leaking to the sea.

Rectification/improvement was observed during the follow-up audit session on 3 August 2016.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

05/07/2016

To properly provide wheel washing facility at exit S8.

Rectification/improvement was observed during the follow-up audit session on 19 July 2016.

12/07/2016

Clear the mud trails and provide wheel-wash to vehicles using site exit (S8).

Rectification/improvement was observed during the follow-up audit session on 19 July 2016.

26/07/2016

Properly display the proper label of NRMM for the forklift at P72.

Rectification/improvement was observed during the follow-up audit session on 3 August 2016.

Noise

N/A(1)

N/A(1)

N/A(1)

Waste / Chemical Management

05/07/2016

To clear the accumulated waste material at P57.

Rectification/improvement was observed during the follow-up audit session on 12 July 2016.

05/07/2016

To properly repair the waste skip at entrance of Portion C.

Rectification/improvement was observed during the follow-up audit session on 12 July 2016.

05/07/2016

To improve the bunding at the chemical storage area of Portion C.

Rectification/improvement was observed during the follow-up audit session on 12 July 2016.

12/07/2016

Clear the rubbish at the planter area at P107 (Portion A).

Rectification/improvement was observed during the follow-up audit session on 19 July 2016.

19/07/2016

Clear the accumulated rubbish at near P108 (Portion C).

Rectification/improvement was observed during the follow-up audit session on 26 July 2016.

26/07/2016

To seal the hole / close the valve of the drip tray at P72.

Rectification/improvement was observed during the follow-up audit session on 3 August 2016.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 431m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.