7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 1st, 8th, 15th, 22nd and 29th August 2017 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 22nd August 2017. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 16th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 15th June 2017 and next inspection will be conducted in September 2017.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

170815-R01

Silt curtain at P97 Portion A should be properly maintained.

Rectification/improvement was observed during the follow-up audit session on 22 August 2017.

170829-R02

Muddy material near the site boundary of WA4 should be cleared.

Rectification/improvement will be reported in next reporting month.

170829-R04

Silt curtain at P89 Portion A should be properly maintained.

Rectification/improvement will be reported in next reporting month.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

170801-R03

Dusty material at P91 should be removed or covered by impervious sheet.

Rectification/improvement will be reported in next reporting month.

170808-R01

Haul road at WA4 should be sprayed with water for dust suppression.

Rectification/improvement was observed during the follow-up audit session on 15 August 2017.

170808-R03

Stockpile of dusty material at P83 Portion A should be covered by impervious sheet or removed.

Rectification/improvement was observed during the follow-up audit session on 15 August 2017.

170808-R04

The water pipe should be repaired for water spraying during loading process and breaking work along P87-96 to suppress dust production.

Rectification/improvement was observed during the follow-up audit session on 15 August 2017.

170815-R02

Cement bags at P109 Portion C should be covered by impervious sheet.

Rectification/improvement was observed during the follow-up audit session on 22 August 2017.

170822-R01

Cement mixing works at P83 should be done in proper three-side enclosed area and with water spraying.

Rectification/improvement was observed during the follow-up audit session on 29 August 2017.

170822-R03

Dusty material at P72 should be covered with impervious sheet or removed.

Rectification/improvement was observed during the follow-up audit session on 29 August 2017.

170829-R06

Water spraying should be provided during the breaking works at Portion a P82 and Portion C for dust suppression.

Rectification/improvement will be reported in next reporting month.

Noise

N/A(1)

N/A(1)

N/A(1)

Waste / Chemical Management

170801-R01

Accumulated construction waste at P85-87 should be cleared.

Rectification/improvement will be reported in next reporting month.

170801-R02

Chemical containers at P97 should be removed as chemical waste.

Rectification/improvement was observed during the follow-up audit session on 8 August 2017.

170808-R02

Housekeeping at P82 should be enhanced at Portion A.

Rectification/improvement will be reported in next reporting month.

170815-R03

Chemical containers at Portion C gate should be with proper chemical labels.

Rectification/improvement was observed during the follow-up audit session on 22 August 2017.

170822-R02

Oil stain at P69 and P70 should be cleared and drip tray at P70 should be plugged to prevent oil leakage.

Rectification/improvement was observed during the follow-up audit session on 29 August 2017.

170822-R04

Chemical containers at P72 should be with proper chemical label and provided with drip tray.

Rectification/improvement was observed during the follow-up audit session on 29 August 2017.

170829-R01

Chemical waste in the chemical waste storage at WA4 should be provided with proper chemical label.

Rectification/improvement will be reported in next reporting month.

170829-R03

General waste and stand water in the container at WA4 should be removed.

Rectification/improvement will be reported in next reporting month.

170829-R05

Chemical container at P106 Portion C should be provided with drip tray.

Rectification/improvement will be reported in next reporting month.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

15/6/2017

N/A(1)

N/A(1)

Remark:     N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 1762m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.