9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Cross Beam Precast Shell construction

 

Ancillary and Associated Facilities

Ÿ   E&M installation

Ÿ   E&M ducting installation

Ÿ   Installation of precast parapets skins

Ÿ   Erection of Radar Platform

Ÿ   Construction of median and side barriers

Ÿ   Construction of sign gantry footing

 

Marine Viaduct (P0 to P80)

Precast Column Erection

Ÿ   Pier Head Concrete

Double Blade Column

Ÿ   Pier head cast

 

Deck Erection

Ÿ   Segment erection

Ÿ   Erection of SOP segments,

Ÿ   Construction of cross beam recast shell

Ÿ   In-situ RC works

 

External Prestressing Tendon Installation

Internal Trestressing Grouting

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81-P84)

Ÿ   Removal of filled platform

Ÿ   Reinstatement of slope area and  drainage

Ÿ   Construction of longitudinal stitching

Ÿ   Road barrier construction

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.