7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 4th, 11th, 18th and 25th October 2016 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 25th October 2016. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 15th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 20th September 2016 and next inspection will be conducted in December 2016.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

18/10/2016

Muddy water was discharging to the sea at WA4 during the heavy rainstorm. The contractor was reminded to enhance the sand bag bund and divert the muddy water for treatment before discharging out.

Rectification/improvement was observed during the follow-up audit session on 25 October 2016.

18/10/2016

Provide designated concrete washout area to avoid the concrete wash water discharging to the nearby marine water at between P82 and P83.

Rectification/improvement was observed during the follow-up audit session on 25 October 2016.

25/10/2016

Silt curtain should be properly maintained (P109).

Rectification/improvement was observed during the follow-up audit session on 1 November 2016.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

04/10/2016

NRMM labels should be provided for equipment at Portion C (P112).

Rectification/improvement was observed during the follow-up audit session on 11 October 2016.

25/10/2016

Dusty material on the deck should be cleared (P83).

Rectification/improvement was observed during the follow-up audit session on 1 November 2016.

Noise

N/A(1)

N/A(1)

N/A(1)

Waste / Chemical Management

25/10/2016

Oily water in the drip tray should be removed (P83, P109).

Rectification/improvement was observed during the follow-up audit session on 1 November 2016.

04/10/2016

Accumulated waste at P83 should be cleared properly.

Rectification/improvement was observed during the follow-up audit session on 11 October 2016.

11/10/2016

Drip tray for the chemical containers at P72 (deck-surface) should be plugged properly.

Rectification/improvement was observed during the follow-up audit session on 18 October 2016.

11/10/2016

Provide drip tray for the chemical containers at near the power pack at P72 (deck-surface).

Rectification/improvement was observed during the follow-up audit session on 18 October 2016.

18/10/2016

To remove the oil drum at near the sedimentation tank at WA4.

Rectification/improvement was observed during the follow-up audit session on 25 October 2016.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A

N/A(1)

N/A(1)

Remark:     N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 1916m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.