8.1
Summary of exceedance is provided in Appendix L.
8.2
No Action/Limit Level exceedance was recorded for air quality and
construction noise.
8.3
There are four Action Level and one Limit Level exceedances were recorded
for suspended solids. No Action/Limit Level exceedance for dissolved oxygen and
turbidity were recorded.
8.4
According to the investigation, the exceedances are considered not due
to the Contract due to the following reasons:
1)
No pollution discharge from construction activity was observed;
2)
The exceeded results were similar or within the ranges baseline
monitoring results;
3)
Monitoring station is situated at the upstream of the construction
sites;
4)
Adverse water quality outside the site boundary was observed while no
construction vessel for this Contract was travelling nearby.
Summary of Environmental Complaint
8.5
No environmental related complaint was received in the reporting month. The
Complaint Log is attached in Appendix P.
8.6
There was one prosecution or notification of summons received since the Contract
commencement. Summary of successful prosecution as attached in Appendix Q.