2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
¡P
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan,
provisioning of a compensatory marine radar, and provisioning of security
systems; and
¡P
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) ¡V Cinotech
Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site activities
undertaken in the reporting month included:
Ancillary and Associated Facilities
(a) P115 & P114 interface
area - Breaking off the concrete footings for reinstatement of slope underneath
the deck is in progress;
(b) Reinstatement of sloping
seawall at P94 to P90 and P84 to P87 are in progress;
(c) The precast parapet facial
panel progress is summarized as follows:
Item |
Number in this month |
Cumulative No. of Precast Parapet
Completed (up to 28th of month) |
Precast Parapet Facial
Panel Casting |
19 |
6813 |
Precast Parapet Facial
Panel Installation |
473 |
5656 |
In-situ concreting works |
1130 |
13517 |
(d) The central barrier progress
is summarized as follows:
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of month) |
Central barrier (precast
method) |
Precast |
52 |
5834 |
Installation |
1099 |
4798 |
|
Central barrier (precast
+ in-situ method) |
In-fill concreting # |
1713 |
6690 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
central barrier shall be regarded as completed.
(e) The side barrier progress is
summarized as follows:
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of month) |
Side barrier (precast
method) |
Precast |
109 |
6113 |
Installation |
732 |
5570 |
|
Side barrier (precast +
in-situ method) |
In-fill concreting # |
2273 |
15657 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
side barrier shall be regarded as completed.
(f) Construction of the
longitudinal stitching at ML7, ML9, ML12 and ML13 are in progress. Longitudinal
from ML1 to ML6 were completed;
(g) Sealing of deck openings and
preparation deck surface for waterproofing at ML7, ML10, ML11 and ML14 are in
progress;;
(h) Fire hydrants at P0, P8, P68,
P71 and P73 were installed, fire main at ML1 and ML14 are in progress;
(i) Installation of stormwater drainage for Chek Lap Kok South Road realignment;
(j) Construction of concrete
carriageway for Chek Lap Kok
South Road realignment;
(k) Site clearance/formation work
to the reinstatement of South Perimeter Road between P84 to P81 in progress.
E&M Works
(a) E&M ducting installation
at ML1 and ML11 completed;
(b) E&M ducting installation
at ML7 and ML10 continue;
(c) E&M ducting installation
at ML8 and ML9 commence;
(d) E&M ducting installation
from ML12 and ML14 continue;
(e) E&M works inside SHT
building is in progress;
(f) Cable hanger installation at
ML11 continue;
(g) Cable hanger installation at
ML12 and ML13 commence;
(h) Construction of Load Centre 5
completed;
(i) Construction of Load Centre 3
continue;
(j) Street light cables and poles
installation at ML2 to ML6 completed;
(k) Street light cables and poles
installation at ML1 continue;
(l) LV and HV cable laying works
at ML1 to ML6 and ML15 to ML19 continue;
(m) Optic fibre
laying works for the SMS scope from SHT tunnel to HMA building complete;
(n) Cable tray installation of SMS system at
ML3 and ML4 continue;
(o) Optic fibre
cable laying works at ML14 to ML19 complete;
(p) GPS pole installation
commence from ML1 to ML14.
Deck Erection
(a) P67 Dismantling Works
i)
Dismantling of RMD towers were completed and transported
to WA4;
ii)
All temporary piles were removed.
(b) Movement Joints
i)
Installation of movement joints at P29R, P37L, P74R,
P78R, P84R, P92L, P99L, P104L and P111L were completed;
ii)
Installation of movement joints at P8R, P21L,
P29L, P45R, P67R, P70R, P74R, P78R, P84L and P115C in progress;
iii)
Surface preparation (breaking temporary concrete)
prior to movement joints installation in progress.
External Prestressing Tendon Installation
Viaduct |
Activities |
Quantities |
Unit |
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
ML15R |
Threading Stressing Grouting |
108.74 18 21.15 |
T U M3 |
ML15L |
Threading Stressing Grouting |
106.26 18 21.45 |
T U M3 |
ML14R |
Threading Stressing Grouting |
116.06 16 23.04 |
T U M3 |
ML14L |
Threading Stressing Grouting |
118.55 16 23.54 |
T U M3 |
ML13R |
Threading Stressing Grouting |
122.22 16 24.27 |
T U M3 |
ML13L |
Threading Stressing Grouting |
212.71 16 24.17 |
T U M3 |
ML12R |
Threading Stressing Grouting |
166.28 26 32.99 |
T U M3 |
ML12L |
Threading Stressing Grouting |
165.41 24 32.83 |
T U M3 |
ML11R |
Threading Stressing Grouting |
164.83 24 32.72 |
T U M3 |
ML11L |
Threading Stressing Grouting |
166.74 24 33.10 |
T U M3 |
ML10R |
Threading Stressing Grouting |
121.69 16 24.17 |
T U M3 |
ML10L |
Threading Stressing Grouting |
122.16 16 24.26 |
T U M3 |
ML09R |
Threading Stressing Grouting |
140.32 32 27.73 |
T U M3 |
ML09L |
Threading Stressing Grouting |
129.46 32 25.56 |
T U M3 |
ML08R |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
ML08L |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
ML1R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
ML1L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
Internal Prestressing Grouting Progress
Viaduct |
Activities |
Quantities |
Unit |
ML19C |
Air test & Grouting |
14.09 |
M3 |
ML19R |
Air test & Grouting |
14.90 |
M3 |
ML19L |
Air test & Grouting |
13.90 |
M3 |
ML18R |
Air test & Grouting |
25.24 |
M3 |
ML18L |
Air test & Grouting |
24.76 |
M3 |
ML17R |
Air test & Grouting |
23.47 |
M3 |
ML17L |
Air test & Grouting |
23.46 |
M3 |
ML16R |
Air test & Grouting |
36.54 |
M3 |
ML16L |
Air test & Grouting |
35.46 |
M3 |
ML15R |
Air test & Grouting |
39.34 |
M3 |
ML15L |
Air test & Grouting |
39.69 |
M3 |
ML14R |
Air test & Grouting |
104.9 |
M3 |
ML14L |
Air test & Grouting |
106.55 |
M3 |
ML13R |
Air test & Grouting |
108.28 |
M3 |
ML13L |
Air test & Grouting |
107.73 |
M3 |
ML12R |
Air test & Grouting |
121.77 |
M3 |
ML12L |
Air test & Grouting |
121.00 |
M3 |
ML11R |
Air test & Grouting |
111.47 |
M3 |
ML11L |
Air test & Grouting |
112.75 |
M3 |
ML10R |
Air test & Grouting |
89.33 |
M3 |
ML10L |
Air test & Grouting |
89.59 |
M3 |
ML09R |
Air test & Grouting |
63.27 |
M3 |
ML09L |
Air test & Grouting |
57.86 |
M3 |
ML08R |
Air test & Grouting |
36.58 |
M3 |
ML08L |
Air test & Grouting |
36.56 |
M3 |
ML07R |
Air test & Grouting |
59.61 |
M3 |
ML07L |
Air test & Grouting |
60.05 |
M3 |
ML06R |
Air test & Grouting |
58.31 |
M3 |
ML06L |
Air test & Grouting |
58.31 |
M3 |
ML05R |
Air test & Grouting |
58.62 |
M3 |
ML05L |
Air test & Grouting |
58.01 |
M3 |
ML04R |
Air test & Grouting |
57.64 |
M3 |
ML04L |
Air test & Grouting |
57.69 |
M3 |
ML03R |
Air test & Grouting |
126.65 |
M3 |
ML03L |
Air test & Grouting |
127.63 |
M3 |
ML02R |
Air test & Grouting |
62.74 |
M3 |
ML02L |
Air test & Grouting |
62.74 |
M3 |
ML01R |
Air test & Grouting |
53.80 |
M3 |
ML01L |
Air test & Grouting |
53.80 |
M3 |
Turnaround Facilities
(a)
Top slab for longitudinal stitch (LHS) between box
girders was cast;
(b)
Bottom slab between BG, IB and CB (4 of 4) were
cast;
(c)
Wing slab falsework erection completed;
(d)
Wing slab formwork completed in down chainage. Rebar fixing for wing slab in progress;
(e)
All steel members of sling platform erected;
(f)
Falsework and formwork for top slab between IB and
ramp segment in progress. Rebar fixing for top slab will follow;
(g)
Rebar fixing for Insitu
beam (4 of 4) completed;
(h)
Type 3 parapet (main deck and ramp) installation
in progress;
(i)
Insitu barrier for type 3 parapet
rebar fixing in progress;
(j)
P55-P56 and P56-P57 both LHS and RHS, span tendons
stressing were completed.
Road Pavement
Road Pavement |
Total (m2) |
Monthly Workdone (m2) |
Cumulative Workdone (m2) |
Base Course |
284440 |
45155 |
169725 |
Wearing Course |
284440 |
46058 |
159239 |
Friction Course |
274688 |
0 |
0 |
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
P84-P115: GW-RS0279-17 |
06/04/2017 (00:00) |
05/10/2017 (23:00) |
Expired
on 5/10/2017 |
P84-P115: GW-RW0847-17 |
06/10/2017 (19:00) |
05/04/2018 (23:00) |
Valid |
P0-P83: GW-RS0684-17 |
09/08/2017 (19:00) |
08/02/2018 (24:00) |
Valid |
P94-P100: GW-RS0758-17 |
07/09/2017 (01:00) |
31/12/2017 (05:30) |
Valid |
PWA4: GW-RW0471-17 |
08/09/2017 (00:00) |
07/03/2018 (24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
04/06/2012 |
N/A |
Receipt acknowledged by EPD |
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A (DCVJV
site office): WT00028521-2017 |
18/07/2017 |
30/09/2022 |
Valid |
WA6B (SOR site office): WT00028841-2017 |
03/08/2017 |
31/10/2022 |
Valid |
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00023624-2016 |
17/02/2016 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
P81-P83: WT00023608-2016 |
01/04/2016 |
31/07/2020 |
Valid |
Specific Process License
(SP license) for conduct Tar and Bitumen Works |
|||
WA4: Licence
No. L-15-038(1) |
31/05/2017 |
30/05/2020 |
Valid* |
*The license holder is the
supplier, ASL and the operation of the asphalt plant has not yet been
commenced.