9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

¡P             Cross Beam Precast Shell construction

Ancillary and Associated Facilities

¡P             E&M installation

¡P             E&M ducting installation

¡P             Construction of Load Centre (CL1)

¡P             Installation of carrier drains

¡P             Installation of precast parapet skins

¡P             Erection of Radar Platform

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Erection of gantry posts for Sign gantry

¡P             Reinstatement of slope area and drainage works

¡P             Reinstatement of sloping seawall

 

Marine Viaduct (P0 to P80)

Deck Erection

¡P             Segment erection

¡P             Erection of SOP segments

¡P             Erection of cantilever

¡P             Construction of cross beam precase shell

¡P             In-situ RC works

¡P             Erection of precase SOP unit to Turnaround

¡P             Alignment and levels adjustment

¡P             Construction of temporary platform

External Prestressing Tendon Installation

Internal Prestressing Grouting

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.