Table 7.1        Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

N/A(1)

N/A(1)

N/A(1)

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

171107-R01

Water spraying should be provided to the scrabbling works along P67-68, contractor was reminded to provide water container at every working point.

Rectification/improvement was observed during the follow-up audit session on 14 November 2017.

171107-R02

NRMM label should be provided to the equipment at P59.

Rectification/improvement was observed during the follow-up audit session on 14 November 2017.

171107-R04

Cement bags at Portion C P113 should be covered by impervious sheet.

This item was remarked as 171114-R01.

171114-R01

Cement bags at Portion C P113 should be covered by impervious sheet.

Rectification/improvement was observed during the follow-up audit session on 21 November 2017.

171121-R02

NRMM labels should be fixed at P54 and provided to the equipments at P56.

Rectification/improvement was observed during the follow-up audit session on 28 November 2017.

171128-R01

Breaking work at Portion C P112 should be provided with water spray for dust suppression.

Rectification/improvement will be reported in next reporting month.

Noise

N/A(1)

 N/A(1)

N/A(1)

Waste / Chemical Management

171107-R03

Oil stain at P59 should be cleared as chemical waste.

Rectification/improvement was observed during the follow-up audit session on 14 November 2017.

171107-R05

General waste at Portion C P113 should be stored in waste skip or removed.

This item was remarked as 171114-R02.

171114-R02

General waste at Portion C P113 should be stored in waste skip or removed.

Rectification/improvement was observed during the follow-up audit session on 21 November 2017.

171121-R01

Chemical containers at P54 should be provided with proper chemical labels and drip tray.

Rectification/improvement was observed during the follow-up audit session on 28 November 2017.

171121-R03

Housekeeping at P56 should be enhanced.

Rectification/improvement was observed during the follow-up audit session on 28 November 2017.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

12/9/2017

N/A(1)

N/A(1)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.