9.1
Major site activities for the coming
reporting month will include:
WA4
¡P
Establishment
for Asphalt Plant
Ancillary and Associated Facilities
¡P
Breaking off
the concrete footings for reinstatement of slope underneath the deck
¡P
Reinstatement
of sloping seawall
¡P
Installation
of precast parapet facial panel
¡P
Construction
of median and side barriers
¡P
Construction
of longitudinal stitching
¡P
Sealing of
deck openings and preparation deck surface for waterproofing
¡P
Installation
of fire main
¡P
Erection of
sign gantry
¡P
Installation
of stormwater drainage
¡P
Site
clearance / formation work to reinstatement of SPR
¡P
Fill slope
and roadworks for CLKSR realignment
¡P
Installation
of carrier drains
¡P
Installation
of watermain
¡P
Laying of
asphalt pavement
E&M Works
¡P
E&M
ducting installation
¡P
E&M works
inside SHT building
¡P
Street light
cables and poles installation
¡P
Cable hanger
installation
¡P
Construction
of Load Centre
¡P
Optic fibre cable laying works
¡P
LV and HV
cable laying works
¡P
Cable tray
installation
Marine Viaduct (P0 to P80)
Deck Erection
¡P
Dismantling
works
¡P
Stitching
works
¡P
Movement
joints installation
External Prestressing
Tendon Installation
Internal Prestressing
Grouting
Turnaround Facilities
¡P
Casting at
top slab for longitudinal stich
¡P
Petrol
interceptor rebar fixing
¡P
Erection of
falsework and formwork
¡P
Wingslab falsework erection
¡P
Sling
platform erection
¡P
Grouting
bearing plinth
¡P
Load transfer
on bearing
¡P
Concrete
stitching
¡P
Erect 4
number of Corner Beams
9.2
The tentative environmental monitoring
schedule for the next month is shown in Appendix
D.
9.3
A tentative construction programme
is provided in Appendix A.