9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

¡P             Operation of Asphalt Plant

 

Ancillary and Associated Facilities

¡P             Breaking off the concrete footings for reinstatement of slope underneath the deck

¡P             Reinstatement of sloping seawall

¡P             Installation of precast parapet facial panel

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Sealing of deck openings and preparation deck surface for waterproofing

¡P             Installation of fire main

¡P             Erection of sign gantry

¡P             Installation of stormwater drainage

¡P             Installation of the additional pier number and information signs

¡P             Site clearance / formation work to reinstatement of SPR

¡P             Construction of concrete carriageway for Chek Lap Kok South Road realignment*

¡P             Installation of carrier drains

¡P             Installation of watermain

¡P             Laying of asphalt pavement

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

¡P             E&M ducting installation

¡P             E&M works inside SHT building

¡P             Street light cables and poles installation

¡P             Cable hanger installation

¡P             Construction of Load Centre

¡P             Optic fibre cable laying works

¡P             LV and HV cable laying works

¡P             Cable tray installation

¡P             GPS pole installation

 

Marine Viaduct (P0 to P80)

 

Deck Erection

¡P             Dismantling works

¡P             Movement joints installation

 

External Prestressing Tendon Installation

Internal Prestressing Grouting

Turnaround Facilities

¡P             Casting of wingslab

¡P             Dismantle of wingslab falsework

¡P             Sling platform dismantling

¡P             Casting of mobile telecom equipment room

¡P             Parapet installation

¡P             Installation of insitu parapet barrier

 

10m at P0

¡P             Erection of falsework for extending the wing to the utility trough

¡P             Fabrication & erection of the formwork to the central barrier

¡P             Construction of the utility trough, erect fascia panels and edge barrier

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.