Table 7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
18/10/2016 |
Muddy
water was discharging to the sea at WA4 during the heavy rainstorm. The
contractor was reminded to enhance the sand bag bund and divert the muddy
water for treatment before discharging out. |
Rectification/improvement
was observed during the follow-up audit session on 25 October 2016. |
18/10/2016 |
Provide
designated concrete washout area to avoid the concrete wash water discharging
to the nearby marine water at between P82 and P83. |
Rectification/improvement
was observed during the follow-up audit session on 25 October 2016. |
|
25/10/2016 |
Silt
curtain should be properly maintained (P109). |
Rectification/improvement
was observed during the follow-up audit session on 1 November 2016. |
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air Quality |
04/10/2016 |
NRMM labels should be
provided for equipment at Portion C (P112). |
Rectification/improvement
was observed during the follow-up audit session on 11 October 2016. |
25/10/2016 |
Dusty
material on the deck should be cleared (P83). |
Rectification/improvement
was observed during the follow-up audit session on 1 November 2016. |
|
Noise |
N/A(1) |
N/A(1) |
N/A(1) |
Waste / Chemical Management |
25/10/2016 |
Oily water in the drip
tray should be removed (P83, P109). |
Rectification/improvement
was observed during the follow-up audit session on 1 November 2016. |
04/10/2016 |
Accumulated
waste at P83 should be cleared properly. |
Rectification/improvement
was observed during the follow-up audit session on 11 October 2016. |
|
11/10/2016 |
Drip tray for the
chemical containers at P72 (deck-surface) should be plugged properly. |
Rectification/improvement
was observed during the follow-up audit session on 18 October 2016. |
|
11/10/2016 |
Provide drip tray for the
chemical containers at near the power pack at P72 (deck-surface). |
Rectification/improvement
was observed during the follow-up audit session on 18 October 2016. |
|
18/10/2016 |
To remove the oil drum at
near the sedimentation tank at WA4. |
Rectification/improvement
was observed during the follow-up audit session on 25 October 2016. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological Site) |
N/A |
N/A(1) |
N/A(1) |
Remark: N/A(1)
- No major environmental deficiency was identified during the site
inspection in the reporting month.