EXECUTIVE SUMMARY

Introduction

1.              This is the 47th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project ¡§Contract No. HY/2011/09 ¡V Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR Boundary and Scenic Hill¡¨ (hereinafter called the ¡§Contract¡¨). This report documents the findings of EM&A Works conducted in September 2016.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

1st, 7th, 13th, 19th, 23th and 29th December 2016

24-hr TSP Monitoring

1st, 7th, 13th, 19th, 23th and 29th December 2016

Noise Monitoring

2nd, 8th, 14th, 20th and 30th December 2016

Water Quality Monitoring

2nd, 5th, 7th, 9th, 12th, 14th, 16th, 19th, 21st, 23rd, 26th, 28th and 30th December 2016

Dolphin Monitoring (Line-transect Vessel Surveys)

2nd and 12th December 2016

Environmental Site Inspection

6th, 13th, 20th and 29th December 2016

Archaeological Site Inspection

13th December 2016

 

 

 


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

Total No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Total No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

0

0

24-hr TSP

0

0

0

0

0

0

Noise

Leq(30min)

0

0

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids (SS)

6

0

6

0

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 


Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are six Action Level were recorded for suspended solids. No Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.

8.              According to the investigation, the exceedances are considered not due to the Contract due to the following reasons:

1)      No pollution discharge from construction activity was observed;

2)      Control Station value already exceeded either the Baseline Action or Limit Levels;

3)      Monitoring station is situated at the upstream of the construction sites;

4)      Sediment plume due to natural fluctuation of shallow water was observed; and

5)      Adverse water quality outside the site boundary was observed. Dispersion of sediment plume to the monitoring stations from the area outside the site boundary (i.e. works area not under and related to HY/2011/09) was also observed.

Complaint Log

 

9.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

¡P             Cross Beam Precast Shell construction

Ancillary and Associated Facilities

¡P             E&M installation

¡P             E&M ducting installation

¡P             Construction of Load Centre (CL1)

¡P             Installation of carrier drains

¡P             Installation of precast parapet skins

¡P             Erection of Radar Platform

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Erection of gantry posts for Sign gantry

¡P             Reinstatement of slope area and drainage works

¡P             Reinstatement of sloping seawall

 

Marine Viaduct (P0 to P80)

Deck Erection

¡P             Segment erection

¡P             Erection of SOP segments

¡P             Erection of cantilever

¡P             Construction of cross beam precase shell

¡P             In-situ RC works

¡P             Erection of precase SOP unit to Turnaround

¡P             Alignment and levels adjustment

¡P             Construction of temporary platform

External Prestressing Tendon Installation

Internal Prestressing Grouting