7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 6th, 13th, 20th and 29th December 2016 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 20th December 2016. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 16th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 13th December 2016 and next inspection will be conducted in March 2017.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

N/A(1)

N/A(1)

N/A(1)

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

6/12/2016

NRMM label should be provided for equipment at P50.

Rectification/improvement was observed during the follow-up audit session on 13 December 2016.

6/12/2016

Haul roads at portion a (P89) and portion c should be sprayed with water regularly.

Rectification/improvement was observed during the follow-up audit session on 13 December 2016.

13/12/2016

Site vehicles should be wheel washed before leaving the site at P81.

Rectification/improvement was observed during the follow-up audit session on 20 December 2016.

20/12/2016

Dusty material should be cleared at P55.

Rectification/improvement was observed during the follow-up audit session on 29 December 2016.

20/12/2016

Smoke exhausted from the power generator at P56 should be avoided.

Rectification/improvement was observed during the follow-up audit session on 29 December 2016.

Noise

N/A(1)

N/A(1)

N/A(1)

Waste / Chemical Management

6/12/2016

Chemical containers should be with chemical labels and store in drip trays (P50, 53, 55)

Rectification/improvement was observed during the follow-up audit session on 13 December 2016.

6/12/2016

Oily water in drip tray at P56 should be cleared.

Rectification/improvement was observed during the follow-up audit session on 13 December 2016.

6/12/2016

Accumulated waste at P46 should be cleared.

Rectification/improvement was observed during the follow-up audit session on 13 December 2016.

13/12/2016

Chemical containers should be with chemical labels and store in drip trays at P68, P70 and P82.

Rectification/improvement was observed during the follow-up audit session on 20 December 2016.

13/12/2016

Drip tray should be plugged at P68.

Rectification/improvement was observed during the follow-up audit session on 20 December 2016.

20/12/2016

Oil stain at P55, 56, 67 should be cleared.

 

Rectification/improvement was observed during the follow-up audit session on 29 December 2016.

20/12/2016

Drip trays should be provided for chemical containers at P55.

Rectification/improvement was observed during the follow-up audit session on 29 December 2016.

20/12/2016

Drip tray at P54 should be plugged.

Rectification/improvement was observed during the follow-up audit session on 29 December 2016.

29/12/2016

Chemical containers at P53 and Portion a (P82) should be provided with drip trays.

Rectification/improvement was observed during the follow-up audit session on 3 January 2017.

29/12/2016

Oily water in the drip tray at P47 should be removed and oil stain should be cleared.

Rectification/improvement was observed during the follow-up audit session on 3 January 2017.

29/12/2016

Accumulated waste should be cleared regularly at Portion a (P82).

Rectification/improvement was observed during the follow-up audit session on 3 January 2017.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

13/12/2016

N/A(1)

N/A(1)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 2758m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O