9.1
Major site activities for the coming reporting month will include:
WA4
Cross Beam Precast Shell construction
Ancillary
and Associated Facilities
E&M installation
E&M ducting installation
Installation of precast parapets skins
Erection of Radar Platform
Construction of median and side barriers
Construction of sign gantry footing
Marine
Viaduct (P0 to P80)
Precast
Column Erection
Pier Head Concrete
Double
Blade Column
Pier head cast
Deck
Erection
Segment erection
Erection of SOP segments,
Construction of cross beam recast shell
In-situ RC works
External
Prestressing Tendon Installation
Internal
Trestressing Grouting
Land
Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81-P84)
Removal of filled platform
Reinstatement of slope area and drainage
Construction of longitudinal stitching
Road barrier construction
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.