EXECUTIVE SUMMARY

Introduction

1.              This is the 58th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project ¡§Contract No. HY/2011/09 ¡V Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR Boundary and Scenic Hill¡¨ (hereinafter called the ¡§Contract¡¨). This report documents the findings of EM&A Works conducted in November 2017.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

*6th, *7th, 10th, 16th, 22nd and 28th November 2017

24-hr TSP Monitoring

*7th, 10th, 16th, 22nd and 28th November 2017

Noise Monitoring

1st, 7th, 17th, 23rd and 29th November 2017

Water Quality Monitoring

1st, 3rd, 6th, 8th, 10th, 13th, 15th, 17th, 20th, 22nd, 24th, 28th and 30th November 2017

Dolphin Monitoring (Line-transect Vessel Surveys)

9th and 22nd November 2017

Environmental Site Inspection

7th, 14th, 21st and 28th November 2017

Archaeological Site Inspection

12th September 2017

*1hr (2nd and 3rd hour for AMS1) & 24 hr TSP at AMS1 and AMS4 were cancelled and postponed to 7 November 2017 due to the failure of power supply from the premises. The power supply was resumed on 7 November 2017.

 


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

Total No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Total No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

0

0

24-hr TSP

0

0

0

0

0

0

Noise

Leq(30min)

0

0

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids (SS)

3

0

3

0

0

0

Dolphin Monitoring

Quarterly Analysis (September to November 2017)

1

0

1

under investigation

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month except 1-hour TSP monitoring at AMS1 (2nd and 3rd hour) and AMS4 on 6 November 2017 which was cancelled and postponed to 7 November 2017 due to the failure of power supply from the premises. The power supply was resumed on 7 November 2017. No Action/Limit Level exceedances were recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month except 24-hour TSP monitoring at AMS1 and AMS4 on 6 November 2017 which was cancelled and postponed to 7 November 2017 due to the failure of power supply from the premises. The power supply was resumed on 7 November 2017. No Action/Limit Level exceedances were recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are three Action Level and no Limit Level exceedances were recorded for suspended solids. No Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.

 

8.              According to the investigation, the exceedances are considered not due to the Contract due to the following reasons:

1)      No pollution discharge from construction activity was observed; 

2)      The exceeded results were similar or within the ranges baseline monitoring results;

3)      Sediment plume due to natural fluctuation of shallow water was observed;

4)      Adverse water quality outside the site boundary was observed while no pollution source from this Contract was observed and no construction vessel for this Contract was travelling nearby. Dispersion of sediment plume to the monitoring stations from the area outside the site boundary (i.e. works area not under and related to HY/2011/09) was also observed.

 

Dolphin Monitoring

 

9.              There was an Action Level exceedance of dolphin monitoring for the quarterly monitoring data (between September to November 2017). The exceedance will be reported and evaluation of impacts on dolphins due to construction work will be conducted in the quarterly EM&A report.

 

Complaint Log

 

10.          No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

11.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

12.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

13.          Major site activities for the coming reporting month will include:

WA4

¡P             Operation of Asphalt Plant

 

Ancillary and Associated Facilities

¡P             Breaking off the concrete footings for reinstatement of slope underneath the deck

¡P             Reinstatement of sloping seawall

¡P             Installation of precast parapet facial panel

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Sealing of deck openings and preparation deck surface for waterproofing

¡P             Installation of fire main

¡P             Erection of sign gantry

¡P             Installation of stormwater drainage

¡P             Installation of the additional pier number and information signs

¡P             Site clearance / formation work to reinstatement of SPR

¡P             Construction of concrete carriageway for Chek Lap Kok South Road realignment*

¡P             Installation of carrier drains

¡P             Installation of watermain

¡P             Laying of asphalt pavement

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

¡P             E&M ducting installation

¡P             E&M works inside SHT building

¡P             Street light cables and poles installation

¡P             Cable hanger installation

¡P             Construction of Load Centre

¡P             Optic fibre cable laying works

¡P             LV and HV cable laying works

¡P             Cable tray installation

¡P             GPS pole installation

 

Marine Viaduct (P0 to P80)

 

Deck Erection

¡P             Dismantling works

¡P             Movement joints installation

 

External Prestressing Tendon Installation

Internal Prestressing Grouting

Turnaround Facilities

¡P             Casting of wingslab

¡P             Dismantle of wingslab falsework

¡P             Sling platform dismantling

¡P             Casting of mobile telecom equipment room

¡P             Parapet installation

¡P             Installation of insitu parapet barrier

 

10m at P0

¡P             Erection of falsework for extending the wing to the utility trough

¡P             Fabrication & erection of the formwork to the central barrier

¡P             Construction of the utility trough, erect fascia panels and edge barrier