2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
¡P
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan,
provisioning of a compensatory marine radar, and provisioning of security
systems; and
¡P
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) ¡V Cinotech
Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Ancillary and Associated Facilities
(a) P115 & P114 interface
area - Reinstatement of slope area temporarily on-hold pending for drainage and
reinstatement detailing coupling with the additional maintenance path;
(b) Reinstatement of sloping
seawall at P103, P104 and P101, P102 are in progress;
(c) The precast parapet progress
is summarized as follows:
Item |
Number in this month |
Cumulative No. of Precast Parapet
Completed (up to end of month) |
Parapet Casting |
623 |
4151 |
Parapet Installation |
583 |
2632 |
In-situ concreting works |
1393 |
629 |
(d) The central barrier progress
is summarized as follows:
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to end of month) |
Central barrier (precast
method) |
Precast |
757 |
3623 |
Installation |
230 |
926 |
|
Central barrier (precast
+ in-situ method) |
In-fill concreting # |
458 |
1275 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
central barrier shall be regarded as completed.
(e) The side barrier progress is
summarized as follows:
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of month) |
Side barrier (precast
method) |
Precast |
870 |
3961 |
Installation |
394 |
1634 |
|
Side barrier (precast +
in-situ method) |
In-fill concreting # |
177 |
2546 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
side barrier shall be regarded as completed.
(f) Construction of the
longitudinal stitching from P92 to P87 & P40 to P33 is in progress;
(g) Installation of carrier
drains at P89L is in progress;
(h) Sealing of deck openings and
preparation deck surface for waterproofing is in progress;
(i) Waterproofing and asphalt
laying at ML16 to ML19 is in progress;
(j) Watermain installation from P99 to P97 and P44 to P42 is in progress;Watermain
installation from P98 to P115 was completed;
(k) Sign gantry GW13, GE15 and
GE13, GE14 were erected, posts for sign gantry GE12 and GW12 were erected.
E&M Works
(a) E&M works from ML3 to ML1
is in progress, E&M ducting installation at ML3 commenced;
(b) E&M ducting installation
from ML5 to ML4 is in progress;
(c) E&M works inside SHT
building is in progress;
(d) Street light cables and poles
installation in ML19 & ML18 is in progress;
(e) Cable hanger installation
from ML19 to ML15 is in progress;
(f) E&M ducting installation
inside deck void from ML19 to ML15 was completed;
(g) E&M ducting installation
at ML6 was completed;
(h) Cable hanger installation
from ML6 to ML4 commenced;
(i) E&M ducting installation
at radar platform commenced;
(j) Construction of Load Centre 7
commenced.
Deck Erection
(a)
Segment erection in February 2017:
Type |
Location of Segments erected in this reporting period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
Launching Gantry 1 (LG1) |
All completed |
0 |
1020 |
Launching Gantry 2 (LG2) |
P0 |
0 |
1776 |
Lifting Frames 1 (LF1), Hanger Beam (HB)
and Crane Barge |
P67, P75, P78, P82 and P83 |
109 |
1141 |
Lifting Frames 1 (LF1), Hanger Beam (HB)
and Crane Barge |
P80 |
24 |
842 |
Typical Span SOP |
P0 |
0 |
242 |
Long Span SOP |
All completed |
0 |
96 |
Movement Joint (MJ) SOP
Airport Channel |
All completed |
0 |
20 |
Short Span (SS) and Movement
Joint (MJ) SOP type B |
All completed |
0 |
16 |
Typical Span Segment type B |
P55R, P56R&L, P57R&L
& P58L |
78 |
210 |
Segment Lifter / Crane
Barge |
P68 and P69 |
68 |
118 |
External Prestressing Tendon Installation
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
100% 100% 100% |
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
100% 100% 100% |
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
100% 100% 100% |
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
100% 100% 100% |
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
100% 100% 100% |
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
100% 100% 100% |
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
100% 100% 100% |
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
100% 100% 100% |
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
100% 100% 100% |
ML15R |
Threading Stressing Grouting |
108.74 18 21.15 |
T U M3 |
87% 66% 72% |
ML15L |
Threading Stressing Grouting |
106.26 18 21.45 |
T U M3 |
87% 66% 72% |
ML11R |
Threading Stressing Grouting |
164.83 24 32.72 |
T U M3 |
50% 0% 0% |
ML11L |
Threading Stressing Grouting |
166.74 24 33.10 |
T U M3 |
50% 0% 0% |
ML10R |
Threading Stressing Grouting |
121.69 16 24.17 |
T U M3 |
0% 0% 0% |
ML10L |
Threading Stressing Grouting |
122.16 16 24.26 |
T U M3 |
0% 0% 0% |
ML09R |
Threading Stressing Grouting |
140.32 32 27.73 |
T U M3 |
0% 0% 0% |
ML09L |
Threading Stressing Grouting |
129.46 32 25.56 |
T U M3 |
0% 0% 0% |
ML08R |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
100% 16% 0% |
ML08L |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
100% 16% 0% |
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
93% 17% 0% |
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
44% 16% 0% |
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
100% 100% 100% |
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
100% 100% 100% |
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
100% 100% 100% |
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
100% 100% 100% |
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
100% 100% 95% |
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
100% 100% 100% |
ML1R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
70% 66% 30% |
ML1L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
70% 66% 30% |
Internal Prestressing Grouting Progress
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Air test & Grouting |
14.09 |
M3 |
100% |
ML19R |
Air test & Grouting |
14.90 |
M3 |
100% |
ML19L |
Air test & Grouting |
13.90 |
M3 |
100% |
ML18R |
Air test & Grouting |
25.24 |
M3 |
100% |
ML18L |
Air test & Grouting |
24.76 |
M3 |
96% |
ML17R |
Air test & Grouting |
23.47 |
M3 |
100% |
ML17L |
Air test & Grouting |
23.46 |
M3 |
100% |
ML16R |
Air test & Grouting |
36.54 |
M3 |
99% |
ML16L |
Air test & Grouting |
35.46 |
M3 |
99% |
ML15R |
Air test & Grouting |
39.34 |
M3 |
100% |
ML15L |
Air test & Grouting |
39.69 |
M3 |
100% |
ML09R |
Air test & Grouting |
63.27 |
M3 |
24% |
ML09L |
Air test & Grouting |
57.86 |
M3 |
32% |
ML08R |
Air test & Grouting |
36.58 |
M3 |
31% |
ML08L |
Air test & Grouting |
36.56 |
M3 |
31% |
ML07R |
Air test & Grouting |
59.61 |
M3 |
46% |
ML07L |
Air test & Grouting |
60.05 |
M3 |
55% |
ML06R |
Air test & Grouting |
58.31 |
M3 |
100% |
ML06L |
Air test & Grouting |
58.31 |
M3 |
100% |
ML05R |
Air test & Grouting |
58.62 |
M3 |
100% |
ML05L |
Air test & Grouting |
58.01 |
M3 |
100% |
ML04R |
Air test & Grouting |
57.64 |
M3 |
100% |
ML04L |
Air test & Grouting |
57.69 |
M3 |
100% |
ML03R |
Air test & Grouting |
126.65 |
M3 |
31% |
ML03L |
Air test & Grouting |
127.63 |
M3 |
62% |
ML02R |
Air test & Grouting |
62.74 |
M3 |
32% |
ML02L |
Air test & Grouting |
62.74 |
M3 |
32% |
ML01R |
Air test & Grouting |
53.80 |
M3 |
0% |
ML01L |
Air test & Grouting |
53.80 |
M3 |
0% |
Turnaround Facilities
(a) Stitching works between 2 Box
Girders BG03, BG04 and SOPs is in progress with the soffit casted;
(b) BG02 was completed;
(c) Steel fixing for BG01 top
slab is in progress;
(d) Erection of formwork and
steel fixing for 1st I-beam is in progress;
(e) Erection of extended platform
at P56R is in progress.
Delivery for Precast
Concrete Elements (by barge)
(a)
Precast
Deck Segments:
- Number of barges engaged in this period: 18.
- Number of deck segment deliveries in this period: 61 trips.
- Cumulative number of deck segment deliveries: 1112 trips.
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to end of month) |
A |
2 |
2462 |
B |
78 |
248 |
C |
208 |
1602 |
D |
0 |
216 |
E |
0 |
1014 |
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
P84 ¡V P115: GW-RS1248-16 |
16/12/2016 (19:00) |
15/06/2017 (23:00) |
Valid |
P69, P79 ¡V P83: GW-RS1269-16 |
21/12/2016 (01:30) |
20/03/2017 (07:00) |
Valid |
P69-P83: GW-RS1040-16 |
06/10/2016 (19:00) |
05/04/2017 (24:00) |
Valid |
P0-P68: GW-RS1039-16 |
06/10/2016 (19:00) |
05/04/2017 (24:00) |
Valid |
PWA4: GW-RW0576-16 |
07/10/2016 (00:00) |
04/04/2017 (24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
04/06/2012 |
N/A |
Receipt acknowledged by EPD |
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A (DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00023624-2016 |
17/02/2016 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7:
WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Site was handed over on
30 Jun 2016 |
P0 ¡V P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
P81-P83: WT00023608-2016 |
01/04/2016 |
31/07/2020 |
Valid |