7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 5th, 12th, 19th and 27th December 2017 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 19th December 2017. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 17th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 12th December 2017 and next inspection will be conducted in March 2018.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

N/A(1)

N/A(1)

N/A(1)

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

171205-R02

Water spraying should be provided to the scrabbling works at P57 for dust suppression.

Rectification/improvement was observed during the follow-up audit session on 12 December 2017.

171212-R03

Cement bags at P113 Portion C should be covered by impervious sheet.

Rectification/improvement was observed during the follow-up audit session on 27 December 2017.

171219-R02

Dusty material at P55 should be covered by impervious sheet or removed.

This item was remarked as 171227-R02.

171219-R03

NRMM label should be provided to the generator at P56 and replaced on the equipment at P57.

This item was remarked as 171227-R03.

171227-R02

Dusty material at P55 should be covered by impervious sheet or removed.

Rectification/improvement will be reported in next reporting month.

171227-R03

NRMM label should be replaced on the generator at P57 and WA4.

Rectification/improvement will be reported in next reporting month.

Noise

N/A(1)

 N/A(1)

N/A(1)

Waste / Chemical Management

171205-R01

Housekeeping should be enhanced at P56.

Rectification/improvement was observed during the follow-up audit session on 12 December 2017.

171205-R03

Chemical containers at P55 should be provided with proper chemical label and drip tray.

Rectification/improvement was observed during the follow-up audit session on 12 December 2017.

171212-R01

Oil stain at P106 Portion C should be cleared as chemical waste.

Rectification/improvement was observed during the follow-up audit session on 27 December 2017.

171212-R02

Housekeeping at P111-112 Portion C should be enhanced.

Rectification/improvement was observed during the follow-up audit session on 27 December 2017.

171219-R01

Housekeeping at P55 should be enhanced.

This item was remarked as 171227-R01.

171227-R01

Housekeeping at P56 should be enhanced.

Rectification/improvement will be reported in next reporting month.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

12/12/2017

N/A(1)

N/A(1)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 2659m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.