9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

¡P             Establishment for Asphalt Plant

 

Ancillary and Associated Facilities

¡P             Breaking off the concrete footings for reinstatement of slope underneath the deck

¡P             Reinstatement of sloping seawall

¡P             Installation of precast parapet facial panel

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Sealing of deck openings and preparation deck surface for waterproofing

¡P             Installation of fire main

¡P             Erection of sign gantry

¡P             Installation of stormwater drainage

¡P             Site clearance / formation work to reinstatement of SPR

¡P             Fill slope and roadworks for CLKSR realignment

¡P             Installation of carrier drains

¡P             Installation of watermain

¡P             Laying of asphalt pavement

 

E&M Works

¡P             E&M ducting installation

¡P             E&M works inside SHT building

¡P             Street light cables and poles installation

¡P             Cable hanger installation

¡P             Construction of Load Centre

¡P             Optic fibre cable laying works

¡P             LV and HV cable laying works

¡P             Cable tray installation

 

Marine Viaduct (P0 to P80)

 

Deck Erection

¡P             Dismantling works

¡P             Stitching works

¡P             Movement joints installation

 

External Prestressing Tendon Installation

Internal Prestressing Grouting

Turnaround Facilities

¡P             Casting at top slab for longitudinal stich

¡P             Petrol interceptor rebar fixing

¡P             Erection of falsework and formwork

¡P             Wingslab falsework erection

¡P             Sling platform erection

¡P             Grouting bearing plinth

¡P             Load transfer on bearing

¡P             Concrete stitching

¡P             Erect 4 number of Corner Beams

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.