7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 5th, 12th, 19th and 26th September 2017 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 26th September 2017. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 17th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 12th September 2017 and next inspection will be conducted in December 2017.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

170926-R01

Accumulated construction waste at P56 should be cleared and grouting material should be cleared and well bunded to avoid runoff to sea.

Rectification/improvement will be reported in next reporting month.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

170905-R03

Water spraying should be provided to the breaking works at P70 and P73 for dust suppression.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170905-R04

Cement bags should be covered by impervious sheet at Portion C.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170912-R02

Water spraying should be provided to the scrabbling works and dumping of waste at P8 & P9, contractor was reminded to provide water container at every working point.

Rectification/improvement was observed during the follow-up audit session on 19 September 2017.

170919-R03

Water spraying should be provided during the breaking work at Portion C for dust suppression.

Rectification/improvement will be reported in next reporting month.

170926-R03

Grout mixing plant at P70 should be fully enclosed by three sides enclosure.

Rectification/improvement will be reported in next reporting month.

Noise

170912-R03

Handheld breaker and air compressor at P8 should be provided with NEL.

Rectification/improvement was observed during the follow-up audit session on 19 September 2017.

Waste / Chemical Management

170905-R01

Chemical labels should be provided to the chemical containers at P55 and P62 and oily water in the drip tray should be removed.

Rectification/improvement was observed during the follow-up audit session on 12 September 2017.

170905-R02

Housekeeping should be enhanced at P64.

Rectification/improvement was observed during the follow-up audit session on 12 September 2017.

170912-R01

Housekeeping should be enhanced at P21.

Rectification/improvement was observed during the follow-up audit session on 19 September 2017.

170919-R01

Dusty material and accumulated waste at P13 should be removed.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170919-R02

Oil stain at P6 and Portion C P112 should be cleared.

Rectification/improvement was observed during the follow-up audit session on 26 September 2017.

170926-R01

Accumulated construction waste at P56 should be cleared and grouting material should be cleared and well bunded to avoid runoff to sea.

Rectification/improvement will be reported in next reporting month.

170926-R02

The drip tray at P56 should be plugged and oily water and oil stain should be cleared as chemical waste.

Rectification/improvement will be reported in next reporting month.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

12/9/2017

N/A(1)

N/A(1)

Remark:     N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 6076m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.