9.1
Major site activities for the coming reporting month will include:
WA4
¡P
Establishment for Asphalt Plant
Ancillary
and Associated Facilities
¡P
Sealing of deck openings and preparation deck
surface for waterproofing
¡P
Waterproofing and asphalt laying
¡P
Watermain
installation
¡P
Installation of carrier drains
¡P
Installation of precast parapet skins
¡P
Construction of median and side barriers
¡P
Construction of longitudinal stitching
¡P
Erection of sign gantry
¡P
Reinstatement of slope area and drainage works
¡P
Reinstatement of sloping seawall
¡P
Fill slope for CLK South Road realignment
¡P
Laying of asphalt pavement
¡P
Sealing of gantry crane loading opening
E&M
Works
¡P
E&M installation
¡P
E&M ducting installation
¡P
E&M works inside SHT building
¡P
Street light cables and poles installation
¡P
Cable hanger installation
¡P
Construction of Lad Centre
Marine
Viaduct (P0 to P80)
Deck
Erection
¡P
Segment erection
External
Prestressing Tendon Installation
Internal
Prestressing Grouting
Turnaround
Facilities
¡P
Stitching works
¡P
Erection of I-beam supporting towers
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.