Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

170926-R01

Accumulated construction waste at P56 should be cleared and grouting material should be cleared and well bunded to avoid runoff to sea.

Rectification/improvement will be reported in next reporting month.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

170905-R03

Water spraying should be provided to the breaking works at P70 and P73 for dust suppression.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170905-R04

Cement bags should be covered by impervious sheet at Portion C.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170912-R02

Water spraying should be provided to the scrabbling works and dumping of waste at P8 & P9, contractor was reminded to provide water container at every working point.

Rectification/improvement was observed during the follow-up audit session on 19 September 2017.

170919-R03

Water spraying should be provided during the breaking work at Portion C for dust suppression.

Rectification/improvement will be reported in next reporting month.

170926-R03

Grout mixing plant at P70 should be fully enclosed by three sides enclosure.

Rectification/improvement will be reported in next reporting month.

Noise

170912-R03

Handheld breaker and air compressor at P8 should be provided with NEL.

Rectification/improvement was observed during the follow-up audit session on 19 September 2017.

Waste / Chemical Management

170905-R01

Chemical labels should be provided to the chemical containers at P55 and P62 and oily water in the drip tray should be removed.

Rectification/improvement was observed during the follow-up audit session on 12 September 2017.

170905-R02

Housekeeping should be enhanced at P64.

Rectification/improvement was observed during the follow-up audit session on 12 September 2017.

170912-R01

Housekeeping should be enhanced at P21.

Rectification/improvement was observed during the follow-up audit session on 19 September 2017.

170919-R01

Dusty material and accumulated waste at P13 should be removed.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170919-R02

Oil stain at P6 and Portion C P112 should be cleared.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170926-R01

Accumulated construction waste at P56 should be cleared and grouting material should be cleared and well bunded to avoid runoff to sea.

Rectification/improvement will be reported in next reporting month.

170926-R02

The drip tray at P56 should be plugged and oily water and oil stain should be cleared as chemical waste.

Rectification/improvement will be reported in next reporting month.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

12/9/2017

N/A(1)

N/A(1)

Remark:     N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.