9.1
Major site activities for the coming reporting month will include:
WA4
¡P
Operation of Asphalt Plant
Ancillary
and Associated Facilities
¡P
Breaking off the concrete footings for
reinstatement of slope underneath the deck
¡P
Reinstatement of sloping seawall
¡P
Installation of precast parapet facial panel
¡P
Construction of median and side barriers
¡P
Construction of longitudinal stitching
¡P
Sealing of deck openings and preparation deck
surface for waterproofing
¡P
Installation of fire main
¡P
Erection of sign gantry
¡P
Installation of stormwater
drainage
¡P
Installation of the additional pier number and
information signs
¡P
Site clearance / formation work to
reinstatement of SPR
¡P
Construction of concrete carriageway for Chek Lap Kok South Road
realignment*
¡P
Installation of carrier drains
¡P
Installation of watermain
¡P
Laying of asphalt pavement
Note:
*Minor Modification Works:-
¡PShifting the bus stop location;
¡PShifting the old alignment near
P109 southward; and
¡PRe-instating the underground
drainage with the new alignment due to the minor modification works above.
E&M
Works
¡P
E&M ducting installation
¡P
E&M works inside SHT building
¡P
Street light cables and poles installation
¡P
Cable hanger installation
¡P
Construction of Load Centre
¡P
Optic fibre cable
laying works
¡P
LV and HV cable laying works
¡P
Cable tray installation
¡P
GPS pole installation
Marine
Viaduct (P0 to P80)
Deck
Erection
¡P
Dismantling works
¡P
Movement joints installation
External
Prestressing Tendon Installation
Internal
Prestressing Grouting
Turnaround
Facilities
¡P
Casting of wingslab
¡P
Dismantle of wingslab
falsework
¡P
Sling platform dismantling
¡P
Casting of mobile telecom equipment room
¡P
Parapet installation
¡P
Installation of insitu
parapet barrier
10m
at P0
¡P
Erection of falsework for extending the wing
to the utility trough
¡P
Fabrication & erection of the formwork to
the central barrier
¡P
Construction of the utility trough, erect
fascia panels and edge barrier
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.