7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 1st, 8th, 15th, 22nd and 29th November 2016 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 22nd November 2016. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 15th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 20th September 2016 and next inspection will be conducted in December 2016.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

1/11/2016

No wastewater should be discharged to sea at P82.

Rectification/improvement was observed during the follow-up audit session on 15 November 2016.

29/11/2016

Silt curtain should be maintained at Portion a (P101).

Rectification/improvement was observed during the follow-up audit session on 6 December 2016.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

15/11/2016

Cement bags should be covered with impervious sheet. (Portion C)

Rectification/improvement was observed during the follow-up audit session on 22 November 2016.

Noise

N/A(1)

N/A(1)

N/A(1)

Waste / Chemical Management

1/11/2016

Oil stain at P47 should be cleared.

Rectification/improvement was observed during the follow-up audit session on 8 November 2016.

1/11/2016

Accumulated waste at P52 should be cleared.

Rectification/improvement was observed during the follow-up audit session on 8 November 2016.

1/11/2016

Chemical containers should be provided with drip tray or removed at P52, P106 Portion c and with proper chemical labels.

Rectification/improvement was observed during the follow-up audit session on 8 November 2016.

1/11/2016

General waste should be cleared in the drainage at Portion a.

Rectification/improvement was observed during the follow-up audit session on 8 November 2016.

8/11/2016

The oily water in the drip tray and oil stain should be cleared. (WA4)

Rectification/improvement was observed during the follow-up audit session on 15 November 2016.

8/11/2016

The chemical containers should be properly stored or removed. (WA4, P47)

Rectification/improvement was observed during the follow-up audit session on 15 November 2016.

8/11/2016

The chemical container should be properly labelled. (P47)

Rectification/improvement was observed during the follow-up audit session on 15 November 2016.

15/11/2016

Chemical containers should be provided with drip trays and with proper chemical labels. (Portion C P106)

Rectification/improvement was observed during the follow-up audit session on 22 November 2016.

22/11/2016

Chemical containers should be stored properly with drip tray and away from the deck edge to prevent discharge to sea. (P60, P79)

Rectification/improvement was observed during the follow-up audit session on 29 November 2016.

22/11/2016

Chemical labels should be provided for all chemical containers. (P79)

Rectification/improvement was observed during the follow-up audit session on 29 November 2016.

29/11/2016

Drip tray should be provided for the chemical containers at P80.

Rectification/improvement was observed during the follow-up audit session on 6 December 2016.

29/11/2016

Accumulated waste should be cleared regularly at Portion a (P82).

Rectification/improvement was observed during the follow-up audit session on 6 December 2016.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A

N/A(1)

N/A(1)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 8704m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.