EXECUTIVE SUMMARY

Introduction

1.              This is the 59th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project ¡§Contract No. HY/2011/09 ¡V Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR Boundary and Scenic Hill¡¨ (hereinafter called the ¡§Contract¡¨). This report documents the findings of EM&A Works conducted in December 2017.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

4th, 8th, 14th, 20th, 26th and 30th December 2017

24-hr TSP Monitoring

4th, 8th, 14th, 20th, 26th and 30th December 2017

Noise Monitoring

5th, 15th, 21st and 27th December 2017

Water Quality Monitoring

2nd, 4th, 6th, 8th, 12th, 14th, 16th, 18th, 20th, 22nd, 26th, 28th and 30th December 2017

Dolphin Monitoring (Line-transect Vessel Surveys)

4th and 21st December 2017

Environmental Site Inspection

5th, 12th, 19th and 27th December 2017

Archaeological Site Inspection

12th December 2017

 


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

Total No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Total No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

0

0

24-hr TSP

0

0

0

0

0

0

Noise

Leq(30min)

0

0

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids (SS)

3

1

4

0

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedances were recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedances were recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are three Action Level and one Limit Level exceedances were recorded for suspended solids. No Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.

 

8.              According to the investigation, the exceedances are considered not due to the Contract due to the following reasons:

1)      No pollution discharge from construction activity was observed; 

2)      Control Station value already exceeded either the Baseline Action or Limit Levels;

3)      Adverse water quality outside the site boundary was observed while no pollution source from this Contract was observed and no construction vessel for this Contract was travelling nearby. Dispersion of sediment plume to the monitoring stations from the area outside the site boundary (i.e. works area not under and related to HY/2011/09) was also observed.

 

Complaint Log

 

9.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

¡P             Operation of Asphalt Plant

 

Ancillary and Associated Facilities

¡P             Breaking off the concrete footings for reinstatement of slope underneath the deck

¡P             Reinstatement of sloping seawall

¡P             Installation of precast parapet facial panel

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Sealing of deck openings and preparation deck surface for waterproofing

¡P             Installation of fire hydrants and fire main

¡P             Installation of utility trough covers

¡P             Erection of sign gantry

¡P             Installation of the additional pier number and information signs

¡P             Installation of the headroom sign and vessel length restriction sign

¡P             Installation of the height restriction sign

¡P             Site clearance / formation work to reinstatement of SPR

¡P             Construction of concrete carriageway for Chek Lap Kok South Road realignment*

¡P             Installation of carrier drains

¡P             Installation of watermain

¡P             Laying of asphalt pavement

¡P             Fill slope and road works for Chek Lap Kok South Road realignment*

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

¡P             E&M ducting installation

¡P             E&M works inside SHT building

¡P             Street light cables and poles installation

¡P             Cable hanger installation

¡P             LV and HV cable laying works

¡P             Cable tray installation of SMS system

¡P             Cable laying works for HKPF

¡P             GPS pole installation

¡P             Installation of electrical sliding barrier

¡P             Installation of pile cap lighting

¡P             Installation of radar at radar platform

 

Removal of Temporary works at P68 - P70

Deck Erection

¡P             Movement joints installation

 

Turnaround Facilities

¡P             Casting of wingslab

¡P             Casting of roof finishing and ground level finish of mobile telecom equipment room

¡P             Apply waterproof membrane for mobile telecom equipment room

¡P             Dismantling of sling platform, box girder support tower and extended platform

¡P             Installation of Type K1 Kerb for traffic island

¡P             Parapet installation

 

10m at P0

¡P             Construction of central barrier and side barriers

¡P             Construction of the utility trough