7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 6th, 15th, 22nd and 27th June 2017 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 22nd June 2017. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 16th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 15th June 2017 and next inspection will be conducted in September 2017.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

170606-R02

Silt curtain at P98 should be properly maintained.

Rectification/improvement was observed during the follow-up audit session on 15 June 2017.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

170627-R01

NRMM and NEL labels should be provided to the equipment at P60.

Rectification/improvement will be reported in next reporting month.

170627-R03

Dusty material should be covered by impervious sheet or removed at P68.

Rectification/improvement will be reported in next reporting month.

Noise

170627-R01

NRMM and NEL labels should be provided to the equipment at P60.

Rectification/improvement will be reported in next reporting month.

Waste / Chemical Management

170606-R01

Accumulated construction waste at P92 should be removed.

Rectification/improvement will be reported in next reporting month.

 

170615-R01

Housekeeping at P48, 55 should be enhanced.

Rectification/improvement was observed during the follow-up audit session on 27 June 2017.

 

170615-R02

Drip tray at P51 should be plugged and oil stain should be removed as chemical waste.

Rectification/improvement was observed during the follow-up audit session on 27 June 2017.

 

170615-R03

Chemical containers at P50 should be provided with proper chemical label and with drip tray.

Rectification/improvement was observed during the follow-up audit session on 27 June 2017.

170622-R01

Proper chemical label should be provided to the chemical containers at P57.

Rectification/improvement will be reported in next reporting month.

170622-R02

The chemical should be stored in proper container with chemical label and provided with drip tray at P57.

Rectification/improvement was observed during the follow-up audit session on 27 June 2017.

170622-R03

The drip trays along P58-60 should be plugged to avoid oily water leakage.

Rectification/improvement will be reported in next reporting month.

170622-R04

Housekeeping should be enhanced at P65.

Rectification/improvement will be reported in next reporting month.

170622-R05

The chemical waste store at P57 should be improved to fulfill COP requirement with proper chemical waste label and provide shelter to keep dry during the rainy day.

Rectification/improvement will be reported in next reporting month.

170627-R02

Housekeeping should be enhanced at P63.

Rectification/improvement will be reported in next reporting month.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

15/6/2017

N/A(1)

N/A(1)

Remark:       N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 561m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.