9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

¡P             Foundation works for Asphalt Plant

 

Ancillary and Associated Facilities

¡P             Sealing of deck openings and preparation deck surface for waterproofing

¡P             Waterproofing and asphalt laying

¡P             Watermain installation

¡P             Installation of carrier drains

¡P             Installation of precast parapet skins

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Erection of  sign gantry

¡P             Reinstatement of slope area and drainage works

¡P             Reinstatement of sloping seawall

¡P             Fill slope for CLK South Road realignment

¡P             Laying of asphalt pavement

¡P             Sealing of gantry crane loading opening

 

E&M Works

¡P             E&M installation

¡P             E&M ducting installation

¡P             Street light cables and poles installation

¡P             Cable hanger installation

¡P             Construction of Lad Centre

 

Marine Viaduct (P0 to P80)

 

Deck Erection

¡P             Segment erection

¡P             Temporary steel structure dismantling

¡P             Erection of cantilever

¡P             Span erection

 

External Prestressing Tendon Installation

Internal Prestressing Grouting

Turnaround Facilities

¡P             Stitching works

¡P             Steel fixing

¡P             Erection of formworks and steel fixing

¡P             Erection of extended platform

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.