9.1
Major site activities for the coming reporting month will include:
l
Cross Beam Precast Shell construction
Ancillary and Associated Facilities
l
E&M installation
l
E&M ducting installation
l
Construction of Load Centre (CL1)
l
Installation of carrier drains
l
Installation of precast parapet skins
l
Erection of Radar Platform
l
Construction of median and side barriers
l
Construction of longitudinal stitching
l
Erection of gantry posts for Sign gantry
l
Reinstatement of slope area and drainage works
l
Reinstatement of sloping seawall
Marine Viaduct (P0 to P80)
Deck Erection
l
Segment erection
l
Erection of SOP segments
l
Erection of cantilever
l
Construction of cross beam precase shell
l
In-situ RC works
l
Erection of precase SOP unit to Turnaround
l
Alignment and levels adjustment
l
Construction of temporary platform
External Prestressing Tendon
Installation
Internal Prestressing Grouting
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.