7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 7th, 14th, 21st and 28th November 2017 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 21st November 2017. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 17th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 12th September 2017 and next inspection will be conducted in December 2017.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

N/A(1)

N/A(1)

N/A(1)

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

171107-R01

Water spraying should be provided to the scrabbling works along P67-68, contractor was reminded to provide water container at every working point.

Rectification/improvement was observed during the follow-up audit session on 14 November 2017.

171107-R02

NRMM label should be provided to the equipment at P59.

Rectification/improvement was observed during the follow-up audit session on 14 November 2017.

171107-R04

Cement bags at Portion C P113 should be covered by impervious sheet.

This item was remarked as 171114-R01.

171114-R01

Cement bags at Portion C P113 should be covered by impervious sheet.

Rectification/improvement was observed during the follow-up audit session on 21 November 2017.

171121-R02

NRMM labels should be fixed at P54 and provided to the equipments at P56.

Rectification/improvement was observed during the follow-up audit session on 28 November 2017.

171128-R01

Breaking work at Portion C P112 should be provided with water spray for dust suppression.

Rectification/improvement will be reported in next reporting month.

Noise

N/A(1)

 N/A(1)

N/A(1)

Waste / Chemical Management

171107-R03

Oil stain at P59 should be cleared as chemical waste.

Rectification/improvement was observed during the follow-up audit session on 14 November 2017.

171107-R05

General waste at Portion C P113 should be stored in waste skip or removed.

This item was remarked as 171114-R02.

171114-R02

General waste at Portion C P113 should be stored in waste skip or removed.

Rectification/improvement was observed during the follow-up audit session on 21 November 2017.

171121-R01

Chemical containers at P54 should be provided with proper chemical labels and drip tray.

Rectification/improvement was observed during the follow-up audit session on 28 November 2017.

171121-R03

Housekeeping at P56 should be enhanced.

Rectification/improvement was observed during the follow-up audit session on 28 November 2017.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

12/9/2017

N/A(1)

N/A(1)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 7762m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.